1.Project L costs $35,000, its expected cash inflows are $13,000 per year for 9 years, and its WACC is 9%. What is the project's NPV? Do not round intermediate calculations. Round your answer to the nearest cent.
2.Project L costs $50,011.04, its expected cash inflows are $12,000 per year for 8 years, and its WACC is 11%. What is the project's IRR? Round your answer to two decimal places
3.Project L costs $60,000, its expected cash inflows are $15,000 per year for 8 years, and its WACC is 10%. What is the project's MIRR? Do not round intermediate calculations. Round your answer to two decimal places
4.Project L costs $35,000, its expected cash inflows are $15,000 per year for 8 years, and its WACC is 12%. What is the project's payback? Round your answer to two decimal places.
5.Project L costs $60,000, its expected cash inflows are $14,000 per year for 8 years, and its WACC is 13%. What is the project's discounted payback? Do not round intermediate calculations. Round your answer to two decimal places.
1.Project L costs $35,000, its expected cash inflows are $13,000 per year for 9 years, and...
4.Project L costs $35,000, its expected cash inflows are $15,000 per year for 8 years, and its WACC is 12%. What is the project's payback? Round your answer to two decimal places. 5.Project L costs $60,000, its expected cash inflows are $14,000 per year for 8 years, and its WACC is 13%. What is the project's discounted payback? Do not round intermediate calculations. Round your answer to two decimal places.
1A. Project L costs $35,000, its expected cash inflows are $9,000 per year for 8 years, and its WACC is 10%. What is the project's NPV? Round your answer to the nearest cent. Do not round your intermediate calculations. 1B. Project L costs $46,724.57, its expected cash inflows are $9,000 per year for 11 years, and its WACC is 9%. What is the project's IRR? Round your answer to two decimal places. 1C. Project L costs $65,000, its expected cash...
Project L costs $35,000, its expected cash inflows are $11,000 per year for 8 years, and its WACC is 9%. What is the project's payback? Round your answer to two decimal places. years
Project L costs $65,000, its expected cash inflows are $15,000 per year for 8 years, and its WACC is 10%. What is the project's discounted payback? Do not round intermediate calculations. Round your answer to two decimal places. _____ years
3.Project L costs $60,000, its expected cash inflows are $15,000 per year for 8 years, and its WACC is 10%. What is the project's MIRR? Do not round intermediate calculations. Round your answer to two decimal places
Project L costs $45,000, its expected cash inflows are $11,000 per year for 8 years, and its WACC is 8%. What is the project's discounted payback? Do not round intermediate calculations. Round your answer to two decimal places. ______ years
NPV Project L costs $35,000, its expected cash inflows are $13,000 per year for 10 years, and its WACC is 12%. What is the project's NPV? Round your answer to the nearest cent. Do not round your intermediate calculations.
Project L costs $65,000, its expected cash inflows are $13,000 per year for 8 years, and its WACC is 12%. What is the project's MIRR? Round your answer to two decimal places. Do not round your intermediate calculations.
PAYBACK PERIOD Project L costs $35,000, its expected cash inflows are $11,000 per year for 12 years, and its WACC is 12%. What is the project's payback? Round your answer to two decimal places. years
MIRR Project L costs $40,000, its expected cash inflows are $13,000 per year for 8 years, and its WACC is 14%, what is the project's MIRR? Round your answer to two decimal places. Do not round your intermediate calculations.