Given the following cash flows for a capital project, calculate the NPV and IRR. The required rate of return is 8 percent
Cash Flows Year 0$-50825 Year 1 $18550 Year 2 $11350 Year 3 $20900 Year 4 $9200 Year 5 $4250
The NPV of a project is the PV of the outflows minus the PV of the inflows.
NPV = -$50825 + $18550/1.08 + $11350/1.082 + $20900/1.083 + $9200/1.084 + $4250/1.085
NPV = $2,327.57
The IRR is the interest rate that makes the NPV of the project equal to zero. So, the equation that defines the IRR for this project is:
0 = -$50825 + $18550/(1 + IRR) + $11350/(1 + IRR)2 + $20900/(1 + IRR)3 + $9200/(1 + IRR)4 + $4250/(1 + IRR)5
IRR = 10.04%
Given the following cash flows for a capital project, calculate the NPV and IRR. The required...
Given the following cash flows for a capital project, calculate the Payback period, NPV, PI, IRR, and MIRR. The required rate of return is 8 percent. Year CF 0 $(50,000.00) 1 $15,000.00 2 $15,000.00 3 $15,000.00 4 $15,000.00 5 $5,000.00
1. Given the following set of cash flows for a project, calculate the NPV, PI, IRR, MIRR, Payback, Discounted Payback and Accounting Rate of Return. Assume a cost of capital of 10%. Assuming that this is an independent project, should the project be accepted? Why or why not? (20 pts.) Year Cash Flow Net Profit Depreciation 0 -$125,000 1 $22,000 $15,000 $10,000 2 $58,000 $43,000 $25,000 3 -$30,000 $24,000 $21,000 4 $35,000 $28,000 $18,000 5 $28,000 $20,000 $15,000 6 $60,000 ...
Calculate the NPV given the following cash flows, if the appropriate required rate of return is 9 percent. Should the project be accepted? What is the project's NPV? YEAR CASH FLOWS 0 -40,000 1 20,000 2 20,000 3 15,000 4 15,000 5 30,000 6 30,000
(NPV calculation) Calculate the NPV given the following cash flows, __, if the appropriate required rate of return is 8 percent. Should the project be accepted? What is the project's NPV? $ (Round to the nearest cent.) YEAR CASH FLOWS 0 −$90,000 1 30,000 2 30,000 3 25,000 4 25,000 5 10,000 6 10,000 (Click on the icon located on the top-right corner of the data table above in order to copy its contents into a spreadsheet.) PrintDone
Calculate the NPV given the following cash flows, if the appropriate required rate of return is 12 percent. Should the project be accepted? YEAR CASH FLOWS 0 -40000 1 20000 2 20000 3 15000 4 15000 5 10000 6 10000
(NPV calculation) Calculate the NPV given the following free cash flows, YEAR CASH FLOWS 0 -50,000 1 30,000 2 30,000 3 30,000 4 -30,000 5 30,000 6 30,000 if the appropriate required rate of return is 12 percent. Should the project be accepted? What is the project's NPV?
Given a project with the following cash flows and a cost of capital of 9%. Calculate the NPV, IRR, MIRR, and PI. For each of the four calculations, give a brief interpretation of what it measures and how it should be used to evaluate a project. Should the project be accepted? Why or why not? Time Period Cash Flow 0 -$200,000 1 $50,000 2 $70,000 3 -$80,000 4 $75,000 5 $100,000 6 $120,000...
(Related to Checkpoint 12.1) (Comprehensive problem-calculating project cash flows, NPV, PI, and IRR) Traid Winds Corporation, a firm in the 30 percent marginal tax bracket with a required rate of return or discount rate of 10 percent, is considering a new project. This project involves the introduction of a new product. The project is expected to last 5 years and then, because this is somewhat of a fad product, it will be terminated. Given the following information, determine the free...
(Related to Checkpoint 12.1) (Comprehensive problem-calculating project cash flows, NPV, PI, and IRR) Traid Winds Corporation, a firm in the 30 percent marginal tax bracket with a required rate of return or discount rate of 10 percent, is considering a new project. This project involves the introduction of a new product. The project is expected to last 5 years and then, because this is somewhat of a fad product, it will be terminated. Given the following information, determine the free...
s. Understanding the NPV profile Aa Aa If an independent project with conventional, or normal, cash flows is being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree. Projects W and X are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars) Year Project W Project x 800 0 - $1,500 -$1,000 $200 $350 600 Project X 2 $350 $500 $400 $600 400 4 $600 $750 Project W 200...