Help Save & Ched On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order cos
Problems each of the three jobs for March. 2. Determine the total dollar amount of Work in Process Inventory at the end of Ma
Help Sove On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing an
00. Alol party Allocates Overhead newconnect.mheducation.com/flow/connect html Chapter 2 Problems 21) Cash War (Explicit- e +
1 0
Add a comment Improve this question Transcribed image text
Answer #1

Date / 00000 RANKA Page Job cost sheet Job1 $5400 $9300 $2862 ($5400X537.) (87Y00X 53%.) Job3 91900 $3600 $1007 ($1900X53%) J

Add a comment
Know the answer?
Add Answer to:
Help Save & Ched On March 1 a dressmaker starts work on three custom-designed wedding dresses....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On March 1 a dressmaker starts work on three custom- designed wedding dresses. The company uses...

    On March 1 a dressmaker starts work on three custom- designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 40% of direct materials costs. During the month, the jobs used direct materials as shown below. Job 1 $5 000 Job 2 $7000 Job 3 $1.500 Direct materials used During the month, the jobs used direct labor as shown below. Jobs 1 and 3 are not finished by the end...

  • Check On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses...

    Check On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 54% of direct materials costs. During the month, the jobs used direct materials as shown below. Job 1 Job 2 Job 3 $5,900 $7,900 $2,400 Direct materials used During the month, the jobs used direct labor as shown below. Jobs 1 and 3 are not finished by the end of...

  • On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job...

    On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 42% of direct materials costs. During the month, the jobs used direct materials as shown below. Job 1 Job 2 Job 3 Direct materials used $5,800 $7, 800 $2,300 During the month, the jobs used direct labor as shown below. Jobs 1 and 3 are not finished by the end of...

  • On March 1 adressmaker starts work on three custom designed wedding dresses. The company uses job...

    On March 1 adressmaker starts work on three custom designed wedding dresses. The company uses job order costing and applies Overhead to each job (dress) at the rate of 5% of direct materials costs. During the month, the jobs used direct materials as shown below Direct materials used Job Job a $5,800 $7,00 Job 3 $2, SO During the month, the jobs used direct labor as shown below. but not sold by the end of March the end of March,...

  • Check my work On March 1 a dressmaker starts work on three custom-designed wedding dresses. The...

    Check my work On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 53% of direct materials costs. During the month, the jobs used direct materials as shown below. Job 1 Job 2 Job 3 $5,700 $7,700 $2,200 Direct materials used During the month, the jobs used direct labor as shown below, Jobs 1 and 3 are not finished by the...

  • QS 15-10 Manufacturing cost flows LO P1, P2, P3 On March 1 a dressmaker starts work on three custom-designed wedding dr...

    QS 15-10 Manufacturing cost flows LO P1, P2, P3 On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 47% of direct materials costs. During the month, the jobs used direct materials as shown below. Job 1 Job 2 Job 3 Direct materials used $5,800 $7,800 $2,300 During the month, the jobs used direct labor as shown below. Jobs 1 and...

  • Saved Help Save & Exit Submit Check my work On March 1 a dressmaker starts work...

    Saved Help Save & Exit Submit Check my work On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 53% of direct materials costs. During the month, the jobs used direct materials as shown below. Direct materials used Job 1 Job 2 Job 3 $5,700 $7,700 $2,200 During the month, the jobs used direct labor as shown below. Jobs 1 and...

  • need help ASAP. Thank you. QS 15-10 Manufacturing cost flows LO P1, P2, P3 On March...

    need help ASAP. Thank you. QS 15-10 Manufacturing cost flows LO P1, P2, P3 On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 45% of direct materials costs. During the month, the jobs used direct materials as shown below. 10 points Direct materials used Job 1 Job 2 Job 3 $6,400 $8,400 $2,900 8 02:55:32 During the month, the jobs...

  • I need help with the whole question with a solution and explanation Please and Thank you....

    I need help with the whole question with a solution and explanation Please and Thank you. Chapter 15 Homework i Saved Help Save & Exit Submit Check my work On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 51% of direct materials costs. During the month, the jobs used direct materials as shown below. 4.44 points Job 1 Job 2...

  • Direct material ve 36.390 10,300 2,800 8 to During the month, the Jobs used direct labor...

    Direct material ve 36.390 10,300 2,800 8 to During the month, the Jobs used direct labor as shown below. Jobs 1 and 3 are not finished by the end of March, and Job 2 is finished but not sold by the end of March Direct labor used $10,100 $4,6000),600 1. Determine the amounts of direct materials, direct labor, and factory overhead oppled that would be reported on job cost sheets for each of the three jobs for March 2. Determine...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT