Alternate problem E Sullivan Company applied overhead to production using a predetermined overhead rate based on machine-hours. Budgeted data is: Budgeted machine-hours 75,000 Budgeted manufacturing overhead $870,000 a. Compute the predetermined overhead rate. b. Assume actual manufacturing overhead amounted to $997,500, and 86,000 machine-hours were used. Compute the amount of underapplied or overapplied manufacturing overhead and prepare the journal entry to transfer underapplied or overapplied overhead to Cost of Goods Sold.
0 0
Add a comment Improve this question Transcribed image text
Answer #1
a) Predetermined overhead rate =
budgeted MOH/Budgeted machine hours
870,000/75,000
11.6 per machine hours
b) Applied manufacturing overhead    (11.6*86000)= 997600
Actual manufacturing overhead 997,500
Manufacturing overhead over applied 100
Accounting titles & explanations Debit Credit
Manufacturing overhead 100
cost of goods sold 100
Add a comment
Know the answer?
Add Answer to:
Alternate problem E Sullivan Company applied overhead to production using a predetermined overhead rate based on...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT