Materials Price Variance shows a debit balance of 25000 which implies Material Prices have increased and are higher than what was set as standard at the beginning of the year.
Material Quantity Variance shows a credit balance of 9000 which implies lower Materials are being consumed for production than what was set as standard at the beginning of the year.
Labor Rate Variance shows a credit balance of 30000 which implies labor rates have decreased than what was set as standard at the beginning of the year.
Labor Efficiency Variance shows a credit balance of 7500 which implies labor efficiency has increased than what was set as standard at the beginning of the year.
3-12 retrieve the stanudlu cu Using variance analysis and interpretation Last year, Endicott Corp. adopted a...
Using variance analysis and interpretation Last year, Endicott Corp. adopted a standard cost system. Labor standards were set on the basis of time studies and prevailing wage rates. Materials standards were determined from materials specifications and the prices then in effect. On June 30, the end of the current fiscal year, a partial trial bal- ance revealed the following: 30,000 Debit Credit Materials Price Variance.......... 25,000 Materials Quantity Variance... 9,000 Labor Rate Variance. .......... Labor Efficiency Variance...... Standards set at...
Problem 10-9 Comprehensive Variance Analysis (LO10-1, LO10-2, LO10-3] Marvel Parts, Inc., manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 1,000 hours each month to produce 2,000 sets of covers. The standard costs associated with...
Problem 10-9 Comprehensive Variance Analysis (LO10-1, LO10-2, LO10-3] Marvel Parts, Inc., manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 1,020 hours each month to produce 2,040 sets of covers. The standard costs associated with...
Problem 10-9 Comprehensive Variance Analysis (LO10-1, LO10-2, LO10-3] Marvel Parts, Inc., manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 990 hours each month to produce 1,980 sets of covers. The standard costs associated with...
Problem 10-9 (Algo) Comprehensive Variance Analysis (LO10-1, LO10-2, LO10-3] Marvel Parts, Inc., manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 1,015 hours each month to produce 2,030 sets of covers. The standard costs associated...
Problem 10-9 Comprehensive Variance Analysis (LO10-1, LO10-2, LO10-3] Marvel Parts, Inc., manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 995 hours each month to produce 1,990 sets of...
Problem 10-9 (Algo) Comprehensive Variance Analysis (LO10-1, LO10-2, LO10-3] Marvel Parts, Inc., manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 1,005 hours each month to produce 2,010 sets of covers. The standard costs associated...
Problem 10-9 Comprehensive Variance Analysis (LO10-1, LO10-2, LO10-3] Marvel Parts, Inc., manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 1,030 hours each month to produce 2,060 sets of covers. The standard costs associated with...
Problem 10-9 (Algo) Comprehensive Variance Analysis (LO10-1, LO10-2, LO10-3) Marvel Parts, Inc., manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 995 hours each month to produce 1,990 sets of covers. The standard costs associated...
Problem 10-9 Comprehensive Variance Analysis [LO10-1, LO10-2, LO10-3 Marvel Parts, Inc., manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 1,045 hours each month to produce 2,090 sets of covers. The standard costs associated with...