Question

5. Tanner Company has two products: A and B. The company uses activity-based costing and has prepared the following analysis
b. $39,840 C. $40,000 d. $96,190
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answers

  • Answer #5
    Correct Answer = Option ‘C’ $ 5.00

Overhead allocated to Product A:

Activity 1

$8,000

=40000*200/1000

Activity 2

$19,467

=29200*1000/1500

Activity 3

$18,000

=180000*600/6000

Total Overhead allocated

$45,467

Units of Product A

                          9,094

Overhead cost per unit

$5.00

=$45467 / 9094 units

  • Answer #6

>Amount of Overhead applied for Activity 3
= 2490 actual activity x ($40000 overhead cost / 2500 expected activity)
= 2490 x 40000 / 2500
= $ 39,840

Correct Answer = Option ‘B’ $ 39,840

Add a comment
Know the answer?
Add Answer to:
5. Tanner Company has two products: A and B. The company uses activity-based costing and has...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. Paul Company has two products: A and B. The company uses activity-based costing. The estimated...

    1. Paul Company has two products: A and B. The company uses activity-based costing. The estimated total cost and expected activity for each of the company's three activity cost pools are as follows: Activity Cost Pool Activity 1............ Activity 2 Activity 3. Estimated Cost $22,000 $16,240 $14,600 Expected Activity Product A Product B 400 100 380 200 500 250 Total 500 580 750 The activity rate under the activity-based costing system for Activity 3 is closest to: 2. James Company...

  • 5. Matt Company uses activity-based costing. The company has two products: A and B. The annual...

    5. Matt Company uses activity-based costing. The company has two products: A and B. The annual production and sales of Product A is 8,000 units and of Product B is 6,000 units. There are three activity overhead cost pools, with estimated total overhead cost and expected activity as follows: Activity Cost Pool Expected Activity Product A Product B Total Estimated Cost $20,000 $37,000 $91,200 Activity 1... Activity 2.......... Activity 3 100 800 800 400 200 3,000 500 1,000 3,800 The...

  • Abbe Company uses activity-based costing. The company has two products: A and B. The annual production...

    Abbe Company uses activity-based costing. The company has two products: A and B. The annual production and sales of Product A is 2,200 units and of Product B is 1,250 units. There are three activity cost pools, with estimated costs and expected activity as follows: Activity Cost Pools Estimated Overhead Cost Expected Activity Product A Product B Total Activity 1 $ 66,033 1,700 1,600 3,300 Activity 2 $ 88,929 2,700 1,400 4,100 Activity 3 $ 102,486 880 860 1,740 The...

  • Selena Company has two products: A and B. The company uses activity-based costing. The estimated total...

    Selena Company has two products: A and B. The company uses activity-based costing. The estimated total cost and expected activity for each of the company's three activity cost pools are as follows: Expected Activity Activity Cost Pool Estimated Cost Product A Product B Total Activity 1 $17,600 800 300 1,100 Activity 2 12,000 500 200 700 Activity 3 26,000 800 400 1,200 The activity rate under the activity-based costing system for Activity 3 is closest to which of the following?

  • Matt Company uses activity-based costing. The company has two products: A and B. The annual production...

    Matt Company uses activity-based costing. The company has two products: A and B. The annual production and sales of Product A is 5,000 units and of Product B is 7,000 units. There are three activity cost pools, with estimated total cost and expected activity as follows: Expected Activity Activity Cost Pool Estimated Cost Product A Product B Total Activity 1 $24,000 200 400 600 Activity 2 36,000 700 200 900 Activity 3 81,200 800 3,000 3,800 The cost per unit...

  • 1.Abbe Company uses activity-based costing. The company has two products: A and B. The annual production...

    1.Abbe Company uses activity-based costing. The company has two products: A and B. The annual production and sales of Product A is 1,600 units and of Product B is 950 units. There are three activity cost pools, with estimated costs and expected activity as follows: Activity Cost Pools Estimated Overhead Cost Expected Activity Product A Product B Total Activity 1 $ 38,241 1,100 1,000 2,100 Activity 2 $ 58,551 2,100 800 2,900 Activity 3 $ 72,702 640 620 1,260 The...

  • Accola Company uses activity-based costing. The company has two products: A and B. The annual production...

    Accola Company uses activity-based costing. The company has two products: A and B. The annual production and sales of Product A is 1,100 units and of Product B is 700 units. The direct production costs (material and labour) for Product A are $110,600 and for B is $70,000. There are three activity cost pools for overhead, with estimated costs and expected activity as follows: Expected Activity Product A Product B Estimated Cost Total Activity Cost Pool Activity 1 Activity 2...

  • 7. Prohoff Company uses activity-based costing to compute product costs for external reports. The company has...

    7. Prohoff Company uses activity-based costing to compute product costs for external reports. The company has three activity cost pools and applies overhead using predetermined overhead rates for each activity cost pool. Estimated costs and activities for the current year are presented below for the three activity cost pools: Activity A Activity B Activity C Estimated Overhead Cost $117,312 $120,096 $260,648 Expected Activity 2,400 4,800 4,400 Actual costs and activities for the current year were as follows: Actual Overhead Cost...

  • Alexander Inc. uses activity-based costing. The company produces two products: Snaps and Pops. The expected annual...

    Alexander Inc. uses activity-based costing. The company produces two products: Snaps and Pops. The expected annual production of Snaps is 1200 units, while the expected annual production of Pops is 2100 units. There are three activity cost pools: Assembly, Testing, and Packing. The estimated costs and activities for each of these three activity pools follows: Expected activity Activity cost pool Estimated cost Snaps Pops Total Assembly $5648 640 1401 780 Testing $25,315 1100 6401 Packing $2301 70 155 225 17401...

  • Angora, Inc. uses activity-based costing to cost its two products: Standard and Deluxe. The company has...

    Angora, Inc. uses activity-based costing to cost its two products: Standard and Deluxe. The company has provided the following data relating to its activities: Estimated Cost Cost Pools Machine (machine-hours) Cutting (number of cuts) Sales (number of orders) $144,000 $536,000 $108,000 Estimated Activity Deluxe 7,000 Standard 1,000 3,000 Machine hours 5,000 Number of cuts 2,000 7,000 Number of orders Required: What is the activity rate for the cutting cost pool? a. If actual activity is the same as that estimated,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT