WACC = | 2% | |
Period | Project 1 | Project 2 |
0 | -$150 | -$60 |
1 | $100 | $50 |
2 | $75 | $35 |
3 | $80 | |
4 | ||
5 | ||
6 |
Based on the information in the table, what is the replacement chain NPV for Project 2?
As project 1 is of 3 years and 1 of 2 years the replacement will go on till project B reaches year 6. NPV is calculated below:
Project 2:
Year | CF | Discount Factor | Discounted CF | ||
0 | $ -60.00 | 1/(1+0.02)^0= | 1 | 1*-60= | $ -60.00 |
1 | $ 50.00 | 1/(1+0.02)^1= | 0.980392157 | 0.980392156862745*50= | $ 49.02 |
2 | 35-60 = $ -25.00 | 1/(1+0.02)^2= | 0.961168781 | 0.961168781237985*-25= | $ -24.03 |
3 | $ 50.00 | 1/(1+0.02)^3= | 0.942322335 | 0.942322334547045*50= | $ 47.12 |
4 | 35-60 = $ -25.00 | 1/(1+0.02)^4= | 0.923845426 | 0.923845426026514*-25= | $ -23.10 |
5 | $ 50.00 | 1/(1+0.02)^5= | 0.90573081 | 0.905730809829916*50= | $ 45.29 |
6 | $ 35.00 | 1/(1+0.02)^6= | 0.887971382 | 0.887971382186192*35= | $ 31.08 |
NPV = Sum of all Discounted CF | $ 172.50 |
In years 2 and 4 the project will be replaced
Replacement NPV for project 1 is given below:
Year | CF | Discount Factor | Discounted CF | ||
0 | $ -150.00 | 1/(1+0.02)^0= | 1 | 1*-150= | $ -150.00 |
1 | $ 100.00 | 1/(1+0.02)^1= | 0.980392157 | 0.980392156862745*100= | $ 98.04 |
2 | $ 75.00 | 1/(1+0.02)^2= | 0.961168781 | 0.961168781237985*75= | $ 72.09 |
3 | 80-100 = $ -70.00 | 1/(1+0.02)^3= | 0.942322335 | 0.942322334547045*-70= | $ -65.96 |
4 | $ 100.00 | 1/(1+0.02)^4= | 0.923845426 | 0.923845426026514*100= | $ 92.38 |
5 | $ 75.00 | 1/(1+0.02)^5= | 0.90573081 | 0.905730809829916*75= | $ 67.93 |
6 | $ 80.00 | 1/(1+0.02)^6= | 0.887971382 | 0.887971382186192*80= | $ 71.04 |
NPV = Sum of all Discounted CF | $ 401.48 |
WACC = 2% Period Project 1 Project 2 0 -$150 -$60 1 $100 $50 2 $75...
WACC = 2% Period Project 1 Project 2 0 -$150 -$60 1 $100 $50 2 $75 $35 3 $80 4 5 6 Based on the information in the table, what is the replacement chain NPV for Project 2? Group of answer choices $65.38 $22.66 $45.32 $78.45
WACC = 8% Period Project 1 Project 2 0 -$200 -$75 1 $100 $100 2 $75 $25 3 $80 4 5 6 Based on the information in the table, what is the replacement chain NPV for Project 1? $20.40 $40.80 $43.91 $36.59
WACC = 6% Project Project Period -$150 $100 $75 $80 $75 $100 $25 Based on the information in the table, what is the replacement chain NPV for Project 2? $111.55 $41.59 $83.18 $133.86
WACC = 4% Period Project 1 Project 2 0 $150 -$60 1 $90 $50 2 $75 $35 3 $60 4 5 6 Based on the information in the table, what is the equivalent annuity for Project 1?
please answer Question 5 20 pts WACC = 8% Period Project Project 1 -$200 -$75 $100 $100 $75 $25 $80 O Based on the information in the table, what is the replacement chain NPV for Project 1? $36.59 $20.40 o $40.80 $43.91
please answer 20 pts Question 2 LO3 WACC = 5% Period Project 1 Project 2 -$75 -$150 0 $90 1 $35 $75 $70 2 $60 3 4 5 Based on the information in the table, what is the equivalent annuity for Project 2? $11.74 O $21.83 O$14.09 O $18.55 $10.91
please answer Question 1 20 pts LO3 WACC = Period 4% Project 1 Project 2 -$150 - $60 $90 $50 $35 $75 $60 Based on the information in the table, what is the equivalent annuity for Project 1? O $21.34 O $59.22 $25.61 O $50.34 O $19.74
Considering the following two projects, if the WACC =10%, then I should: Project Year 0 1 2 3 4 A Cash flows -$100 $50 $60 $70 $80 B Cash flows -$100 $50 $50 $50 $50 Accept project A since its NPV = $102.27 is higher than project B’s NPV = $58.49 Accept project B since its NPV = $102.27 is higher than project A’s NPV = $58.49 Project A’s NPV = - $102.27. Thus, I shall reject project A and...
AFC $300 150 100 75 AVC $100 75 70 73 T Outpuit 1 2 3 4 5 6 7 8 9 10 60 80 ATC $400 225 170 148 140 140 146 156 171 190 MC $100 50 60 80 110 140 180 230 290 360 90 50 43 103 38 33 30 119 138 160 The accompanying table shows cost data for a firm that is selling in a purely competitive market. If the market price for the firm's...
100 80- 60 40- 25 50 75 100 125 150 m/z