Exercise 4.11 Predetermined Overhead Rate, Applied Overhead, Unit Cost Ripley, Inc., costs products using a normal costing sy

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. Calculation of the predetermined overhead rate:

Budgeted overhead cost Predetermined overhead rate = Budgeted Direct labor hours $285,600 10,200 = 28 per labor hour

Hence, the predetermined overhead rate is $28 per labor hour.

2. Calculation of the applied overhead:

Applied overhead = Actual Direct labor hours x Predetermined overhead rate =9,930x $28 = $278,040

Hence, the applied overhead is $278,040.

3.

Actual overheads are $285,000 and applied overhead is $278,040, applied overhead is less than actual overhead, thus the overheads are under applied.

Calculation of underapplied overhead:

Under applied overhead = Actual overhead – Applied overhead = $285,000 - $278,040 = $6,960

Thus, the underapplied overhead is $6,960.

4.

Calculation of total cost per unit:

Applied overhead + Prime cost Total cost per unit = = Number of units $278,040+$1,050,000 150,000 $1,328,040 150,000 = $8.853

Thus, the total cost per unit is $8.8536.

Add a comment
Know the answer?
Add Answer to:
Exercise 4.11 Predetermined Overhead Rate, Applied Overhead, Unit Cost Ripley, Inc., costs products using a normal...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Predetermined Overhead Rate, Applied Overhead, Unit Cost Ripley, Inc., costs products using a normal costing system....

    Predetermined Overhead Rate, Applied Overhead, Unit Cost Ripley, Inc., costs products using a normal costing system. The following data are available for last year: Budgeted:       Overhead      $294,400       Machine hours      87,000       Direct labor hours      9,200 Actual:       Overhead      $293,800       Machine hours      84,800       Direct labor hours       8,920       Prime cost      $694,560       Number of units      140,000 Overhead is applied on the basis of direct labor hours. Required: 1. What was the predetermined overhead rate? $___ per direct...

  • Predetermined Overhead Rate, Applied Overhead, Unit Cost Ripley, Inc., costs products using a normal costing system....

    Predetermined Overhead Rate, Applied Overhead, Unit Cost Ripley, Inc., costs products using a normal costing system. The following data are available for last year: Overhead is applied on the basis of direct labor hours. Required: 1. What was the predetermined overhead rate? $________ per direct labor hour 2. What was the applied overhead for last year? $_________ 3. Was overhead over- or underapplied, and by how much? - Select your answer -Overapplied overheadUnderapplied overheadItem 3 = $________ 4. What was...

  • Predetermined Overhead Rates, Overhead Variances, Unit Costs Primera Company produces two products and uses a predetermined...

    Predetermined Overhead Rates, Overhead Variances, Unit Costs Primera Company produces two products and uses a predetermined overhead rate to apply overhead. Primera currently applies overhead using a plantwide rate based on direct labor hours. Consideration is being given to the use of departmental overhead rates where overhead would be applied on the basis of direct labor hours in Department 1 and on the basis of machine hours in Department 2. At the beginning of the year, the following estimates are...

  • Luthan Company uses a predetermined overhead rate of $23.80 per direct labor-hour. This predetermined rate was...

    Luthan Company uses a predetermined overhead rate of $23.80 per direct labor-hour. This predetermined rate was based on a cost formula that estimated $285,600 of total manufacturing overhead for an estimated activity level of 12,000 direct labor-hours. The company incurred actual total manufacturing overhead costs of $266,000 and 12,500 total direct labor-hours during the period. Required: Determine the amount of manufacturing overhead that would have been applied to all jobs during the period. Manufacturing overhead applied

  • Exercise 2-1 Compute a Predetermined Overhead Rate [LO2-1] Harris Fabrics computes its plantwide predetermined overhead rate...

    Exercise 2-1 Compute a Predetermined Overhead Rate [LO2-1] Harris Fabrics computes its plantwide predetermined overhead rate annually on the basis of direct labor-hours. At the beginning of the year, it estimated that 20,000 direct labor-hours would be required for the period's estimated level of production. The company also estimated $94,000 of fixed manufacturing overhead cost for the coming period and variable manufacturing overhead of $2.00 per direct labor-hour. Harris's actual manufacturing overhead cost for the year was $123.900 and its...

  • Alternate problem E Sullivan Company applied overhead to production using a predetermined overhead rate based on...

    Alternate problem E Sullivan Company applied overhead to production using a predetermined overhead rate based on machine-hours. Budgeted data is: Budgeted machine-hours 75,000 Budgeted manufacturing overhead $870,000 a. Compute the predetermined overhead rate. b. Assume actual manufacturing overhead amounted to $997,500, and 86,000 machine-hours were used. Compute the amount of underapplied or overapplied manufacturing overhead and prepare the journal entry to transfer underapplied or overapplied overhead to Cost of Goods Sold.

  • Predetermined Overhead Rates, Overhead Variances, Unit Costs McCawl Company produces two products and uses a predetermined...

     Predetermined Overhead Rates, Overhead Variances, Unit Costs McCawl Company produces two products and uses a predetermined overhead rate to apply overhead. McCawl currently applies overhead using a plantwide rate based on direct labor hours. Consideration is being given to the use of departmental overhead rates where overhead would be applied on the basis of direct labor hours in department 1 and on the basis of machine hours in department 2. At the beginning of the year, the following estimates are provided: Required: 1....

  • Cornerstone Exercise 4.1 (Algorithmic) Applied Overhead and Unit Overhead Cost: Plantwide Rates Seco, Inc., produces two...

    Cornerstone Exercise 4.1 (Algorithmic) Applied Overhead and Unit Overhead Cost: Plantwide Rates Seco, Inc., produces two types of clothes dryers: deluxe and regular. Seco uses a plantwide rate based on direct labor hours to assign its overhead costs. The company has the following estimated and actual data for the coming year: Estimated overhead $1,710,000 Expected activity 45,000 Actual activity (direct labor hours): Deluxe dryer 9,000   Regular dryer 36,000 Units produced: Deluxe dryer 18,000   Regular dryer 180,000 Required: 1. Calculate the...

  • Walker Enterprises, Inc., uses a job-order costing system and sets a predetermined overhead rate at the...

    Walker Enterprises, Inc., uses a job-order costing system and sets a predetermined overhead rate at the beginning of each year based on estimated manufacturing overhead costs. Each job requires work in both the Assembly and Machining Departments. The predetermined overhead rate is based on direct labor cost in Assembly Department and on machine hours in Machining Department. At the beginning of the year, the company made the following estimates: Assembly Department $120,000 Machining Department $32,000 Direct labor cost Manufacturing overhead...

  • eBook Calculator Applied Overhead and Unit Overhead Cost: Plantwide Rates Seco, Inc., produces two types of...

    eBook Calculator Applied Overhead and Unit Overhead Cost: Plantwide Rates Seco, Inc., produces two types of clothes dryers: deluxe and regular. Seco uses a plantwide rate based on direct labor hours to assign its overhead costs. The company has the following estimated and actual data for the coming year Estimated overhead $2,000,000 Expected activity 50,000 Actual activity (direct labor hours): Deluxe dryer 10,000 Regular dryer 40,000 Units produced Deluxe dryer 20,000 Regular dryer 200,000 Required: 1. Calculate the predetermined plantwide...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT