Question

Orange, Inc. has identified the following cost drivers for its expected overhead costs for the year:...

Orange, Inc. has identified the following cost drivers for its expected overhead costs for the year:

Cost Pools Budgeted Cost Cost Driver Cost Driver Level
Setup $ 61,000 Number of setups 305
Ordering 30,500 Number of orders 1,525
Maintenance 76,250 Machine hours 7,625
Power 15,250 Kilowatt hours 15,250

Total direct labor hours budgeted = 3,050 hours.

The following data applies to Product X, one of the products completed during the year.

Direct materials $ 1,525
Direct labor $ 1,830
Units completed 160
Direct labor hours 61
Number of setups 6
Number of orders 12
Machine hours 60
Kilowatt hours 120

If a volume-based costing system based on direct labor hours to assign overhead is used, the total overhead cost for Product X will be:

Multiple Choice

  • $2,124.

  • $2,184.

  • $3,050.

  • $3,660.

  • $3,184.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Correct answer-----------$3,660

Working

(A) Budgeted Manufacturing Overheads $ 183,000*
(B) Budgeted Direct labor hours 3,050
C= (A/B) Predetermined Overhead rate $ 60.00
(D) Actual Direct labor hours 61
E=(DxC) Overheads Applied $ 3,660

*Budgeted cost = 61000+30500+76250+15250

Add a comment
Know the answer?
Add Answer to:
Orange, Inc. has identified the following cost drivers for its expected overhead costs for the year:...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Orange, Inc. has identified the following cost drivers for its expected overhead costs for the year:...

    Orange, Inc. has identified the following cost drivers for its expected overhead costs for the year: Cost Pools Budgeted Cost Cost Driver Cost Driver Level Setup $ 220,000 Number of setups 1,100 Ordering 110,000 Number of orders 5,500 Maintenance 275,000 Machine hours 27,500 Power 55,000 Kilowatt hours 55,000 Total direct labor hours budgeted = 11,000 hours. The following data applies to Product X, one of the products completed during the year. Direct materials $ 5,500 Direct labor $ 6,600 Units...

  • Orange, Inc. has identified the following cost drivers for its expected overhead costs for the Cost...

    Orange, Inc. has identified the following cost drivers for its expected overhead costs for the Cost Pools Setup Ordering Maintenance Power Budgeted Cost $70,000 35,000 87,500 17,500 Cost Driver Number of setups Number of orders Machine hours Kilowatt hours Cost Driver Level 350 1,750 8,750 17,500 Total direct labor hours budgeted = 3,500 hours. The following data applies to Product X, one of the products completed during the year. Direct materials Direct labor Units completed Direct labor hours Number of...

  • Orange, Inc. has identified the following cost drivers for its expected overhead costs for the year:...

    Orange, Inc. has identified the following cost drivers for its expected overhead costs for the year: Expected Quantity 250 1,500 2,000 4,000 Expected Cost Overhead Item Cost Driver $ 59,500 Number of setups Setup costs Ordering costs Maintenance Power Total Overhead 49,000 Number of orders 138,000 Machine hours 29,500 Kilowatt hours $ 276,000 Total direct labor hours budgeted - 2,000 hours The following actual data applies to one of the products completed during the year: Product X Direct materials Direct...

  • Bonita Inc. has identified the following overhead costs and cost drivers for next year. Overhead Item...

    Bonita Inc. has identified the following overhead costs and cost drivers for next year. Overhead Item Expected Cost Cost Driver Expected Actual Transactions Setup costs $87,912 No. of setups 396 Ordering costs 46,800 No. of orders 3,900 Maintenance costs 125,000 Machine hours 25,000 Power 26,495 Kilowatt hours 75,700 The following are two of the jobs completed during the year: Job 700 Job 701 Direct materials $1,200 $600 Direct labour $890 $420 Units completed 250 100 Direct labour hours 40 20...

  • A company has identified the following overhead costs and cost drivers for the coming year: (CIA...

    A company has identified the following overhead costs and cost drivers for the coming year: (CIA adapted) Overhead Item Machine setup Inspection Material handling Engineering Cost Driver Budgeted Cost Number of setups $ 20,000 Number of inspections 130,000 Number of material moves 80,000 Engineering hours 50,000 Budgeted Activity Level 200 6,500 8,000 1,000 Budgeted direct labor cost was $100,000 and budgeted direct material cost was $280,000. The following Information was collected on three jobs that were completed during the year:...

  • A company has identified the following overhead costs and cost drivers for the coming year:              ...

    A company has identified the following overhead costs and cost drivers for the coming year:                        Budgeted   Overhead Item   Cost Driver Budgeted Cost    Activity Level   Machine setup   Number of setups $ 12,000           150           Inspection   Number of inspections 85,000         4,250           Material handling   Number of material moves 66,000         5,500           Engineering   Engineering hours 11,000         550                 Budgeted direct labor cost was $87,000 and budgeted direct material cost was $241,600. The following information was collected on...

  • same question in both pictures 20) The Gardenview Corporation has identified the following overhead costs and...

    same question in both pictures 20) The Gardenview Corporation has identified the following overhead costs and activity drivers for next year: Overhead Item Expected Cost Activity Driver Expected Quantity Setup costs $ 200,000 Number of setups 250 Ordering costs 80,000 Number of orders 1,600 Manintenance 400,000 Machine hours 2,000 Power 40,000 Kilowatt hours 40,000 The following are two of the jobs completed during the year: JOB 6A JOB 8B Direct materials $ 3,000 $ 4,000 Direct labor $ 2,800 $...

  • Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year:...

    Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $469,800 Number of setups 580 Ordering costs 348,000 Number of orders 17,400 Machine costs 747,000 Machine hours 41,500 Receiving 462,000 Receiving hours 10,500 Deoro produces two models of dishwashers with the following expected prime costs and activity demands: Model A Model B Direct materials $647,000 $779,000 Direct labor $471,000 $484,000 Units completed 15,600 7,200...

  • Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year:...

    Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $480,850 Number of setups 590 Ordering costs 425,500 Number of orders 18,500 Machine costs 700,400 Machine hours 41,200 Receiving 298,800 Receiving hours 8,300 Deoro produces two models of dishwashers with the following expected prime costs and activity demands: Model A Model B Direct materials $570,000 $821,000 Direct labor $462,000 $472,000 Units completed 16,500 8,800...

  • Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year:...

    Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $501,760 Number of setups 640 Ordering costs 384,000 Number of orders 19,200 Machine costs 913,000 Machine hours 41,500 Receiving 323,700 Receiving hours 8,300 Deoro produces two models of dishwashers with the following expected prime costs and activity demands: Model A Model B Direct materials $647,000 $773,000 Direct labor $486,000 $451,000 Units completed 16,200 7,500...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT