Question

Annapolis Company completes job #601 which has a standard of 600 labor hours at a standard...

Annapolis Company completes job #601 which has a standard of 600 labor hours at a standard rate of $18.70 per hour. The job was completed in 640 hours and the average actual labor rate was $18.20 per hour. What is the labor rate variance? A negative number indicates an favorable variance and a positive number indicates an unfavorable variance.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Labor rate Variance : Actual Hour *(Actual rate - standard Rate)

=640 hrs *(18.20-18.70)

=-320 favorable variance

Add a comment
Know the answer?
Add Answer to:
Annapolis Company completes job #601 which has a standard of 600 labor hours at a standard...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Annapolis Company completes job #601 which has a standard of 640 labor hours at a standard...

    Annapolis Company completes job #601 which has a standard of 640 labor hours at a standard rate of $19.70 per hour. The job was completed in 600 hours and the average actual labor rate was $19.70 per hour. What is the labor efficiency (quantity) variance? A negative number indicates an favorable variance and a positive number indicates an unfavorable variance.

  • Annapolis Company completes job #601 which has a standard of 650 labor hours at a standard...

    Annapolis Company completes job #601 which has a standard of 650 labor hours at a standard rate of $19.90 per hour. The job was completed in 560 hours and the average actual labor rate was $19.40 per hour. What is the labor efficiency (quantity) variance? A negative number indicates an favorable variance and a positive number indicates an unfavorable variance.

  • Direct Labor Variances Bellingham Company produces a product that requires 10 standard direct labor hours per...

    Direct Labor Variances Bellingham Company produces a product that requires 10 standard direct labor hours per unit at a standard hourly rate of $19.00 per hour. If 4,600 units used 46,900 hours at an hourly rate of $18.05 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct labor rate variance...

  • Direct Labor Variances Bellingham Company produces a product that requires 2 standard direct labor hours per...

    Direct Labor Variances Bellingham Company produces a product that requires 2 standard direct labor hours per unit at a standard hourly rate of $18.00 per hour. If 4,800 units used 9,900 hours at an hourly rate of $17.10 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number Favorable a. Direct labor rate...

  • Direct Labor Variances Bellingham Company produces a product that requires 9 standard hours per unit at...

    Direct Labor Variances Bellingham Company produces a product that requires 9 standard hours per unit at a standard hourly rate of $21.00 per hour. If 2,800 units required 24,200 hours at a hourly rate of $21.84 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) total direct labor cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct labor rate...

  • Bellingham Company produces a product that requires 10 standard direct labor hours per unit at a...

    Bellingham Company produces a product that requires 10 standard direct labor hours per unit at a standard hourly rate of $21.00 per hour. If 2,200 units used 22,900 hours at an hourly rate of $21.63 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

  • Direct Labor Variances Bellingham Company produces a product that requires 3 standard hours per unit at...

    Direct Labor Variances Bellingham Company produces a product that requires 3 standard hours per unit at a standard hourly rate of $18.00 per hour. If 6,200 units required 18,200 hours at an hourly rate of $18.90 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) total direct labor cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct labor rate...

  • Direct Labor Variances Bellingham Company produces a product that requires 7 standard direct labor hours per...

    Direct Labor Variances Bellingham Company produces a product that requires 7 standard direct labor hours per unit at a standard hourly rate of $13.00 per hour. If 2,800 units used 20,400 hours at an hourly rate of $12.74 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct labor rate variance...

  • Direct Labor Variances Bellingham Company produces a product that requires 4 standard hours per unit at...

    Direct Labor Variances Bellingham Company produces a product that requires 4 standard hours per unit at a standard hourly rate of $13.00 per hour. If 5,700 units required 23,700 hours at an hourly rate of $12.48 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) total direct labor cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct labor rate...

  • Direct Labor Variances Bellingham Company produces a product that requires 4 standard direct labor hours per...

    Direct Labor Variances Bellingham Company produces a product that requires 4 standard direct labor hours per unit at a standard hourly rate of $20 per hour. If 15,000 units used 61,800 hours at an hourly rate of $19.85 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct labor rate variance...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT