Question

A quality-control plan for the concrete in a nuclear reactor containment vessel calls for casting 6 cylinders for each batch of 10 yd poured and testing them as follows: 1 at 7 days, 1 at 14 days, 2 at 28 days, 2 more at 28 days if any of the first four cylinders is inadequate. The required strength is a function of age. If the cylinder to be tested is chosen at random from those remaining (i.e. with equal likelihoods) a)- What is the probability that all six will be tested if in fact one inadequate cylinder exists in the six? b)- If the batch will be rejected if two or more inadequate cylinders are found, what is the likelihood that it will not be rejected given that exactly two are in fact inadequate? (Rejection will lead to more expensive coring and testing of concrete in place) c)-A satisfactory concrete batch gives rise to an inadequate cylinder with probability p-0.1 there will be one or more inadequate cylinders in the six when the batch is satisfactory? (Assume independence of the quality of the individual cylinders) rejected? What is the probability that an unsatisfactory batch (in particular, say, p = 0.3) will not be rejected? Clearly a quality control plan wants to keep both these probabilities low, while also keeping the cost of testing small.please to find the question in the image. thank you

0 0
Add a comment Improve this question Transcribed image text
Answer #1

A.

P(All six will be tested) = P(Inadequate cylinder gets tested in the first 4 selected for testing)

Total ways of selecting 4 cylinders from 6 = \binom{6}{4}

Total ways of always selecting Inadequate cylinder among the 4 from the 6 = \binom{5}{3}

P(All six will be tested) = \binom{5}{3} \div \binom{6}{4}

= 2/3

B.

P(Batch will not be rejected) = P(No inadequate cylinder gets tested in the first 4 testing given that 2 are inadequate)

= \binom{4}{4} \div \binom{6}{4}

= 1/15

C.

P(Inadeqaure cylinder) = p = 0.1

P(adequate cylinder) = q = 0.9

Let X = occurence of inadequate distibution

It becomes a binomial distribution.

n = 6

P(X>=1) = 1-P(X=0)

= 1- \binom{6}{0}*0.1^{0}*0.9^{6}

=1- 0.53

= 0.47

D.

P(Inadeqaure cylinder) = p = 0.1

P(adequate cylinder) = q = 0.9

X = Inadequte cylinders

P(batch will be rejected) = P(Two or more inadequate cylinders are found)

= P(rejection|X = 2) + P(X>=3)

Since occurance of 2 inadequate cylinders does reject the batch only if all the six cylinders ar tested thus, P(X=2) has to be multiplied with probability that the particular batch is rejected.

P(X>=3) = 0.01585

P(X=2) = 0.098415

P(rejection|X = 2) = (1-1/15)*0.098415 = 0.091

P(batch will be rejected) = 0.1073

P(Inadeqaure cylinder) = p = 0.3

P(adequate cylinder) = q = 0.7

X = Inadequte cylinders

P(Unsatisfactory batch will not be rejected) = P(X<=2)

= P(X<=1) + P(Not rejected|X=2)

P(X<=1) = 0.420175

P(X=2) = 0.324135

P(Not rejected|X=2) = 1/15*0.324135 = 0.022

P(Unsatisfactory batch will not be rejected) = 0.44

Add a comment
Know the answer?
Add Answer to:
please to find the question in the image. thank you A quality-control plan for the concrete...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • In order to ensure the quality of concrete material used in a reinforced concrete construction, concrete...

    In order to ensure the quality of concrete material used in a reinforced concrete construction, concrete cylinders are collected at random from concrete mixes delivered to the construction site by a mixing plant. Past records of concrete from the same plant show that 85% of concrete mixes are good or are of satisfactory quality. To further ensure that the concrete delivered on site is of good quality, the engineer requires that one cylinder among those collected each day be tested...

  • A quality control engineer is in charge of testing whether or not 90% of the DVD...

    A quality control engineer is in charge of testing whether or not 90% of the DVD players produced by his company conform to specifications. To do this, the engineer randomly selects a batch of 12 DVD players from each day's production. The day's production is acceptable provided no more than 1 DVD player fails to meet specifications. Otherwise, the entire day's production has to be tested. (i) What is the probability that the engineer incorrectly passes a day's production as...

  • Summarize the experiment(s) and answer the following question: Why is this a correlational study and not...

    Summarize the experiment(s) and answer the following question: Why is this a correlational study and not an experiment (hint: why can't researchers manipulate the independent variable here)? What do you think of their measure of charisma and social skills? Why do you find it satisfactory or unsatisfactory? Read the attached article: link= Hippel et al. _2016_ - Quick Thinkers are Smooth Talkers.pdf the link is also above so can copy and paste it in a internet browser the link is...

  • 10. Write a one-page summary of the attached paper? INTRODUCTION Many problems can develop in activated...

    10. Write a one-page summary of the attached paper? INTRODUCTION Many problems can develop in activated sludge operation that adversely affect effluent quality with origins in the engineering, hydraulic and microbiological components of the process. The real "heart" of the activated sludge system is the development and maintenance of a mixed microbial culture (activated sludge) that treats wastewater and which can be managed. One definition of a wastewater treatment plant operator is a "bug farmer", one who controls the aeration...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT