1. Plant-wide predetermined overhead rate = Estimated total manufacturing overhead / Estimated total machine hours
Plant-wide predetermined overhead rate = $27,800+(2,500*$2.1)+(1,500*$2.9) / 4,000
Plant-wide predetermined overhead rate = $27,800+5,250+4,350 / 4,000 = $9.35 per machine hour
2. Manufcaturing overhead applied::
Job P = 3,700*$9.35 = $34,595
Job Q = 3,100*$9.35 = $28,985
3. Total manufacturing cost assigned to Job P = Direct material+Direct labor+Manufacturing overhead applied
Total manufacturing cost assigned to Job P = $20,000+26,600+34,595 = $81,195
4. Unit product cost Job P = Total manufacturing cost / Units produced
Unit product cost Job P = $81,195 / 20 = $4,060
5. Total manufacturing cost assigned to Job Q = $11,500+10,300+28,985 = $50,785
6. Unit product cost Job Q = $50,785 / 30 = $1,693
7.
Job P | Job Q | |
Total manufacturing cost | $81,195 | $50,785 |
Add: Markup@80% | 64,956 | 40,628 |
Selling price | 146,151 | 91,413 |
Units produced | 20 | 30 |
Selling price per unit | $7,308 | $3,047 |
8.
Sweeten company cost of goods sold = $81,195+50,785 = $131,980
9. Predetermined overhead = Estimated total manufacturing overhead / Estimated machine hours
Molding department = $11,750+2,500*2.10 / 2,500 = $6.8 per machine hour
Fabrication department = $16,050+1,500*$2.90 / 1,500 = $13.6 per machine hour
10.
Molding department to Job P = 2,400*$6.8 = $16,320
Molding department to Job Q = 1,500*$6.8 = $10,200
11.
Fabrication department to Job P = 1,300*$13.6 = $17,680
Fabrication department to Job Q = 1,600*$13.6 = $21,760
12.
Job P unit product cost = Direct material+Direct labor+Manufacturing overhead applied / Units
Job P unit product cost = $20,000+26,600+16,320+17,680 / 20 = $4,030 per unit
13.
Job Q unit product cost = $11,500+10,300+10,200+21,760 / 30 = $1,792 per unit
14.
Job P | Job Q | |
Total manufacturing cost | $80,600 | $53,760 |
Add: Markup@80% | 64,480 | 43,008 |
Selling price | 145,080 | 96,768 |
Units produced | 20 | 30 |
Selling per unit | $7,254 | $3,226 |
15.
Sweeten company cost of goods sold = $80,600+53,760 = $134,360
Required information [The following information applies to the questions displayed below.] Sweeten Company had no jobs...
Required information [The following information applies to the questions displayed below.] Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments--Molding and Fabrication. It started, completed, and sold only two jobs during March-Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours...
Required information (The following information applies to the questions displayed below.] Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments—Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours...
Required information [The following information applies to the questions displayed below.] Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments--Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total...
[The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments --Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours...
Required information [The following information applies to the questions displayed below) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication...
Required information [The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs Panda (all data and questions relate to the month of March): Estimated total machine-hours used...
Required information [The following information applies to the questions displayed below.] Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments--Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March-Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March) Estimated total machine-hours used Estimated total fixed manufacturing overhead Estimated variable manufacturing overhead per...
[The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours used...
Required Information [The following information applies to the questions displayed below) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication, it started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication...