Calculate the NPV given the following cash flows, if the appropriate required rate of return is
9 percent. Should the project be accepted?
What is the project's NPV?
YEAR CASH FLOWS
0 -40,000
1 20,000
2 20,000
3 15,000
4 15,000
5 30,000
6 30,000
Year | Cash Flows | Discount Factor | Discounted cash Flows |
0 | (40,000) | 1 | (40,000) |
1 | 20,000 | 0.91743 | 18,349 |
2 | 20,000 | 0.84168 | 16,834 |
3 | 15,000 | 0.77218 | 11,583 |
4 | 15,000 | 0.70843 | 10,626 |
5 | 30,000 | 0.64993 | 19,498 |
6 | 30,000 | 0.59627 | 17,888 |
Net Present Value | 54,777 | ||
The project have positive NPV, so the project should be accepted |
Calculate the NPV given the following cash flows, if the appropriate required rate of return is...
(NPV calculation) Calculate the NPV given the following cash flows, __, if the appropriate required rate of return is 8 percent. Should the project be accepted? What is the project's NPV? $ (Round to the nearest cent.) YEAR CASH FLOWS 0 −$90,000 1 30,000 2 30,000 3 25,000 4 25,000 5 10,000 6 10,000 (Click on the icon located on the top-right corner of the data table above in order to copy its contents into a spreadsheet.) PrintDone
Calculate the NPV given the following cash flows, if the appropriate required rate of return is 12 percent. Should the project be accepted? YEAR CASH FLOWS 0 -40000 1 20000 2 20000 3 15000 4 15000 5 10000 6 10000
(NPV calculation) Calculate the NPV given the following free cash flows, YEAR CASH FLOWS 0 -50,000 1 30,000 2 30,000 3 30,000 4 -30,000 5 30,000 6 30,000 if the appropriate required rate of return is 12 percent. Should the project be accepted? What is the project's NPV?
1. Given the following set of cash flows for a project, calculate the NPV, PI, IRR, MIRR, Payback, Discounted Payback and Accounting Rate of Return. Assume a cost of capital of 10%. Assuming that this is an independent project, should the project be accepted? Why or why not? (20 pts.) Year Cash Flow Net Profit Depreciation 0 -$125,000 1 $22,000 $15,000 $10,000 2 $58,000 $43,000 $25,000 3 -$30,000 $24,000 $21,000 4 $35,000 $28,000 $18,000 5 $28,000 $20,000 $15,000 6 $60,000 ...
Given the following cash flows for a capital project, calculate the NPV and IRR. The required rate of return is 8 percent Cash Flows Year 0$-50825 Year 1 $18550 Year 2 $11350 Year 3 $20900 Year 4 $9200 Year 5 $4250
Given the following cash flows for two mutually exclusive projects, and a required rate of return of 12%, which of the following statements is true? Year 0 1 Project A -580,000 290,000 290,000 150,000 150,000 2 3 Project B -580,000 130,000 130,000 230.000 230,000 230.000 115,000 4 5 6 O Both projects should be accepted because both have a positive NPV (and EAA). O Project B should be accepted because it has the highest EAA. O Project B should be...
What is the projects NPV? Should they accept the project? calculation) Calculate the NPV given the following cash flows, EB. if the appropnate required rate of return is 14 percent. Should the project be accepted? What is the project's NPV 扣(Round to the nearest cent) i Data Table CASH FLOWS $50,000 35,000 35,000 35,000 -35,000 35,000 35,000
Given the following cash flows for a capital project, calculate the Payback period, NPV, PI, IRR, and MIRR. The required rate of return is 8 percent. Year CF 0 $(50,000.00) 1 $15,000.00 2 $15,000.00 3 $15,000.00 4 $15,000.00 5 $5,000.00
please include parts a - d , thanks (NPV, PI, and IRR calculations) Fijisawa Inc. is considering a major expansion of its product line and has estimated the following cash flows associated with such an expansion. The initial outlay would be $2,000,000, and the project would generate incremental free cash flows of $550,000 per year for 6 years. The appropriate required rate of return is 9 percent. a. Calculate the NPV b. Calculate the Pl c. Calculate the IRR. d....
(NPV with varying required rates of return) Gubanich Sportswear is considering building a new factory to produce aluminum baseball bats. This project would require an initial cash outlay of $4,000,000 and would generate annual free cash inflows of $1,200,000 per year for 7 years. Calculate the project's NPV given: a. A required rate of return of 9 percent b. A required rate of return of 11 percent c. A required rate of return of 13 percent d. A required rate...