Question

Required Information [The following information applies to the questions displayed below) Sweeten Company had no jobs in prog
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Molding overhead rate = (12250/2500+2.3) = 7.2 per MH

Fabrication Overhead rate = (16350/1500+3.1) = 14 per MH

Job P Job Q
Direct material 22000 12500
Direct labor 28200 11100
Molding overhead 2600*7.2 = 18720 12240
Fabrication overhead 1500*14 = 21000 25200
Total Cost 89920 61040
Total price for the Job 89920*1.8 = 161856 61040*1.8 = 109872
Selling price per unit 161856/20 = 8093 109872/30 = 3662
Add a comment
Know the answer?
Add Answer to:
Required Information [The following information applies to the questions displayed below) Sweeten Company had no jobs...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required Information [The following information applies to the questions displayed below.] Sweeten Company had no jobs...

    Required Information [The following information applies to the questions displayed below.] Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (leil data and questions relate to the month of March Estimated total...

  • Required information [The following information applies to the questions displayed below.) Sweeten Company had no jobs...

    Required information [The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs Panda (all data and questions relate to the month of March): Estimated total machine-hours used...

  • Required information [The following information applies to the questions displayed below) Sweeten Company had no jobs...

    Required information [The following information applies to the questions displayed below) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication...

  • Required information [The following information applies to the questions displayed below.) Sweeten Company had no jobs...

    Required information [The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments --Molding and Fabrication. It started, completed, and sold only two jobs during March-Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total...

  • Required information [The following information applies to the questions displayed below.] Sweeten Company had no jobs...

    Required information [The following information applies to the questions displayed below.] Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments--Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total...

  • required information [The following information applies to the questions displayed below.] Sweeten Company had no jobs...

    required information [The following information applies to the questions displayed below.] Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments--Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total...

  • [The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress...

    [The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours used...

  • [The following information applies to the questions displayed below.] Sweeten Company had no jobs in progress...

    [The following information applies to the questions displayed below.] Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments--Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated total...

  • Required information [The following information applies to the questions displayed below] Sweeten Company had no jobs...

    Required information [The following information applies to the questions displayed below] Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments --Molding and Fabrication. It started, completed, and sold only two jobs during March-Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total...

  • Required Information The following information applies to the questions displayed below! Sweeten Company had no jobs...

    Required Information The following information applies to the questions displayed below! Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March Job P and Job Q. The following additional Information is available for the company as a whole and for Jobs P and (all data and questions relate to the month of March): Estimated total machine-hours...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT