Question

Black and Decker Corporation has the following information is for their standard and actual costs: Standard...

Black and Decker Corporation has the following information is for their standard and actual costs:

Standard Costs:

Budgeted units of production - 9,000 (100% of capacity)

Standard material per unit - 12 lbs.

Standard material cost - $14.00 per pound

Standard labor hours per unit - 12

Standard labor rate - $29.00 per hour

Standard variable overhead rate - $7.50 per labor hour

Budgeted fixed overhead - $729,000

Fixed overhead rate is based on budgeted labor hours at 100% capacity

Actual Costs:

Actual Production - 8,400 units

Actual material purchased and used - 87,360 pounds

Actual total material cost - $1,222,350

Actual labor - 101,200 hours

Actual total labor costs - $2,884,200

Actual fixed overhead - $756,250

Actual variable overhead - $715,000

Determine: (a) the quantity, price variance, and total direct materials cost variance; (b) the time variance, rate variance, and total direct labor cost variance; and (c) the volume variance, controllable variance, and total factory overhead cost variance.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution a:

Direct Material Cost Variance
Actual Cost Standard cost for actual quantity Standard Cost
AQ * AP = AQ * SP = SQ * SP =
87360 $13.99 $1,222,350.00 87360 $14.00 $1,223,040.00 100800 $14.00 $1,411,200.00
$690.00 F $188,160.00 F
Direct Material Price Variance Direct Material Qty variance
Direct material price variance $690.00 F
Direct material quantity variance $188,160.00 F
Direct material cost variance $188,850.00 F

Solution b:

Direct Labor Cost Variance
Actual Cost Standard cost for actual quantity Standard Cost
AH * AR = AH * SR = SH * SR =
101200 $28.50 $2,884,200.00 101200 $29.00 $2,934,800.00 100800 $29.00 $2,923,200.00
$50,600.00 F $11,600.00 U
Direct Labor rate Variance Direct Labor Efficiency Variance
Direct Labor Rate variance $50,600.00 F
Direct Labor Efficiency variance $11,600.00 U
Direct labor cost variance $39,000.00 F

Solution c:

Controllable Variance
Actual overhead $1,471,250.00
Budgeted overhead $1,485,000.00
Controllable variance $13,750.00 F
Fixed overhead volume variance
Budgeted fixed overhead $729,000.00
Fixed overhead cost applied $680,400.00
Fixed overhead volume variance $48,600.00 U

Total factory overhead cost variance = $13,750 F + $48,600 U = $34,850 U

Add a comment
Know the answer?
Add Answer to:
Black and Decker Corporation has the following information is for their standard and actual costs: Standard...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following information is for the standard and actual costs for the Happy Corporation: Enter favorable...

    The following information is for the standard and actual costs for the Happy Corporation: Enter favorable variances as negative numbers. Standard Costs: Budgeted units of production - 16,000 [80% (or normal) capacity] Standard labor hours per unit - 4 Standard labor rate - $26 per hour Standard material per unit - 8 lbs. Standard material cost - $12 per pound Standard variable overhead rate - $15 per labor hour Budgeted fixed overhead - $640,000 Fixed overhead rate is based on...

  • please assist with the information provided: Trico Company set the following standard unit costs for its...

    please assist with the information provided: Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.40 per Ib.) Direct labor (6 ha. @ $14 per hr.) Factory overhead-variable (6 hrs. @ $8 per hr.) Factory overhead-fixed 16 hrs. @ $11 per hr.) Total standard cost $132.00 84.00 48.00 66.00 $330.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 60,000 units per quarter....

  • HOW DO I CALCULATE? Sedona Company set the following standard costs for one unit of its...

    HOW DO I CALCULATE? Sedona Company set the following standard costs for one unit of its product for this year. Direct material (30 Ibs. $2.20 per Ib.) Direct labor (20 hrs. $4.20 per hr.) Variable overhead (20 hrs. $2.20 per hr.) Fixed overhead (20 hrs. $1.10 per hr.) $ 66.00 84.00 44.00 22.00 $216.00 Total standard cost The $3.30 ($2.20 +$1.10) total overhead rate per direct labor hour is based on an expected operating level equal to 60% of the...

  • A. The standard costs and actual costs for direct materials for the manufacture of 2,240 actual...

    A. The standard costs and actual costs for direct materials for the manufacture of 2,240 actual units of product are as follows: Standard Costs Direct materials 2,240 kilograms @$8.60 Actual Costs Direct materials 2,300 kilograms The direct materials quantity variance is? Choose the correct answer below $413 favorable $516 unfavorable $516 favorable $413 unfavorable B. The following data relate to direct labor costs for the current period: Standard costs 7,200 hours at $11.30 Actual costs 6,400 hours at $10.80 What...

  • [The following information applies to the questions displayed below.] Trico Company set the following standard unit...

    [The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.10 per Ib.) $ 153.00 Direct labor (4 hrs. @ $15 per hr.) 60.00 Factory overhead—variable (4 hrs. @ $6 per hr.) 24.00 Factory overhead—fixed (4 hrs. @ $11 per hr.) 44.00 Total standard cost $ 281.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity...

  • Trico Company set the following standard unit costs for its single product. Direct materials (30 lbs....

    Trico Company set the following standard unit costs for its single product. Direct materials (30 lbs. @ $4 per Ib.) Direct labor (5 hrs. @ $14 per hr.) Factory overhead-variable (5 hrs. @ $8 per hr.) Factory overhead-fixed (5 hrs. @ $10 per hr.) Total standard cost $120.00 70.00 40.00 50.00 $280.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 60,000 units per quarter. The following flexible budget information is...

  • Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....

    Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.10 per Ib.) Direct labor (8 hrs. @ $15 per hr.) Factory overhead-Variable (8 hrs. @ $6 per hr.) Factory overhead-Fixed (8 hrs. @ $9 per hr.) Total standard cost $ 153.00 120.00 48.00 72.00 $ 393.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 65,000 units per quarter. The following flexible budget...

  • Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....

    Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) Direct labor (8 hrs. @ $16 per hr.) Factory overhead-variable (8 hrs. @ $9 per hr.) Factory overhead-fixed (8 hrs. @ $12 per hr.) Total standard cost $144.00 128.00 72.00 96.00 $440.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 59.000 units per quarter. The following flexible budget information is...

  • Trico Company set the following standard unit costs for its single product.      Direct materials (29...

    Trico Company set the following standard unit costs for its single product.      Direct materials (29 Ibs. @ $3 per Ib.) $ 87.00   Direct labor (6 hrs. @ $6 per hr.) 36.00   Factory overhead—variable (6 hrs. @ $4 per hr.) 24.00   Factory overhead—fixed (6 hrs. @ $5 per hr.) 30.00      Total standard cost $ 177.00    The predetermined overhead rate is based on a planned operating volume of 70% of the productive capacity of 60,000 units per quarter. The...

  • Trico Company set the following standard unit costs for its single product. Direct materials (30 lbs....

    Trico Company set the following standard unit costs for its single product. Direct materials (30 lbs. Direct nater $4 per Ib.) Direct labor (5 hrs. @ $14 per hr.) Factory overhead-variable (5 hrs. @ $8 per hr.) Factory overhead-fixed (5 hrs. @ $10 per hr.) Total standard cost $ 120.00 70.00 40.00 50.ee $ 280.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 60,000 units per quarter. The following flexible...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT