Question

Required information [The following information applies to the questions displayed below.) A manufactured product has the fol

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Actual Cost Standard cost SR AH 24500 AR $17.50 AH 24500 SH 24900 SR $17.00 $17.00 $428,750.00 $416,500.00 $423,300.00 $12,25

Add a comment
Know the answer?
Add Answer to:
Required information [The following information applies to the questions displayed below.) A manufactured product has the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information [The following information applies to the questions displayed below.) A manufactured product has the...

    Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Standard 5 lbs. @ $8 per lb. 3 hrs. @ $17 per hr. 3 hrs. @ $13 per hr. Actual 42.100 lbs. lbs. @ $8.20 per lb. 24,500 hrs. @ $17.50 per hr. $329,000 Direct labor Overhead Units manufactured 8,300 Compute the direct labor rate variance and the direct labor efficiency variance. (Indicate the effect of each variance...

  • Required information [The following information applies to the questions displayed below.) A manufactured product has the...

    Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Actual Direct materials 42,100 lbs. @ $8.20 per Direct labor Standard 5 lbs. @ $8 per lb. 3 hrs. @ $17 per hr. 3 hrs. @ $13 per hr. lb. hrs. @ $17.50 per 24,500 hr. $329,000 Overhead Units manufactured 8,300 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of each variance by...

  • Required information [The following information applies to the questions displayed below.) A manufactured product has the...

    Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June Direct materials Direct labor Overhead Units manufactured Standard 5 lbs. @ $8 per lb. 3 hrs. @ $17 per hr. 3 hrs. @ $13 per hr. Actual 42,100 lbs. @ $8.20 per lb. 24,500 hrs. @ $17.50 per hr. $329,000 8,300 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of each variance by...

  • Required information [The following information applies to the questions displayed below.) A manufactured product has t...

    Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June Direct materials Direct labor Overhead Units manufactured Standard 5 lbs. @ $8 per lb. 3 hrs. @ $17 per hr. 3 hrs. @ $13 per hr. Actual 42,100 lbs. @ $8.20 per lb. 24,500 hrs. @ $17.50 per hr. $329,000 8,300 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of each variance by...

  • Required information (The following information applies to the questions displayed below.) A manufactured product has the...

    Required information (The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. $7 per lb.) (3 hrs. $17 per hr.) (3 hrs. @ $12 per hr.) Actual 50, 200 lbs. @ $7.10 per lb. 24,600 hrs. @ $17.50 per hr. $304,000 8,300 Compute the direct labor rate variance and the direct labor efficiency variance. Indicate whether each variance is favorable or unfavorable....

  • Required information [The following information applies to the questions displayed below] A manufactured product has the...

    Required information [The following information applies to the questions displayed below] A manufactured product has the following information for June. Standard Actual Direct materials Direct labor Overhead (6 lbs. $7 per 1b.) (2 hrs. $17 per hr.) (2 hrs. $11 per hr.) 48,000 lbs.e $7.20 per 1b. 15,5ee hrs.@ $17.50 per hr. $179,4e0 7,900 Units manufactured Compute the direct materials price variance and the direct materials quantity variance. Indicate whether each variance is favorable or unfavorable. AQ= Actual Quantity SQ-...

  • Required information [The following information applies to the questions displayed below.] A manufactured product has the...

    Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (7 lbs. @ $8 per lb.) (2 hrs. @ $15 per hr.) (2 hrs. @ $11 per hr.) Actual 55,900 lbs. @ $8.10 per lb. 15,500 hrs. @ $15.40 per hr. $179, 700 7,900 Compute the direct materials price variance and the direct materials quantity variance. Indicate whether each variance is favorable...

  • Required information [The following information applies to the questions displayed below.] A manufactured product has the...

    Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard Actual Direct materials 5 lbs. @ $9 per lb. 40,400 lbs. @ $9.20 per lb. Direct labor 3 hrs. @ $15 per hr. 23,700 hrs. @ $15.60 per hr. Overhead 3 hrs. @ $12 per hr. $ 294,800 Units manufactured 8,000 Compute the direct labor rate variance and the direct labor efficiency variance. (Indicate the effect of each variance...

  • Required information The following information applies to the questions displayed below. A manufactured product has the...

    Required information The following information applies to the questions displayed below. A manufactured product has the following information for June Standard 5 lbs. 2 S8 per Actual Direct materials 42.100 lbs. @ $8.20 per 42,100 lb s hrs. @ $17.50 per Direct labor 3 hrs. @ $17 per hr. 3 hrs. $13 per hr Overhead Units manufactured 200 $329,000 8,300 (1) Compute the standard cost per unit. (2) Compute the total cost variance for June Complete this question by entering...

  • Required information (The following information applies to the questions displayed below.] A manufactured product has t...

    Required information (The following information applies to the questions displayed below.] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. @ $7 per lb.) (3 hrs. @ $16 per hr.) (3 hrs. @ $12 per hr.) Actual 43,800 lbs. @ $7.20 per lb. 21,300 hrs. @ $16.40 per hr. $264,300 7,200 Compute the direct materials price variance and the direct materials quantity variance. Indicate whether each variance is favorable or...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT