•Festa Oy’s one cost centre has indirect costs of: –Variable indirect costs 70000 € –Fixed indirect...

•Festa Oy’s one cost centre has indirect costs of:

–Variable indirect costs 70000 €

–Fixed indirect costs 28000 €

–Total 98000€

•In this cost centre, machine hours are used in measuring the level of activity.

•The normal level of activity is 700 and the real level of activity is 600 machine hours.

•One product has direct material costs 50 €/piece and direct labour costs 100 €/piece

•In producing this product, the cost centre in question is used for 3 machine hours. Other cost centres are not used in the production of this product.

•What is the minimum production value and the normal production value of this product?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Particulars Minimum production value(600 hrs) Normal production value(700 hrs)

Direct material costs 10000 10000

Direct labour costs 20000    20000   

Indirect costs

Variable costs 70000 70000

Fixed costs 28000 28000

Total cost 128000 128000

No of units produced 600/3=200 700/3=233

cost per unit 640 Euros 549 Euros

Add a comment
Know the answer?
Add Answer to:
•Festa Oy’s one cost centre has indirect costs of: –Variable indirect costs 70000 € –Fixed indirect...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for 2019 for...

    Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools: Fabrication Department Finishing Department Maintenance. ... Materials handling Machine setups Inspections .. $ 20,000 30,000 70,000 $10,000 15,000 5,000 25,000 $55,000 Cost Driver Machine hours Material moves Machine setups Inspection hours $120,000 The following activity predictions were also made for the year: Fabrication Department Finishing Department Machine hours .. Materials moves.. Machine setups Inspection hours. 10,000 3,000 700 5,000...

  • Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for 2016 for...

    Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for 2016 for the given activity cost pools Fabrication Department Finishing Department Cost Driver Maintenance Materials handling Machine setups Inspections $65,000 30,000 70,000 $55,000 Machine hours 15,000 Material moves 5,000 Machine setups 25,000 Inspection hours 165,000 $100,000 The following activity predictions were also made for the year Machine hours Material moves Machine setups Inspection hours Fabrication Department Finishing Department 5,000 1,500 50 1,000 10,000 3,000 700 It...

  • Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for 2016 for...

    Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for 2016 for the given activity cost pools: Maintenance Materials handling Machine setups Inspections Fabrication Department Finishing Department Cost Driver $35,000 $25,000 Machine hours 30,000 15,000 Material moves 70,000 5,000 Machine setups 25,000 Inspection hours $135,000 $70,000 The following activity predictions were also made for the year: Machine hours Material moves Machine setups Inspection hours Fabrication Department Finishing Department 10,000 5,000 3,000 1,500 700 1,000 50 It...

  • Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for 2016 for...

    Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for 2016 for the given activity cost pools Fabrication Department Finishing Department Cost Driver Maintenance Materials handling Machine setups Inspections $35,000 30,000 70,000 $25,000 Machine hours 15,000 Material moves 5,000 Machine setups 25,000 Inspection hours $135,000 $70,000 The following activity predictions were also made for the year: Machine hours Material moves Machine setups Inspection hours Fabrication Department Finishing Department 5,000 1,500 50 1,000 10,000 3,000 700 It...

  • lack Corporation has the following ost pools: predicted indirect costs and cost drivers 2018 18 te...

    lack Corporation has the following ost pools: predicted indirect costs and cost drivers 2018 18 te givell deuoll Finishing Department Cost Driver Maintenance Materials handling Machine setups Inspections Fabrication Department $65,000 30,000 70,000 $55,000 Machine hours 15,000 Material moves 5,000 Machine setups 25,000 Inspection hours $165,000 $100,000 The following activity predictions were also made for the year: Machine hours Material moves Machine setups Inspection hours Fabrication Department Finishing Department 5,000 1,500 50 1,000 10,000 3,000 700 It is assumed that...

  • Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for 2019 for...

    Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools: Fabrication Department Finishing Department Cost Driver Maintenance $20,000 $10,000 Machine hours Materials handling 30,000 15,000 Material moves Machine setups 70,000 5,000 Machine setups Inspections 25,000 inspection hours $120,000 $55,000 The following activity predictions were also made for the year: Fabrication Department Finishing Department Machine hours 10,000 5,000 Material moves 3,000 1,500 Machine setups 700 50 Inspection hours 1,000 It...

  • Activity-Based Costing Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for...

    Activity-Based Costing Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools: Fabrication Finishing Dement Department Center Maintenance 550.000 10000 Machine hours handing 90,000 45.000 Materal moves Machine 200.000 15.000 chines Inspections M The following activity predictions were also made for the years Fabrication Finishing Department Department Machine hours Material moves Machine Setups 350 5.00 It is assumed that the cost per unit of activity for a given activity does not...

  • Bonita Inc. has identified the following overhead costs and cost drivers for next year. Overhead Item...

    Bonita Inc. has identified the following overhead costs and cost drivers for next year. Overhead Item Expected Cost Cost Driver Expected Actual Transactions Setup costs $87,912 No. of setups 396 Ordering costs 46,800 No. of orders 3,900 Maintenance costs 125,000 Machine hours 25,000 Power 26,495 Kilowatt hours 75,700 The following are two of the jobs completed during the year: Job 700 Job 701 Direct materials $1,200 $600 Direct labour $890 $420 Units completed 250 100 Direct labour hours 40 20...

  • Stanley Company has identified the following activities related to indirect production costs: Activity Activity Costs Cost...

    Stanley Company has identified the following activities related to indirect production costs: Activity Activity Costs Cost Drivers Machine Setup $180,000 1,500 setup hours Materials Handling $50,000 12,500 pounds of materials Electric Power $20,000 20,000 kilowatt hours Stanley Company has obtained the following data concerning two products: Product 1 Product 2 Number of units produced 4,000 20,000 Direct materials cost $20,000 $25,000 Direct labor cost $12,000 $20,000 Number of setup hours 100 120 Pounds of materials used 500 1,500 Kilowatt-hours 1,000...

  • Activity-Based Costing Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for...

    Activity-Based Costing Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools: Finishing Department Department Fabrication Cost Driver $ 30,000 15,000 Machine hours Maintenance Materials handling 22,500 Material moves 45,000 Machine 7,500 Machine setups 105,000 Inspections 37,500 Inspection hours $180,000 $82,500 Total The following activity predictions were also made for the year: Finishing Fabrication Department Department Machine hours 5,000 2,500 Material moves 1,500 750 Machine setups 350 25 Inspection hours 500...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT