4 0 Zira Co. reports the following production budget for the next four months. April 692 June May 720 July 706 Production (un
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Direct Materials Budget For April, May and June April 692 May 720 June 726 July 706 (refer workings below) 6 pounds 4,236 (20

Add a comment
Know the answer?
Add Answer to:
4 0 Zira Co. reports the following production budget for the next four months. April 692...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Zira Co. reports the following production budget for the next four months. Production (units) April 455...

    Zira Co. reports the following production budget for the next four months. Production (units) April 455 May 570 June 560 July 540 Each finished unit requires five pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month's production needs. Beginning raw materials inventory for April was 663 pounds. Assume direct materials cost $4 per pound. Prepare a direct materials budget for April, May, and June. ZIRA CO. Direct...

  • Zira Co. reports the following production budget for the next four months. Production (units) April 632...

    Zira Co. reports the following production budget for the next four months. Production (units) April 632 May 662 June 666 July 646 Each finished unit requires four pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month's production needs. Beginning raw materials inventory for April was 758 pounds. Assume direct materials cost $4 per pound Prepare a direct materials budget for April, May, and June (Round your intermediate...

  • Zira Co. reports the following production budget for the next four months. Production (units) April 584...

    Zira Co. reports the following production budget for the next four months. Production (units) April 584 May 625 June 617 July 597 Each finished unit requires five pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month's production needs. Beginning raw materials inventory for April was 876 pounds. Assume direct materials cost $5 per pound Prepare a direct materials budget for April, May, and June. (Round your intermediate...

  • Zira Co. reports the following production budget for the next four months. Production (units) April 624...

    Zira Co. reports the following production budget for the next four months. Production (units) April 624 May 665 June 657 July 637 Each finished unit requires four pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month's production needs. Beginning raw materials inventory for April was 749 pounds. Assume direct materials cost $3 per pound. Prepare a direct materials budget for April, May, and June. (Round your intermediate...

  • Zira Co. reports the following production budget for the next four months. April May June July...

    Zira Co. reports the following production budget for the next four months. April May June July Production (units) 604 645 637 617 Each finished unit requires four pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month’s production needs. Beginning raw materials inventory for April was 725 pounds. Assume direct materials cost $6 per pound. Prepare a direct materials budget for April, May, and June. (Round your intermediate...

  • Zira Co. reports the following production budget for the next four months. Production (units) April 572...

    Zira Co. reports the following production budget for the next four months. Production (units) April 572 May 600 June 606 July 586 Each finished unit requires four pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month's production needs. Beginning raw materials inventory for April was 686 pounds. Assume direct materials cost $4 per pound. Prepare a direct materials budget for April, May, and June. (Round your intermediate...

  • Zira Co. reports the following production budget for the next four months. Production (units) April 544...

    Zira Co. reports the following production budget for the next four months. Production (units) April 544 May 585 June 577 July 557 Each finished unit requires five pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month's production needs. Beginning raw materials inventory for April was 816 pounds. Assume direct materials cost $4 per pound. Prepare a direct materials budget for April, May, and June. (Round your intermediate...

  • Zira Co. reports the following production budget for the next four months. Production (units) April 714...

    Zira Co. reports the following production budget for the next four months. Production (units) April 714 May 755 June 747 July 727 Each finished unit requires six pounds of raw materials and the company wants to end each month with raw materials Inventory equal to 30% of next month's production needs. Beginning raw materials Inventory for April was 1,285 pounds. Assume direct materials cost $5 per pound. Prepare a direct materials budget for April, May, and June. (Round your Intermediate...

  • Zira Co. reports the following production budget for the next four months. April 676 May 730 July 688 June Product...

    Zira Co. reports the following production budget for the next four months. April 676 May 730 July 688 June Production (units) 708 Each finished unit requires six pounds of raw materials and the company wants to end each month with raw materials inventory equal to 40% of next month's production needs. Beginning raw materials inventory for April was 1,622 pounds. Assume direct materials cost $4 per pound. Prepare a direct materials budget for April, May, and June. (Round your intermediate...

  • Zira Co. reports the following production budget for the next four months. Production (units) April 694...

    Zira Co. reports the following production budget for the next four months. Production (units) April 694 May 735 Dune 727 July 7e Each finished unit requires four pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month's production needs. Beginning raw materials inventory for April was 833 pounds. Assume direct materials cost $4 per pound Prepare a direct materials budget for April, May, and June (Round your intermediate...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT