Required 1 :
JOB COST SHEET
Job 1 Job 2 Job 3
Direct materials used 6400 8400 2900
Direct labor used 9100 5600 4600
Factory overhead ( 45% * Direct materials used ) 2880 3780 1305
Total 18380 17780 8805
Required 2 :
Ending work in process inventory = Total cost of Job 1 + Total cost of Job 3 = 18380 + 8805 27185
Required 3 :
Finished goods inventory = Total cost of Job 2 17780
Add a comment
Know the answer?
Add Answer to:
need help ASAP. Thank you. QS 15-10 Manufacturing cost flows LO P1, P2, P3 On March...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • QS 15-10 Manufacturing cost flows LO P1, P2, P3 On March 1 a dressmaker starts work on three custom-designed wedding dr...

    QS 15-10 Manufacturing cost flows LO P1, P2, P3 On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 47% of direct materials costs. During the month, the jobs used direct materials as shown below. Job 1 Job 2 Job 3 Direct materials used $5,800 $7,800 $2,300 During the month, the jobs used direct labor as shown below. Jobs 1 and...

  • Help Save & Ched On March 1 a dressmaker starts work on three custom-designed wedding dresses....

    Help Save & Ched On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 53% of direct materials costs. During the month, the jobs used direct materials as shown below points Jobi Job 2 Job $5,400 57.00 $1,900 During the month, the jobs used direct labor as shown below. Jobs 1 and 3 are not finished by the end of March,...

  • On March 1 a dressmaker starts work on three custom- designed wedding dresses. The company uses...

    On March 1 a dressmaker starts work on three custom- designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 40% of direct materials costs. During the month, the jobs used direct materials as shown below. Job 1 $5 000 Job 2 $7000 Job 3 $1.500 Direct materials used During the month, the jobs used direct labor as shown below. Jobs 1 and 3 are not finished by the end...

  • Check On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses...

    Check On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 54% of direct materials costs. During the month, the jobs used direct materials as shown below. Job 1 Job 2 Job 3 $5,900 $7,900 $2,400 Direct materials used During the month, the jobs used direct labor as shown below. Jobs 1 and 3 are not finished by the end of...

  • On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job...

    On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 42% of direct materials costs. During the month, the jobs used direct materials as shown below. Job 1 Job 2 Job 3 Direct materials used $5,800 $7, 800 $2,300 During the month, the jobs used direct labor as shown below. Jobs 1 and 3 are not finished by the end of...

  • Saved Help Save & Exit Submit Check my work On March 1 a dressmaker starts work...

    Saved Help Save & Exit Submit Check my work On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 53% of direct materials costs. During the month, the jobs used direct materials as shown below. Direct materials used Job 1 Job 2 Job 3 $5,700 $7,700 $2,200 During the month, the jobs used direct labor as shown below. Jobs 1 and...

  • I need help with the whole question with a solution and explanation Please and Thank you....

    I need help with the whole question with a solution and explanation Please and Thank you. Chapter 15 Homework i Saved Help Save & Exit Submit Check my work On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 51% of direct materials costs. During the month, the jobs used direct materials as shown below. 4.44 points Job 1 Job 2...

  • On March 1 adressmaker starts work on three custom designed wedding dresses. The company uses job...

    On March 1 adressmaker starts work on three custom designed wedding dresses. The company uses job order costing and applies Overhead to each job (dress) at the rate of 5% of direct materials costs. During the month, the jobs used direct materials as shown below Direct materials used Job Job a $5,800 $7,00 Job 3 $2, SO During the month, the jobs used direct labor as shown below. but not sold by the end of March the end of March,...

  • Check my work On March 1 a dressmaker starts work on three custom-designed wedding dresses. The...

    Check my work On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 53% of direct materials costs. During the month, the jobs used direct materials as shown below. Job 1 Job 2 Job 3 $5,700 $7,700 $2,200 Direct materials used During the month, the jobs used direct labor as shown below, Jobs 1 and 3 are not finished by the...

  • Exercise 15-5 Manufacturing cost flows LO P1, P2, P3 Custom Cabinetry has one job in process...

    Exercise 15-5 Manufacturing cost flows LO P1, P2, P3 Custom Cabinetry has one job in process (Job 120) as of June 30, at that time, its job cost sheet reports direct materials of $8.000 direct labor of $3,400, and applied overhead of $2.720. Custom Cabinetry applies overhead at the rate of 80% of direct labor cost During July, Job 120 is sold on account) for $31.500. Job 121 is started and completed, and Job 122 is started and still in...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT