Cash flows | Year |
(40,000.000) | 0 |
13,000.000 | 1 |
13,000.000 | 2 |
13,000.000 | 3 |
13,000.000 | 4 |
13,000.000 | 5 |
13,000.000 | 6 |
13,000.000 | 7 |
13,000.000 | 8 |
Use MIRR function in Excel
MIRR = 20.00%
MIRR Project L costs $40,000, its expected cash inflows are $13,000 per year for 8 years,...
1.Project L costs $35,000, its expected cash inflows are $13,000 per year for 9 years, and its WACC is 9%. What is the project's NPV? Do not round intermediate calculations. Round your answer to the nearest cent. 2.Project L costs $50,011.04, its expected cash inflows are $12,000 per year for 8 years, and its WACC is 11%. What is the project's IRR? Round your answer to two decimal places 3.Project L costs $60,000, its expected cash inflows are $15,000 per...
Project L costs $65,000, its expected cash inflows are $13,000 per year for 8 years, and its WACC is 12%. What is the project's MIRR? Round your answer to two decimal places. Do not round your intermediate calculations.
1A. Project L costs $35,000, its expected cash inflows are $9,000 per year for 8 years, and its WACC is 10%. What is the project's NPV? Round your answer to the nearest cent. Do not round your intermediate calculations. 1B. Project L costs $46,724.57, its expected cash inflows are $9,000 per year for 11 years, and its WACC is 9%. What is the project's IRR? Round your answer to two decimal places. 1C. Project L costs $65,000, its expected cash...
MIRR Project L costs $55,000, its expected cash inflows are $10,000 per year for 8 years, and its WACC is 11%. What is the project's MIRR? Round your answer to two decimal places. Do not round your intermediate calculations. %
Project L costs $50,000, its expected cash inflows are $8,000 per year for 8 years, and its WACC is 10%. What is the project's MIRR? Round your answer to two decimal places. Do not round your intermediate calculations. %
3.Project L costs $60,000, its expected cash inflows are $15,000 per year for 8 years, and its WACC is 10%. What is the project's MIRR? Do not round intermediate calculations. Round your answer to two decimal places
Project K costs $75,000, its expected cash inflows are $13,000 per year for 8 years, and its WACC is 12%. What is the project's MIRR? Round your answer to two decimal places.
A)Project L requires an initial outlay at t = 0 of $40,000, its expected cash inflows are $15,000 per year for 9 years, and its WACC is 14%. What is the project's MIRR? Do not round intermediate calculations. Round your answer to two decimal places. B) Project L requires an initial outlay at t = 0 of $88,310, its expected cash inflows are $14,000 per year for 10 years, and its WACC is 14%. What is the project's IRR? Round...
Project L costs $65,000, its expected cash inflows are $13,000 per year for 8 years, and its WACC is 10%. What is the project's NPV? Round your answer to the nearest cent. Do not round your intermediate calculations.
Project K costs $45,000, its expected cash inflows are $15,000 per year for 8 years, and its WACC is 11%. What is the project's MIRR? Round your answer to two decimal places. Project K costs $55,000, its expected cash inflows are $13,000 per year for 8 years, and its WACC is 7%. What is the project's discounted payback? Round your answer to two decimal places.