Question

Calculate the NPV given the following cash​ flows, if the appropriate required rate of return is...

Calculate the NPV given the following cash​ flows, if the appropriate required rate of return is

9 percent. Should the project be​ accepted?

What is the​ project's NPV​?

YEAR   CASH FLOWS
0   -40,000
1   20,000
2   20,000
3   15,000
4   15,000
5   30,000
6   30,000

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Year Cash Flows Discount Factor Discounted cash Flows
0       (40,000) 1                (40,000)
1         20,000 0.91743                 18,349
2         20,000 0.84168                 16,834
3         15,000 0.77218                 11,583
4         15,000 0.70843                 10,626
5         30,000 0.64993                 19,498
6         30,000 0.59627                 17,888
Net Present Value                54,777
The project have positive NPV, so the project should be accepted
Add a comment
Know the answer?
Add Answer to:
Calculate the NPV given the following cash​ flows, if the appropriate required rate of return is...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • ​(NPV calculation​) Calculate the NPV given the following cash​ flows, __​, if the appropriate required rate...

    ​(NPV calculation​) Calculate the NPV given the following cash​ flows, __​, if the appropriate required rate of return is 8 percent. Should the project be​ accepted? What is the​ project's NPV​? ​$  ​(Round to the nearest​ cent.) YEAR CASH FLOWS    0 −​$90,000    1      30,000    2      30,000    3      25,000    4      25,000    5      10,000    6      10,000 ​(Click on the icon located on the​ top-right corner of the data table above in order to copy its contents into a spreadsheet.​) PrintDone

  • Calculate the NPV given the following cash​ flows, if the appropriate required rate of return is...

    Calculate the NPV given the following cash​ flows, if the appropriate required rate of return is 12 percent. Should the project be​ accepted? YEAR   CASH FLOWS 0   -40000 1   20000 2   20000 3   15000 4   15000 5   10000 6   10000

  • (NPV calculation​) Calculate the NPV given the following free cash​ flows, YEAR   CASH FLOWS 0   -50...

    (NPV calculation​) Calculate the NPV given the following free cash​ flows, YEAR   CASH FLOWS 0   -50,000 1   30,000 2   30,000 3   30,000 4   -30,000 5   30,000 6   30,000 if the appropriate required rate of return is 12 percent. Should the project be​ accepted? What is the​ project's NPV​?

  • 1. Given the following set of cash flows for a project, calculate the NPV, PI, IRR,...

    1. Given the following set of cash flows for a project, calculate the NPV, PI, IRR, MIRR, Payback, Discounted Payback and Accounting Rate of Return. Assume a cost of capital of 10%. Assuming that this is an independent project, should the project be accepted? Why or why not? (20 pts.) Year                Cash Flow                 Net Profit                   Depreciation 0                    -$125,000 1                    $22,000                     $15,000                      $10,000 2                    $58,000                     $43,000                      $25,000 3                    -$30,000                   $24,000                      $21,000 4                    $35,000                     $28,000                      $18,000 5                    $28,000                     $20,000                      $15,000 6                    $60,000                     ...

  • Given the following cash flows for a capital project, calculate the NPV and IRR. The required...

    Given the following cash flows for a capital project, calculate the NPV and IRR. The required rate of return is 8 percent Cash Flows Year 0$-50825 Year 1 $18550 Year 2 $11350 Year 3 $20900 Year 4 $9200 Year 5 $4250

  • Given the following cash flows for two mutually exclusive projects, and a required rate of return...

    Given the following cash flows for two mutually exclusive projects, and a required rate of return of 12%, which of the following statements is true? Year 0 1 Project A -580,000 290,000 290,000 150,000 150,000 2 3 Project B -580,000 130,000 130,000 230.000 230,000 230.000 115,000 4 5 6 O Both projects should be accepted because both have a positive NPV (and EAA). O Project B should be accepted because it has the highest EAA. O Project B should be...

  • What is the projects NPV? Should they accept the project? calculation) Calculate the NPV given the...

    What is the projects NPV? Should they accept the project? calculation) Calculate the NPV given the following cash flows, EB. if the appropnate required rate of return is 14 percent. Should the project be accepted? What is the project's NPV 扣(Round to the nearest cent) i Data Table CASH FLOWS $50,000 35,000 35,000 35,000 -35,000 35,000 35,000

  • Given the following cash flows for a capital project, calculate the Payback period, NPV, PI, IRR,...

    Given the following cash flows for a capital project, calculate the Payback period, NPV, PI, IRR, and MIRR. The required rate of return is 8 percent.                 Year                                  CF 0 $(50,000.00) 1 $15,000.00 2 $15,000.00 3 $15,000.00 4 $15,000.00 5 $5,000.00

  • please include parts a - d , thanks (NPV, PI, and IRR calculations) Fijisawa Inc. is...

    please include parts a - d , thanks (NPV, PI, and IRR calculations) Fijisawa Inc. is considering a major expansion of its product line and has estimated the following cash flows associated with such an expansion. The initial outlay would be $2,000,000, and the project would generate incremental free cash flows of $550,000 per year for 6 years. The appropriate required rate of return is 9 percent. a. Calculate the NPV b. Calculate the Pl c. Calculate the IRR. d....

  • ​(NPV with varying required rates of return​) Gubanich Sportswear is considering building a new factory to...

    ​(NPV with varying required rates of return​) Gubanich Sportswear is considering building a new factory to produce aluminum baseball bats. This project would require an initial cash outlay of ​$4,000,000 and would generate annual free cash inflows of ​$1,200,000 per year for 7 years. Calculate the​ project's NPV ​given: a. A required rate of return of 9 percent b. A required rate of return of 11 percent c. A required rate of return of 13 percent d. A required rate...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT