Question

32) Tranquility Company manufactures ceiling fans and uses an activity-based costing system. Each ceiling fan has 20 separate
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Correct answer---------(D) $125.40

Working

Activity name Activity Rates Activity ABC Cost
(A) (B) (A x B)
Material handling $                       0.07                        20.00 $                 1.40
Machining $                       7.40                           2.50 $               18.50
Assembly $                       0.40                        20.00 $                 8.00
Packaging $                       2.50                           1.00 $ 2.50
Direct material cost $ 95.00 1 $ 95.00
Total cost including direct material assigned $              125.40
Add a comment
Know the answer?
Add Answer to:
32) Tranquility Company manufactures ceiling fans and uses an activity-based costing system. Each ceiling fan has...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question Help Tranquility Company manufactures ceiling fans and uses an activity-based costing system. Each ceiling fan...

    Question Help Tranquility Company manufactures ceiling fans and uses an activity-based costing system. Each ceiling fan has 20 separate parts. The direct materials cost is $75 and each ceiling fan requires 4 hours of machine time to manufacture. There is no direct labor. Additional information is as follows: Predetermined Overhead Activity Allocation Base Allocation Rate Materials handling Number of parts $ 0.04 Machining Machine hours 68 Assembling Number of parts 0.25 Packaging Number of finished units 3.2 What is the...

  • 2). Brannon Company manufactures ceiling fans and uses an activity-based costing system to allocate all manufacturing...

    2). Brannon Company manufactures ceiling fans and uses an activity-based costing system to allocate all manufacturing convers ion costs. Each ceiling fan consists of 10 separate parts totaling $100 in direct materials, and requires 2 hours of machine time to produce. Additional information follows: Activity Materials handling Number of parts Machining Assembling Packaging What is the total manufacturing cost per ceiling fan? Allocation Base Cost Allocation Rate $.08 per part 7.20 per machine hour 35 per part 2.70 per finished...

  • Beaver Company manufactures coffee tables and uses an activity - based costing system. Each coffee table...

    Beaver Company manufactures coffee tables and uses an activity - based costing system. Each coffee table consists of 20 separate parts totaling $290 in direct materials, and requires 7 hours of machine time to produce. Additional information follows: Activity Allocation Base Cost Allocation Rate Materials handling Number of parts $2.00 per part Machining Machine hours $3.90 per machine hour Assembling Number of parts $4.00 per part Packaging Number of finished units $6.00 per finished unit What is the cost of...

  • Beaver Company manufactures coffee tables and uses an activity-based costing system. Each coffee table consists of...

    Beaver Company manufactures coffee tables and uses an activity-based costing system. Each coffee table consists of 20 separate parts totaling $180 in direct materials, and requires 7 hours of machine time to produce. Additional information follows: Activity Materials handling Machining Assembling Packaging Allocation Base Number of parts Machine hours Number of parts Number of finished units Cost Allocation Rate $3.00 per part $2.80 per machine hour $5.00 per part $7.00 per finished unit What is the cost of materials handling...

  • Yorba Company manufactures cuckoo clocks and uses an activity-based costing system to allocate overhead to its...

    Yorba Company manufactures cuckoo clocks and uses an activity-based costing system to allocate overhead to its products. Each cuckoo clock consists of 6 separate parts totaling $80 in direct materials, $40 in direct labor and requires 1.5 hours of machine time to produce. Additional information follows: Activity Allocation Base Cost Allocation Rate Materials handling Number of parts $1.34 per part Machining Machine hours $2.50 per machine hour Assembling Number of parts $0.56 per part Packaging Number of finished units $2.19...

  • Colonial Company manufactures decorative wall clocks and uses activity-based costing. Each clock consists of 20 separate...

    Colonial Company manufactures decorative wall clocks and uses activity-based costing. Each clock consists of 20 separate parts totaling $95 in direct materials, and requires 2.5 hours of machine time to produce. Additional information is as follows: Activity Allocation Base Cost Allocation Rate Materials handling Number of parts $ 0.08 Machining Machine hours 7.20 Assembling Number of parts 0.35 Packaging Number of finished clocks 2.70 What is the cost of materials handling per clock? Multiple Choice $0.08. $1.60. $6.00. $5.00. $7.20.

  • The company manufactures coffee tables and uses an activity-based costing system to allocate all manufacturing conversion...

    The company manufactures coffee tables and uses an activity-based costing system to allocate all manufacturing conversion costs. Each coffee tables consists of 20 separate parts totaling $190 in direct materials, and requires 4.0 hours of machine time to produce.  What is the cost of packaging per coffee table? (round answer to nearest whole number.) Activity Allocation Base MOH Allocation Rate Materials Handling Number of Parts $1 per part Machining Machine Hours $3.5 per machine hour Assembling Number of Parts $2 per...

  • The company manufactures coffee tables and uses an activity-based costing system to allocate all manufacturing conversion...

    The company manufactures coffee tables and uses an activity-based costing system to allocate all manufacturing conversion costs. Each coffee tables consists of 20 separate parts totaling $190 in direct materials, and requires 4.0 hours of machine time to produce.  What is the cost of materials handling per coffee table? (round answer to nearest whole number.) Activity Allocation Base MOH Allocation Rate Materials Handling Number of Parts $1 per part Machining Machine Hours $3.5 per machine hour Assembling Number of Parts $2...

  • comem collection Supe SOUMILIT What is the machining cost per ceiling fan? A. $0.32 OB. $24.80...

    comem collection Supe SOUMILIT What is the machining cost per ceiling fan? A. $0.32 OB. $24.80 C. $1.60 D.$124.00 QUESTION 11 Brannon Inc, manufactures ceiling fans and uses activity-based costing. Each fan has 20 separate parts. The direct material cost is $70, and each ceiling fan requires 4 hours of machine time to manufacture. Additional information: Predetermined Overhead Activity Allocation Base Allocation Rate Materials handling Number of parts $ 0.08/part Machining Machine hours $6.20/MH What is the total manufacturing cost...

  • Harold Company manufactures partner desks and uses an activity-based costing system to allocate all manufacturing conversion...

    Harold Company manufactures partner desks and uses an activity-based costing system to allocate all manufacturing conversion costs. Each partner desk consists of 20 separate parts totaling $220 in direct materials, and requires 7.0 hours of machine time to produce. Additional information follows: Activity Allocation Base Cost Allocation Rate Materials handling Number of parts $2.00 per part Machining Machine hours $3.10 per machine hour Assembling Number of parts $1.00 per part Packaging Number of finished units $4.00 per finished unit What...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT