Question

(a) What would the company’s budget need to be to fund all 7 projects?

(b) What projects would be funded if the company could get a return on its money of 15% through other means?

(c) What other, non-financial factors, might lead the company to decide to fund one or more of the projects with lower rates of return?

Project $0 N (years) First Cost $10,000 $20,000 $30,000 $40,000 $35,000 $25,000 $20,000 Annual Benefits Salvage Value $2,500

0 0
Add a comment Improve this question Transcribed image text
Answer #1

(a): To fund all 7 projects the company will need an amount = sum of all first costs i.e. the initial investment. Thus amount = 10000+20000+30000+40000+35000+25000+20000

= $180,000

(b): Here hurdle rate is 15% and we will determine IRR of all the projects using a trial and error approach. It should be noted that IRR is the rate which makes the NPV as nil.

IRR
Project 1 21.41%
Project 2 13.53%
Project 3 10.27%
Project 4 9.93%
Project 5 8.36%
Project 6 18.63%
Project 7 18.97%

Thus projects 1, 6 and 7 will be funded as the rate of return for these projects are greater than 15%.

IRR computation for project 1 is shown below for your reference. In the same manner IRR of all other projects were computed:

Year Cash flow IRR 1+r PV = Cash flow/(1+r)^n Type of flow
0 - 10,000.00 21.41%    1.214065 -                              10,000.00 First cost
                1      2,500.00                                   2,059.20 Annual benefits
                2      2,500.00                                   1,696.12 Annual benefits
                3      2,500.00                                   1,397.06 Annual benefits
                4      2,500.00                                   1,150.73 Annual benefits
                5      2,500.00                                      947.83 Annual benefits
                6      2,500.00                                      780.71 Annual benefits
                7      2,500.00                                      643.05 Annual benefits
                8      2,500.00                                      529.67 Annual benefits
                9      2,500.00                                      436.28 Annual benefits
              10      2,500.00                                      359.35 Annual benefits
              10 0                                                -   Salvage value
NPV                                           0.00

(c):  Other non-financial factors that might lead the company to decide to fund one or more of the projects with lower rate of return are factors like need for technical superiority in terms of flexibility and adaptability, operational considerations and servicing arrangements. There could be other factors like matching industry standards and good practice, staff motivation, climatic and environmental factors, and customer satisfaction levels.

Add a comment
Know the answer?
Add Answer to:
(a) What would the company’s budget need to be to fund all 7 projects? (b) What...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A company is trying to determine which projects to fund. Since the firm does not have...

    A company is trying to determine which projects to fund. Since the firm does not have the capital budget to fund all the projects, rank each by IRR. If the firm’s capital budget is $75,000, which projects will be funded? What will the firm’s MARR be? Project $0 N (years) First Cost $10,000 $20,000 $30,000 $40,000 $35,000 $25,000 $20,000 Annual Benefits Salvage Value $2,500 $3,500 $5,000 $3,600 $3,000 $4,500 $10,000 $4,000 $5,000 $5,000 $3,000 $4,200 $10,000

  • please show work for how to solve! 1. Consider the following three, mutually exclusive, projects. 1a....

    please show work for how to solve! 1. Consider the following three, mutually exclusive, projects. 1a. Using a benefit to cost ratio (BC) approach, choose the best project using a MARR of 9% and a project lifetime of each of 10 years. Your work must be shown for full credit. 40 points Initial Investment Annual Benefits (Income) Annual Cost (Maintenance) Salvage Value Project A $16,000 $3,500 $750 $2,930 Project B $13,000 $2,500 $400 $1,900 Project C $24,500 $4,500 $900 $1,780...

  • Bell Entertainment sells souvenir T-shirts at each rock concert that it sponsors. The shirts cost $7...

    Bell Entertainment sells souvenir T-shirts at each rock concert that it sponsors. The shirts cost $7 each. Any excess shirts can be returned to the manufacturer for a full refund of the purchase price. The sales price is $16 per shirt. Required a. What are the total cost of shirts and cost per shirt if sales amount to 2,000, 2,500, 3,000, 3,500, or 4,000? b. Is the cost of T-shirts a fixed or a variable cost? Complete this question by...

  • The Carpet Company’s 2019 and 2020 balance sheets included the following items: December 31 2020 2019 De...

    The Carpet Company’s 2019 and 2020 balance sheets included the following items: December 31 2020 2019 Debits Cash       $10,500 $ 4,000 Accounts receivable      8,000 9,000 Merchandise inventory      21,000 18,000 Equipment      18,000 15,000           Totals      $57,500 $46,000 Credits Accumulated depreciation, equipment      $ 4,000 $ 3,000 Accounts payable      7,000 5,000 Taxes payable      1,000 2,000 Dividends payable      1,500 0 Common stock, $10 par value      27,000 25,000 Contributed capital in excess of par, common stock      6,000 5,000 Retained earnings      11,000    6,000          ...

  • 7. Critical thinking and ethics The management accountant for the Chocolate S'more Company has prepared the...

    7. Critical thinking and ethics The management accountant for the Chocolate S'more Company has prepared the following income statement for the most current year: Chocolate Other Candy $40,000 26,000 14,000 Total Fudge $25,000 $35,000 $100,000 19,000 16,000 2,000 2,000 5.000 S7,000 Sales Cost of goods sold Contribution margin Delivery and ordering costs2,000 Rent (per sq. foot used) 3,000 Allocated corporate costs 5,000 Corporate profit 60.000 40,000 7,000 8,000 15,000 $10,000 15,000 10,000 3,000 3,000 5,000 s(1,000) $4,000 a. I pt-...

  • All four parts are independent of all other parts. Assume that all cash flows are after-tax...

    All four parts are independent of all other parts. Assume that all cash flows are after-tax cash flows: Randy Willis is considering investing in one of the following two projects. Either project will require an investment of $10,000. The expected cash flows for the two projects follow. Assume that each project is depreciable. Year      Project A        Project B 1            $ 3,000          $3,000 2               4,000             4,000 3               5,000             6,000 4            10,000            3,000 5            10,000            3,000 Wilma Golding is retiring and has the option to take her retirement as a lump sum of $225,000...

  • I'm not the best at cash budget, and need this done for my group to look...

    I'm not the best at cash budget, and need this done for my group to look over in a few hours. I have an example of how our professor did it in class and my worksheet completed by another expert with my cash budget so far. I need the calculations and boxes to be filled out for the cash budget (if there's something I'm missing or not enough information, please let me know and I can provide the information required)...

  • 1.) Projects A and B both have 5 years of life. The initial investments and cash...

    1.) Projects A and B both have 5 years of life. The initial investments and cash flows from these two projects are shown below. Year 0 1 2 3 4 5 Project A -12,300 4,500 4,000 3,500 3,000 2,500 Project B -15,000 6,000 5,000 4,000 3,200 2,400 A.) Use Data Table tool to find the NPVs of both projects when the discount rate is 10%. B.) Use Data Table tool to find the IRRs of both projects C.) Plot the...

  • economics

    . Project L and M are two projects such as roads or dams. For L, Stage L1 would be the first stage; L2 the next stage, etc. No stage can begin unless preceding stages have been completed. Thus L2 must be preceded by L1. The projects show the following patterns of costs and benefits.                           PROJECT L                                                       PROJECT M            Total Cost   Total Benefit                                    Total Cost     Total Benefit            $5,000               9,000                Stage 1              $5,000               8,000            10,000              16,000        ...

  • Selling Price = $28.00 Variable 2,000 6,000 12 Fixed Cost $20,000 20,000 20,000 30,000 30,000 30,000...

    Selling Price = $28.00 Variable 2,000 6,000 12 Fixed Cost $20,000 20,000 20,000 30,000 30,000 30,000 40,000 40,000 40,000 $ 14,000 12,000 10,000 4,000 2,000 Sales Volume 3,000 4,000 5,000 Profitability $ 31,000 $ 48,000 $ 65,000 28,000 44,000 60,000 25,000 40,000 55,000 21,000 38,000 55,000 18,000 34,000 50,000 15,000 30,000 45,000 11,000 28,000 45,000 8,000 24,000 40,000 5,000 20,000 35,000 $ 82,000 76,000 70,000 72,000 66,000 60,000 62,000 56,000 50,000 (6,000) (8,000) (10,000) Required a. Determine the sales volume,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT