Answer:
Option 1st is correct. i.e $11,080.
First calculate Variable cost per hour and Fixed cost per month using High Low method | |||
Note: Units = Hours | |||
Months | Units | Cost($) | |
High Level | May | 1,180 | 11,080 |
Low Level | Jan | 460 | 8,920 |
Difference | 720 | 2,160 | |
A | Difference in Cost | 2,160 | |
B | Difference in units | 720 | |
C = A/B | Variable cost per unit | 3.00 | |
Working | High Level | Low Level | |
A | Total Cost | 11,080 | 8,920 |
B | Total Units | 1,180 | 460 |
C | Variable cost per unit | 3 | 3 |
D = B x C | Total Variable cost | 3,540 | 1,380 |
E = A - D | Total Fixed Cost | 7,540 | 7,540 |
Variable cost = $ 3 per hour | |||
Fixed Cost = $ 7540 per month | |||
Requirement: | |||
Estimated Total cost of 1180 hours = $ 7540 + ($3.00 x 1180 hours) | |||
10585 | |||
= $ 11,080 Answer |
Pearson Electric Company uses the high-low method to analyze mixed costs. The following information relates to...
Pearson Electric Company uses the high-low method to analyze mixed costs. The following information relates to the production data for the first six months of the year. Month January February March April May Cost(Y) Hours (H) $ 9,520 5ee $11,625 930 $ 9,540 610 $ 9,985 530 $11,680 1,220 $11,310 905 June How should the cost function be properly stated using the high-low method? Multiple Choice Ο Y« $7,525 + $2.00H. Ο Y = $8,020 + $3.0ΟΗ. Ο Y =...
please answer requierement 1,2 and 3
Tran Company, which uses the high-low method to analyze cost behavior, has determined that machine hours best predict the company's total utilities cost. The company's cost and machine hour usage data for the first six months of the year follow: Click the icon to view the data.) Read the requirements - X Х Data Table 1 - till Month Total Cost Machine Hours 3,400 1,090 January...... $ February ..... $ March ... $ 3,770...
Barkoff Enterprises, which uses the high-low method to analyze cost behavior, has determined that machine hours best explain the company's utilities cost. The company's relevant range of activity varies from a low of 600 machine hours to a high of 1,200 machine hours, with the following data being available for the first six months of the year: Month, Utilities Machine Hours January $ 9,200 850 February 8,860 770 March 9,450 860 April 9,860 970 May 10,240 1,000 June 9,650 950...
Barkoff Enterprises, which uses the high-low method to analyze cost behavior, has determined that machine hours best explain the company's utilities cost. The company's relevant range of activity varies from a low of 600 machine hours to a high of 1,200 machine hours, with the following data being available for the first six months of the year: Machine Month Utilities Hours January February $10,300 960 9,960 880 March 10,550 970 April 10,960 1,080 May 11,087 1,110 June 10,750 1,060 Using...
E6-23 (similar to) Chen Company, which uses the High-Low method to analyze cost behavior, has determined that machine hours best predict the company's total utilities cost. The company's cost and machine hour usage data for the first six months of the year follow: Month Machine Hours January 1,090 Total Costs $ 3,400 $ 3,760 $ 3,532 February 1,190 March 1,080 April $3,760 1,260 May $ 4,400 1,380 June $ 4,192 1,480 Requirements: Using the High-Low method to predict the total...
Coughlin Company, which uses the high-low method to analyze cost behavior, has determined that machine hours best predict the company's total utilities cost. The company's cost and machine hour usage data for the first six months of the year follow: (Click the icon to view the data.) i Data Table Requirements Using the high-low method, answer the following questions: 1. What is the variable utilities cost per machine hour? 2. What is the fixed cost of utilities each month? 3....
1. ker Corporation uses the high-low method to analyze cost behavior. You as controller have determined that machine hours best explain the company's utilities cost. The company's relevant range of activity varies from a low of 600 machine hours to a high of 1,100 machine hours, with the following data being available for the first six months of the year: Month Utilities Machine Hours January $8,700 800 February 8,360 720 March 8,950 810 April 9,360 920 May 9,625 950 June...
Question Help Tran Company, which uses the high-low method to analyze cost behaviour, has determined that machine hours best predict the company's total utilities cost. The company's cost and machine hour usage data for the first six months of the year follow Click the icon to view the data.) Requirements Using the high-low method, answer the following questions: 1. What is the variable utilities cost per machine hour? 2. What is the fixed cost of utilities each month? 3. If...
Coughlin Company, which uses the high-low method to analyze cost behavior, has determined that machine hours best predict the company's total utlities cost. The company's cost and machine hour usage data for the first six months of the year follow (Click the icon to view the data.) Requirements Using the high-low method, answer the following questions: 1. What is the variable utilities cost per machine hour? 2. What is the fixed cost of utilities each month? 3. If Coughlin Company...
Jungemann Company, which uses the high-low method to analyze
cost behavior, has determined that machine hours best predict the
company's total utilities cost. The company's cost and machine
hour usage data for the first six months of the year
follow:
Jungemann Company, which uses the high-low method to analyze cost behavior, has determined that machine hours best predict the company's total utilities cost. The company's cost and machine hour usage data for the first six months of the year follow:...