Bonita Inc. has identified the following overhead costs and cost
drivers for next year.
Overhead Item | Expected Cost | Cost Driver | Expected Actual Transactions | |||||||
Setup costs | $87,912 | No. of setups | 396 | |||||||
Ordering costs | 46,800 | No. of orders | 3,900 | |||||||
Maintenance costs | 125,000 | Machine hours | 25,000 | |||||||
Power | 26,495 | Kilowatt hours | 75,700 |
The following are two of the jobs completed during the
year:
Job 700 | Job 701 | ||||||||
Direct materials | $1,200 | $600 | |||||||
Direct labour | $890 | $420 | |||||||
Units completed | 250 | 100 | |||||||
Direct labour hours | 40 | 20 | |||||||
Number of setups | 2 | 1 | |||||||
Number of orders | 11 | 4 | |||||||
Machine hours | 50 | 37 | |||||||
Kilowatt hours | 65 | 28 |
The company's normal activity is 4,800 direct labour hours.
Determine the unit cost for each job using direct labour hours
to apply overhead. (Round overhead rate and final
answers to 2 decimal places, e.g. 15.25.)
Cost | ||||
Job 700 | $ | per unit | ||
Job 701 | $ | per unit |
Determine the unit cost for each job using the four cost
drivers. (Round overhead rates and final answers to 2
decimal places, e.g. 15.25.)
Cost | ||||
Job 700 | $ | per unit | ||
Job 701 | $ | per unit |
Bonita Inc. has identified the following overhead costs and cost drivers for next year. Overhead Item...
Orange, Inc. has identified the following cost drivers for its expected overhead costs for the year: Expected Quantity 250 1,500 2,000 4,000 Expected Cost Overhead Item Cost Driver $ 59,500 Number of setups Setup costs Ordering costs Maintenance Power Total Overhead 49,000 Number of orders 138,000 Machine hours 29,500 Kilowatt hours $ 276,000 Total direct labor hours budgeted - 2,000 hours The following actual data applies to one of the products completed during the year: Product X Direct materials Direct...
Orange, Inc. has identified the following cost drivers for its expected overhead costs for the year: Cost Pools Budgeted Cost Cost Driver Cost Driver Level Setup $ 220,000 Number of setups 1,100 Ordering 110,000 Number of orders 5,500 Maintenance 275,000 Machine hours 27,500 Power 55,000 Kilowatt hours 55,000 Total direct labor hours budgeted = 11,000 hours. The following data applies to Product X, one of the products completed during the year. Direct materials $ 5,500 Direct labor $ 6,600 Units...
Orange, Inc. has identified the following cost drivers for its expected overhead costs for the Cost Pools Setup Ordering Maintenance Power Budgeted Cost $70,000 35,000 87,500 17,500 Cost Driver Number of setups Number of orders Machine hours Kilowatt hours Cost Driver Level 350 1,750 8,750 17,500 Total direct labor hours budgeted = 3,500 hours. The following data applies to Product X, one of the products completed during the year. Direct materials Direct labor Units completed Direct labor hours Number of...
Orange, Inc. has identified the following cost drivers for its expected overhead costs for the year: Cost Pools Budgeted Cost Cost Driver Cost Driver Level Setup $ 61,000 Number of setups 305 Ordering 30,500 Number of orders 1,525 Maintenance 76,250 Machine hours 7,625 Power 15,250 Kilowatt hours 15,250 Total direct labor hours budgeted = 3,050 hours. The following data applies to Product X, one of the products completed during the year. Direct materials $ 1,525 Direct labor $ 1,830 Units...
same question in both pictures 20) The Gardenview Corporation has identified the following overhead costs and activity drivers for next year: Overhead Item Expected Cost Activity Driver Expected Quantity Setup costs $ 200,000 Number of setups 250 Ordering costs 80,000 Number of orders 1,600 Manintenance 400,000 Machine hours 2,000 Power 40,000 Kilowatt hours 40,000 The following are two of the jobs completed during the year: JOB 6A JOB 8B Direct materials $ 3,000 $ 4,000 Direct labor $ 2,800 $...
ng Company has established the following overhead cost pools and cost drivers for the month of May: Cost Pool Overhead Costs Cost Driver Levels Purchase orders $ 23,000 20 orders Machine setups 40,000 100 setups Electricity 26,000 26,000 kilowatt hours The following information pertains to the actual consumption of activity resources for two sample jobs completed during May. Job M1 Job M2 Number of units produced 590 1,000 Number of purchase orders 10 5 Number of setups 20 5 Number...
Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $480,850 Number of setups 590 Ordering costs 425,500 Number of orders 18,500 Machine costs 700,400 Machine hours 41,200 Receiving 298,800 Receiving hours 8,300 Deoro produces two models of dishwashers with the following expected prime costs and activity demands: Model A Model B Direct materials $570,000 $821,000 Direct labor $462,000 $472,000 Units completed 16,500 8,800...
Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $469,800 Number of setups 580 Ordering costs 348,000 Number of orders 17,400 Machine costs 747,000 Machine hours 41,500 Receiving 462,000 Receiving hours 10,500 Deoro produces two models of dishwashers with the following expected prime costs and activity demands: Model A Model B Direct materials $647,000 $779,000 Direct labor $471,000 $484,000 Units completed 15,600 7,200...
Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $501,760 Number of setups 640 Ordering costs 384,000 Number of orders 19,200 Machine costs 913,000 Machine hours 41,500 Receiving 323,700 Receiving hours 8,300 Deoro produces two models of dishwashers with the following expected prime costs and activity demands: Model A Model B Direct materials $647,000 $773,000 Direct labor $486,000 $451,000 Units completed 16,200 7,500...
Wang Company has established the following overhead cost pools and cost drivers for the month of May. Cost Pool Purchase orders Machine setups Electricity Overhead Costs $22,800 40,eee 26,000 Cost Driver Levels 20 orders 108 setups 26,000 kilowatt hours The following information pertains to the actual consumption of activity resources for two sample jobs completed during May. Job Mi 560 Job M2 1,000 Number of units produced Number of purchase orders Number of setups Number of kilowatt hours le le...