Annapolis Company completes job #601 which has a standard of 600 labor hours at a standard rate of $18.70 per hour. The job was completed in 640 hours and the average actual labor rate was $18.20 per hour. What is the labor rate variance? A negative number indicates an favorable variance and a positive number indicates an unfavorable variance.
Labor rate Variance : Actual Hour *(Actual rate - standard Rate)
=640 hrs *(18.20-18.70)
=-320 favorable variance
Annapolis Company completes job #601 which has a standard of 600 labor hours at a standard...
Annapolis Company completes job #601 which has a standard of 640 labor hours at a standard rate of $19.70 per hour. The job was completed in 600 hours and the average actual labor rate was $19.70 per hour. What is the labor efficiency (quantity) variance? A negative number indicates an favorable variance and a positive number indicates an unfavorable variance.
Annapolis Company completes job #601 which has a standard of 650 labor hours at a standard rate of $19.90 per hour. The job was completed in 560 hours and the average actual labor rate was $19.40 per hour. What is the labor efficiency (quantity) variance? A negative number indicates an favorable variance and a positive number indicates an unfavorable variance.
Direct Labor Variances Bellingham Company produces a product that requires 10 standard direct labor hours per unit at a standard hourly rate of $19.00 per hour. If 4,600 units used 46,900 hours at an hourly rate of $18.05 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct labor rate variance...
Direct Labor Variances Bellingham Company produces a product that requires 2 standard direct labor hours per unit at a standard hourly rate of $18.00 per hour. If 4,800 units used 9,900 hours at an hourly rate of $17.10 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number Favorable a. Direct labor rate...
Direct Labor Variances Bellingham Company produces a product that requires 9 standard hours per unit at a standard hourly rate of $21.00 per hour. If 2,800 units required 24,200 hours at a hourly rate of $21.84 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) total direct labor cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct labor rate...
Bellingham Company produces a product that requires 10 standard direct labor hours per unit at a standard hourly rate of $21.00 per hour. If 2,200 units used 22,900 hours at an hourly rate of $21.63 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
Direct Labor Variances Bellingham Company produces a product that requires 3 standard hours per unit at a standard hourly rate of $18.00 per hour. If 6,200 units required 18,200 hours at an hourly rate of $18.90 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) total direct labor cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct labor rate...
Direct Labor Variances Bellingham Company produces a product that requires 7 standard direct labor hours per unit at a standard hourly rate of $13.00 per hour. If 2,800 units used 20,400 hours at an hourly rate of $12.74 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct labor rate variance...
Direct Labor Variances Bellingham Company produces a product that requires 4 standard hours per unit at a standard hourly rate of $13.00 per hour. If 5,700 units required 23,700 hours at an hourly rate of $12.48 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) total direct labor cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct labor rate...
Direct Labor Variances Bellingham Company produces a product that requires 4 standard direct labor hours per unit at a standard hourly rate of $20 per hour. If 15,000 units used 61,800 hours at an hourly rate of $19.85 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct labor rate variance...