Project K costs $55,000, its expected cash inflows are $15,000 per year for 11 years, and its WACC is 9%. What is the project's payback? Round your answer to two decimal places.
Payback period is the time taken for the cumulative cash flows to equal zero
Payback period = 3 + (cash flow required in year 4 for cumulative cash flows to equal zero / year 4 cash flow)
Payback period = 3 + ($10,000 / $15,000) = 3.67 years
Project K costs $55,000, its expected cash inflows are $15,000 per year for 11 years, and...
Project K costs $45,000, its expected cash inflows are $15,000 per year for 8 years, and its WACC is 11%. What is the project's MIRR? Round your answer to two decimal places. Project K costs $55,000, its expected cash inflows are $13,000 per year for 8 years, and its WACC is 7%. What is the project's discounted payback? Round your answer to two decimal places.
12-8: Payback Period Payback period Project K costs $55,000, its expected cash inflows are $15,000 per year for 9 years, and its WACC is 10%. What is the project's payback? Round your answer to two decimal places. years
Project K costs $55,000, its expected cash inflows are $13,000 per year for 8 years, and its WACC is 7%. What is the project's discounted payback? Round your answer to two decimal places.
11-8: Payback Period Payback period Project K costs $70,000, its expected cash inflows are $15,000 per year for 9 years, and its WACC is 14%. what is the project's payback? Round your answer to two decimal places. years
1.Project L costs $35,000, its expected cash inflows are $13,000 per year for 9 years, and its WACC is 9%. What is the project's NPV? Do not round intermediate calculations. Round your answer to the nearest cent. 2.Project L costs $50,011.04, its expected cash inflows are $12,000 per year for 8 years, and its WACC is 11%. What is the project's IRR? Round your answer to two decimal places 3.Project L costs $60,000, its expected cash inflows are $15,000 per...
Project L costs $55,000, its expected cash inflows are $10,000 per year for 12 years, and its WACC is 11%. What is the project's payback? Round your answer to two decimal places. ____years
11-8: Payback Period Discounted payback Project K costs $55,000, its expected cash inflows are $13,000 per year for 8 years, and its WACC is 796, what is the project's discounted payback? Round our answer to two decimal places years
Project L costs $55,000, its expected cash inflows are $11,000 per year for 7 years, and its WACC is 13%. What is the project's payback? Round your answer to two decimal places.
Project K costs $65,000, its expected cash inflows are $13,000 per year for 11 years, and its WACC is 12%. What is the project's NPV? Round your answer to the nearest cent. Project K costs $48,457.36, its expected cash inflows are $10,000 per year for 11 years, and its WACC is 12%. What is the project's IRR? Round your answer to two decimal places.
Project K costs $55,000, its expected cash inflows are $12,000 per year for 11 years, and its WACC is 14%. What is the project's NPV? Round your answer to the nearest cent.