Question

12) Halcyon Inc, completed Job 10B last month. The cost details of Job 10B are shown below $2,040 $90 Direct labor cost Direc
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer: B)$ 4,590

Calculations:

Direct materials cost $90
Direct labor cost $2,040
Overhead cost $2,460
Total job cost for Job 10B $4,590

*Overhead = Cost driver x Predetermined overhead rate = 75 labor hours x $32.80 = $2,460

Add a comment
Know the answer?
Add Answer to:
12) Halcyon Inc, completed Job 10B last month. The cost details of Job 10B are shown...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Iglesias, Inc. completed Job 12 on November 30. The details of Job 12 are given below:...

    Iglesias, Inc. completed Job 12 on November 30. The details of Job 12 are given below: Direct labor cost Direct materials cost Machine hours Direct labor hours Predetermined overhead allocation rate $880 $1,100 7 hours 21 hours $80 per machine hour What is the total cost of Job 12? O A. $1,980 O B. $2,540 OC. $1,660 OD. $1,440

  • Iglesias, Inc. completed Job 12 on November 30. The details of Job 12 are given below....

    Iglesias, Inc. completed Job 12 on November 30. The details of Job 12 are given below. Direct labor cost Direct materials cost Machine hours Direct labor hours Predetermined overhead allocation rate $900 $1,000 7 hours 23 hours $70 per machine hour What is the total cost of Job 12? O A. $1,490 OB. $1,900 OC. $1,390 OD. $2,390 Click to select your answer.

  • 10) Matthew's Fish Fry has a monthly target operating income of $200. Variable expenses are 40%...

    10) Matthew's Fish Fry has a monthly target operating income of $200. Variable expenses are 40% of sales and monthly fixed expenses are $1,800. What is the monthly margin of safety in dollars if the business achieve operating income goal? A) $18,000 B) $13.500 C) None of them are correct D) $12,000 11) Martin Enterprises has a predicted operating income of $100 total variable expenses are $50,000 and its total fixed expenses are $20,000. The unit contribution margins for the...

  • Job 243 was recently completed. The following data have been recorded on its job cost sheet...

    Job 243 was recently completed. The following data have been recorded on its job cost sheet $57,870 Direct materials Direct labor-hours Direct labor wage rate Machine-hours Number of units completed 495 labor-hours 11 per labor-hour 576 machine-hours 4,500 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $13 per machine- hour Required Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to 2...

  • Job 910 was recently completed. The following data have been recorded on its job cost sheet:...

    Job 910 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor wage rate Machine-hours $2,429 71 labor-hours $ 20 per labor-hour 134 machine-hours The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $21 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 910 would be:

  • Job 243 was recently completed. The following data have been recorded on its job cost sheet:...

    Job 243 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor vage rate Machine-hours Number of units completed $50,370 420 labor-hours $ 10 per labor-hour 501 machine-hours 3,000 units 4 The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $14 per machine- hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer...

  • 9. Job 593 was recently completed. The following data have been recorded on its job cost...

    9. Job 593 was recently completed. The following data have been recorded on its job cost sheet:      Direct materials $2,412   Direct labor-hours 74 labor-hours   Direct labor wage rate $    21 per labor-hour   Machine-hours 137 machine-hours     The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $22 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 593 would be:

  • Job 910 was recently completed. The following data have been recorded on its job cost sheet:...

    Job 910 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor wage rate Machine-hours $2,474 73 labor-hours $ 19 per labor-hour 134 machine-hours The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $20 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 910 would be: $3,865 $7,381 $3,861

  • Job 243 was recently completed. The following data have been recorded on its job cost sheet:...

    Job 243 was recently completed. The following data have been recorded on its job cost sheet: Direct materials $ 55,870 Direct labor-hours 475 labor-hours Direct labor wage rate $ 11 per labor-hour Machine-hours 556 machine-hours Number of units completed 4,100 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $13 per machine-hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to...

  • Job 243 was recently completed. The following data have been recorded on its job cost sheet:...

    Job 243 was recently completed. The following data have been recorded on its job cost sheet: $58,370 Direct materials Direct labor-hours 500 labor-hours Direct labor wage rate $10 per labor-hour Machine-hours 581 machine-hours Number of units completed 4,600units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate i $14 per machine-hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to 2 decimal places.)

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT