Question

Predetermined Overhead Rate, Applied Overhead, Unit Cost Ripley, Inc., costs products using a normal costing system....

Predetermined Overhead Rate, Applied Overhead, Unit Cost

Ripley, Inc., costs products using a normal costing system. The following data are available for last year:

Budgeted:
      Overhead      $294,400
      Machine hours      87,000
      Direct labor hours      9,200
Actual:
      Overhead      $293,800
      Machine hours      84,800
      Direct labor hours       8,920
      Prime cost      $694,560
      Number of units      140,000

Overhead is applied on the basis of direct labor hours.

Required:

1. What was the predetermined overhead rate?
$___ per direct labor hour

2. What was the applied overhead for last year?
$____

3. Was overhead over- or underapplied, and by how much?
Underapplied overhead  = $___

4. What was the total cost per unit produced? (Carry your answer to four significant digits.)
$____ per unit

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1.

Predetermined overhead rate = Estimated overheads/Direct labor hours

= 294,400/9,200

= $32 per direct labor hour

2.

Applied overhead = Actual direct labor hours x Predetermined overhead rate

= 8,920 x 32

= $285,440

3.

Actual overhead = $293,800

Applied overhead = $285,440

Since Applied overhead is less than Actual overhead, hence overhead is under applied.

Under applied overhead  = Actual overhead - Applied overhead

= $293,800 - $285,440

= $8,360

4.

Total cost =   Prime cost + Applied overhead

= 694,560 + 285,440

= $980,000

Total cost per unit = Total cost/Number of units produced

= 980,000/140,000

= $7

Kindly give a positive rating if you are satisfied with the answer. Feel free to ask if you have any doubt. Thanks.

Add a comment
Know the answer?
Add Answer to:
Predetermined Overhead Rate, Applied Overhead, Unit Cost Ripley, Inc., costs products using a normal costing system....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 4.11 Predetermined Overhead Rate, Applied Overhead, Unit Cost Ripley, Inc., costs products using a normal...

    Exercise 4.11 Predetermined Overhead Rate, Applied Overhead, Unit Cost Ripley, Inc., costs products using a normal costing system. The following data are available for last year: Budgeted: Overhead $285,600 Machine hours 84.000 Direct labor hours 10.200 Actual: Overhead $285,000 Machine hours 82.200 Direct labor hours 9,930 Prime cost $1,050,000 Number of units 150,000 Overhead is applied on the basis of direct labor hours. Required: 1. What was the predetermined overhead rate? 2. What was the applied overhead for last year?...

  • Predetermined Overhead Rate, Applied Overhead, Unit Cost Ripley, Inc., costs products using a normal costing system....

    Predetermined Overhead Rate, Applied Overhead, Unit Cost Ripley, Inc., costs products using a normal costing system. The following data are available for last year: Overhead is applied on the basis of direct labor hours. Required: 1. What was the predetermined overhead rate? $________ per direct labor hour 2. What was the applied overhead for last year? $_________ 3. Was overhead over- or underapplied, and by how much? - Select your answer -Overapplied overheadUnderapplied overheadItem 3 = $________ 4. What was...

  • Predetermined Overhead Rates, Overhead Variances, Unit Costs Primera Company produces two products and uses a predetermined...

    Predetermined Overhead Rates, Overhead Variances, Unit Costs Primera Company produces two products and uses a predetermined overhead rate to apply overhead. Primera currently applies overhead using a plantwide rate based on direct labor hours. Consideration is being given to the use of departmental overhead rates where overhead would be applied on the basis of direct labor hours in Department 1 and on the basis of machine hours in Department 2. At the beginning of the year, the following estimates are...

  • Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as...

    Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $15 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 54,500 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials Direct labor Manufacturing overhead applied Total job cost 2 ? $1,533,500 Job Omega Direct materials Direct...

  • Koebel Corp. uses a job order costing system with manufacturing overhead applied to products on the...

    Koebel Corp. uses a job order costing system with manufacturing overhead applied to products on the basis of direct labor hours. For the upcoming year, Koebel Corp estimated total manufacturing overhead cost at $777,000 and total direct labor hours of 51,800. Koebel Corp. started the year with no beginning balances in either Work in Process Inventory or Finished Goods Inventory. During the year actual manufacturing overhead incurred was $747,400 and 48,200 direct labor hours were used. (a) Calculate the predetermined...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine- hour 31,000 $310,000 $ 4.00 Recently, Job T587 was completed with the following characteristics: 10 Number of units in the job Total machine-hours Direct materials Direct labor cost 30 $ 730 $1,460 The total job cost...

  • Predetermined Overhead Rates, Overhead Variances, Unit Costs McCawl Company produces two products and uses a predetermined...

     Predetermined Overhead Rates, Overhead Variances, Unit Costs McCawl Company produces two products and uses a predetermined overhead rate to apply overhead. McCawl currently applies overhead using a plantwide rate based on direct labor hours. Consideration is being given to the use of departmental overhead rates where overhead would be applied on the basis of direct labor hours in department 1 and on the basis of machine hours in department 2. At the beginning of the year, the following estimates are provided: Required: 1....

  • Chloe Corp uses a job order costing system with manufacturing overhead applied to products on the...

    Chloe Corp uses a job order costing system with manufacturing overhead applied to products on the basis of direct labor hours. For the upcoming year, Chloe Corp estimated total manufacturing overhead cost at $652,800 and total direct labor hours of 40,800. During the year actual manufacturing overhead incurred was $620,200 and 40,500 direct labor hours were used. (a) Calculate the predetermined overhead rate. (b) Calculate how much manufacturing overhead will be applied to production. (c) Is overhead over - or...

  • Tyler Tooling Company uses a job order cost system with overhead applied to products on the...

    Tyler Tooling Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $214,540 and total machine hours at 63,100. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each job: Direct materials used Direct labor Machine hours Job 101 Job 102...

  • eBook Calculator Applied Overhead and Unit Overhead Cost: Plantwide Rates Seco, Inc., produces two types of...

    eBook Calculator Applied Overhead and Unit Overhead Cost: Plantwide Rates Seco, Inc., produces two types of clothes dryers: deluxe and regular. Seco uses a plantwide rate based on direct labor hours to assign its overhead costs. The company has the following estimated and actual data for the coming year Estimated overhead $2,000,000 Expected activity 50,000 Actual activity (direct labor hours): Deluxe dryer 10,000 Regular dryer 40,000 Units produced Deluxe dryer 20,000 Regular dryer 200,000 Required: 1. Calculate the predetermined plantwide...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT