The following data were drawn from the records of Campbell Corporation. Planned volume for year (static budget) Standard dire

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Pre-determined overhead rate = 17200/4300 = $                4.00 per unit
Fixed cost volume variance = (4700-4300)*4 = $             1,600 F

Answer is given for e and g, as f is correct.

Add a comment
Know the answer?
Add Answer to:
The following data were drawn from the records of Campbell Corporation. Planned volume for year (static...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following data were drawn from the records of Solomon Corporation. Planned volume for year (static...

    The following data were drawn from the records of Solomon Corporation. Planned volume for year (static budget) Standard direct materials cost per unit Standard direct labor cost per unit Total expected fixed overhead costs Actual volume for the year (flexible budget) Actual direct materials cost per unit Actual direct labor cost per unit Total actual fixed overhead costs 4,100 units 4.00 pounds @ $1.60 per pound 2.10 hours @ $5.00 per hour $ 18,450 4,500 units 3.60 pounds @ $2.00...

  • The following data were drawn from the records of Perez Corporation. Planned volume for year (static budget) Standard d...

    The following data were drawn from the records of Perez Corporation. Planned volume for year (static budget) Standard direct materials cost per unit Standard direct labor cost per unit Total expected fixed overhead costs Actual volume for the year (flexible budget) Actual direct materials cost per unit Actual direct labor cost per unit Total actual fixed overhead costs 3,400 units 3.50 pounds @ $1.50 per pound 2.30 hours @ $3.30 per hour $14,620 3,900 units 3.10 pounds @ $2.00 per...

  • Vernon Company manufactures molded candles that are finished by hand. The company developed the following standards...

    Vernon Company manufactures molded candles that are finished by hand. The company developed the following standards for a new line of drip candles. Amount of direct materials per candle Price of direct materials per pound Quantity of labor per unit Price of direct labor per hour Total budgeted fixed overhead 1.30 pounds $ 0.70 1.50 hours $ 7.30/hour $ 128,800 During Year 2, Vernon planned to produce 23,000 drip candles. Production lagged behind expectations, and it actually produced only 16,000...

  • Vernon Company manufactures molded candles that are finished by hand. The company developed the following standards...

    Vernon Company manufactures molded candles that are finished by hand. The company developed the following standards for a new line of drip candles. Amount of direct materials per candle Price of direct materials per pound Quantity of labor per unit Price of direct labor per hour Total budgeted fixed overhead 1.50 pounds $ 0.50 1.10 hours $ 8.60/hour $145,700 During Year 2, Vernon planned to produce 31,000 drip candles. Production lagged behind expectations, and it actually produced only 24,000 drip...

  • 16 Perez Company manufactures molded candles that are finished by hand. The company developed the following...

    16 Perez Company manufactures molded candles that are finished by hand. The company developed the following standards for a new line of drip candles: 1.80 pounds Amount of direct materials per candle Price of direct materials per pound 0.50 Quantity of labor per unit Price of direct labor per hour 1.30 hours 8.00/hour $94,600 Total budgeted fixed overhead. During 2017, Perez planned to produce 22,000 drip candles. Production lagged behind expectations, and it actually produced only 15,000 drip candles. At...

  • Walton's Doll Company produces handmade dolls. The standard amount of time spent on each doll is 1.50 hours. The standa...

    Walton's Doll Company produces handmade dolls. The standard amount of time spent on each doll is 1.50 hours. The standard cost of labor is $7.73 per hour. The company planned to make 8,000 dolls during the year but actually used 12,700 hours of labor to make 8,900 dolls. The payroll amounted to $102,743. Required a. Should labor variances be based on the planned volume of 8,000 dolls or the actual volume of 8,900 dolls? b. Prepare a table that shows...

  • 4. STANDARD COST SYSTEMS VARIANCE COMPUTATIONS Livingston Corporation recently implemented a standard cost system. The company's...

    4. STANDARD COST SYSTEMS VARIANCE COMPUTATIONS Livingston Corporation recently implemented a standard cost system. The company's cost accountant has provided the following data to perform a variance analysis for May Standard Cost Information Direct Material Standard Price $12 per pound Standard Quantity Allowed Per Unit Direct Labor Standard Rate Standard Hours Allowed Per Unit Fixed Overhead Budgeted Normal Level of Production Variable Overhead Application Rate Fixed Overhead Application Rate ($24,000/12,000 units) Total Overhead Application Rate 4 pounds per unit $7...

  • In addition to other costs, Thornton Telephone Company planned to incur $465,500 of fixed manufacturing overhead...

    In addition to other costs, Thornton Telephone Company planned to incur $465,500 of fixed manufacturing overhead in making 350,000 telephones. Thornton actually produced 358,000 telephones, incurring actual overhead costs of $457,500. Thornton establishes its predetermined overhead rate based on the planned volume of production (expected number of telephones). Required: a. Calculate the predetermined overhead rate. (Round your answer to 2 decimal places.) b. Determine the fixed cost spending variance and indicate whether it is favorable (F) or unfavorable (U). (Select...

  • In addition to other costs, Zachary Telephone Company planned to incur $420,070 of fixed manufacturing overhead...

    In addition to other costs, Zachary Telephone Company planned to incur $420,070 of fixed manufacturing overhead in making 353,000 telephones. Zachary actually produced 361,000 telephones, incurring actual overhead costs of $413,070. Zachary establishes its predetermined overhead rate based on the planned volume of production (expected number of telephones). Required: a. Calculate the predetermined overhead rate. (Round your answer to 2 decimal places.) b. Determine the fixed cost spending variance and indicate whether it is favorable (F) or unfavorable (U). (Select...

  • Check my work Songsu Co. is struggling to control costs. We are hired as consultants to...

    Check my work Songsu Co. is struggling to control costs. We are hired as consultants to determine why the company's actual costs exceed budgeted costs. The Tableau Dashboard is provided for our analysis. Direct Materials Direct Labor Standard Actual Standard Actual $7 $17 $6 6 lbs 15 $14 4 lbs 2 2.5 hrs 2 hrs Pounds Per Price Per Pounds Per Price Per Hours Per Price Per Hours Per Price Per Unit Pound Unit Pound Unit Hour Unit Hour Overhead...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT