Question

Arizona Desert Homes (ADH) constructed a new subdivision during 2017 and 2018 under contract with Cactus...

Arizona Desert Homes (ADH) constructed a new subdivision during 2017 and 2018 under contract with Cactus Development Co. Relevant data are summarized below:

Contract amount $ 3,315,000
Cost: 2017 1,270,000
2018 670,000
Gross profit: 2017 905,000
2018 470,000
Contract billings: 2017 1,657,500
2018 1,657,500


ADH recognizes revenue upon completion of the contract.

What is the journal entry in 2018 to record revenue?

Multiple Choice

  • Construction in progress 1,375,000
    Cost of construction 1,940,000
    Revenue from long-term contracts 3,315,000
  • Cost of construction 2,175,000
    Gross profit 1,140,000
    Revenue from long-term contracts 3,315,000
  • Construction in progress 470,000
    Cost of construction 670,000
    Revenue from long-term contracts 1,140,000
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

If ADH  recognizes revenue upon completion of the contract, then  journal entry in 2018 to record revenue is :

Construction in progress 1,375,000
Cost of construction 1,940,000
Revenue from long-term contracts 3,315,000

Hence first option is correct.

Add a comment
Know the answer?
Add Answer to:
Arizona Desert Homes (ADH) constructed a new subdivision during 2017 and 2018 under contract with Cactus...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Arizona Desert Homes (ADH) constructed a new subdivision during 2017 and 2018 under contract with Cactus...

    Arizona Desert Homes (ADH) constructed a new subdivision during 2017 and 2018 under contract with Cactus Development Co. Relevant data are summarized below: Contract amount $ 3,315,000 Cost: 2017 1,270,000 2018 670,000 Gross profit: 2017 905,000 2018 470,000 Contract billings: 2017 1,657,500 2018 1,657,500 ADH recognizes revenue upon completion of the contract. What is the journal entry in 2018 to record revenue? Multiple Choice Construction in progress 1,375,000 Cost of construction 1,940,000 Revenue from long-term contracts 3,315,000 Cost of construction...

  • What is the correct answer? Arizona Desert Homes (ADH) constructed a new subdivision during 2020 and...

    What is the correct answer? Arizona Desert Homes (ADH) constructed a new subdivision during 2020 and 2021 under contract with Cactus Development Co. Relevant data are summarized below: Contract amount Cost: 2020 2021 Gross profit: $3,000,000 1,200,000 600,000 800,000 400,000 1,500,000 1,500,000 2020 2021 2020 2021 Contract billings: ADH recognizes revenue over time with respect to these contracts. For 2021, what is the journal entry to record revenue? Multiple Choice Cost of construction Grocs nofi + 2,000,000 1,000,000 Revenue from...

  • Arizona Desert Homes (ADH) constructed a new subdivision during 2020 and 2021 under contract with Cactus...

    Arizona Desert Homes (ADH) constructed a new subdivision during 2020 and 2021 under contract with Cactus Development Co. Relevant data are summarized below: Contract amount $ 3,000,000 Cost: 2020 1,200,000 2021 600,000 Gross profit: 2020 800,000 2021 400,000 Contract billings: 2020 1,500,000 2021 1,500,000 ADH recognizes revenue over time with respect to these contracts. In its December 31, 2020, balance sheet, ADH would report:    A) The contract asset, deferred profit, of $400,000. B) The contract asset, cost and profits in...

  • Arizona Desert Homes (ADH) constructed a new subdivision during 2020 and 2021 under contract with Cactus...

    Arizona Desert Homes (ADH) constructed a new subdivision during 2020 and 2021 under contract with Cactus Development Co. Relevant data are summarized below: Contract amount Cost: Gross profit: 2020 2021 2020 2021 2020 2021 $3,180,000 1,240,000 640,000 860,000 440,000 1,590,000 1,590,000 Contract billings: ADH recognizes revenue upon completion of the contract. In its December 31, 2020, balance sheet, ADH would report: Multiple Choice C ) The contract asset, contract amount in excess of billings, of $1,590,000. The contract asset, deferred...

  • ABZ constructed a new subdivision during 2020 and 2021 under contract with Cactus Development Co. Relevant...

    ABZ constructed a new subdivision during 2020 and 2021 under contract with Cactus Development Co. Relevant data are summarized below: Contract amount $   3,000,000 Cost: 2020 1,200,000 2021 600,000 Gross profit: 2020 800,000 2021 400,000 Contract billings: 2020 1,500,000 2021 1,500,000 ABZ recognizes revenue upon completion of the contract. For 2020, what is the journal entry to record revenue? A) Accounts receivable 1,500,000       Revenue from long-term contracts 1,500,000 B) Accounts receivable 2,300,000       Gross profit 800,000       Revenue from long-term contracts 1,500,000...

  • During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job...

    During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 –0– Billings to date 301,000 897,000 1,610,000 Collections to date 271,000 817,000 1,428,000 A) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ 258,000 Gross...

  • Tamarisk Construction Company uses the percentage-of-completion method of accounting. In 2017, Tamarisk began work under contract...

    Tamarisk Construction Company uses the percentage-of-completion method of accounting. In 2017, Tamarisk began work under contract #E2-D2, which provided for a contract price of $2,227,000. Other details follow: 2017 2018 Cost incurred during the year $660240 $1422000 Estimated costs to complete, as of December 31 911760 0 Billings to date 425000 2227000 Collections during the year 347000 1523000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017 $______________ Revenue...

  • Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract...

    Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10-20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...

  • Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging...

    Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10-20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...

  • During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job...

    During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $400,000 $825,000 $1,070,000 Estimated costs to complete 600,000 275,000 –0– Billings to date 300,000 900,000 1,600,000 Collections to date 270,000 810,000 1,425,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT