Polk Company | |||||||
Equivalent units | |||||||
Physical | Mateials | Conversion | |||||
units | costs | ||||||
Quantities | |||||||
Units to be accounted for | |||||||
Work in process,July 1 | 590 | ||||||
Started into production | 1,230 | ||||||
Total units | 1820 | ||||||
Units accounted for | |||||||
Transferred out | 1290 | 1290 | 1290 | ||||
Work in process,July 31 | 530 | 530 | 212 | ||||
Total units | 1820 | 1820 | 1502 | ||||
Costs | Materials | CC | Total | ||||
Unit costs | |||||||
Costs in July | 3710 | 3640 | 7350 | ||||
Equivalent units | 1820 | 1502 | |||||
unit costs | 2.04 | 2.42 | 4.46 | ||||
Costs to be accounted for | |||||||
Work in process July 1 | 1,360 | ||||||
Started into production | 5990 | ||||||
Total costs | 7,350 | ||||||
Cost Reconcilation Scheule | |||||||
Cost accounted for | |||||||
Transferred out | 5756 | ||||||
Work in process,July 31 | |||||||
Materials | 1080 | ||||||
Conversion costs | 514 | 1594 | |||||
Total costs | 7350 | ||||||
Problem 17-5A (Part Level Submission) Polk Company manufactures basketballs. Materials are added at the beginning of...
Polk Company manufactures basketballs. Materials are added at the beginning of the production process and conversion costs are incurred uniformly. Production and cost data for the month of July 2020 are as follows. Percent Complete Production Data-Basketballs Units Work in process units, July 1 550 60 % Units started into production 1,400 Work in process units, July 31 600 40 % Cost Data-Basketballs Work in process, July 1 Materials $750 Conversion costs 610 $1,360 Direct materials 2,370 Direct labor 654...
Problem 3-5A (Video) (Part Level Submission) Polk Company manufactures basketballs. Materials are added at the beginning of the production process and conversion costs are incurred uniformly. Production and cost data for the month of July 2020 are as follows. Units Percent Complete 440 60 % 1,120 600 40 % Production Data-Basketballs Work in process units, July 1 Units started into production Work in process units, July 31 Cost Data-Basketballs Work in process, July 1 Materials Conversion costs Direct materials Direct...
Current Attempt in Progress Polk Company manufactures basketballs. Materials are added at the beginning of the production process and conversion costs are incurred uniformly. Production and cost data for the month of July 2020 are as follows. Percent Complete 60% Units 500 1.000 600 40% Production Data-Basketballs Work in process units, July 1 Units started into production Work in process units, July 31 Cost Data-Basketballs Work in process, July 1 Materials Conversion costs Direct materials Direct labor Manufacturing overhead $750...
Problem 16-05A Polk Company manufactures basketballs. Materials are added at the beginning of the production process and conversion costs are incurred uniformly. Production and cost data for the month of July 2020 are as follows. Production Data—Basketballs Units Percent Complete Work in process units, July 1 500 60 % Units started into production 1,000 Work in process units, July 31 600 40 % Cost Data—Basketballs Work in process, July 1 Materials $750 Conversion costs 600 $1,350 Direct materials 2,400 Direct...
P16.5A (LO 3, 4) Polk Company manufactures basketballs. Materials are added at the beginning of the production process and conversion costs are incurred uniformly. Production and cost data for the month of July 2020 are as follows. Determine equivalent units and unit costs and assign costs. Percentage Complete 60% Units 500 1,000 600 40% Production Data—Basketballs Work in process units, July 1 Units started into production Work in process units, July 31 Cost Data-Basketballs Work in process, July 1 Materials...
Polk Company manufactures basketballs. Materials are added at the beginning of the production process and conversion costs are incurred uniformly. Production and cost data for the month of July 2020 are as follows. Percent Complete 60% Units 500 1,000 600 40% Production Data-Basketballs Work in process units, July 1 Units started into production Work in process units, July 31 Cost Data-Basketballs Work in process, July 1 Materials Conversion costs Direct materials Direct labor Manufacturing overhead $750 600 $1,350 2.400 1.580...
Units Percent Complete 60 % 440 1,120 600 40 % Production Data-Basketballs Work in process units, July 1 Units started into production Work in process units, July 31 Cost Data-Basketballs Work in process, July 1 Materials Conversion costs Direct materials Direct labor Manufacturing overhead $780 620 $1,400 2,028 530 1,010 Answer CLOSE Problem 3-5A (Video) (Part Level Submission) Calculate the equivalent units of production for materials and conversion costs. Materials Conversion Costs Equivalent Units 1,560 1,200 (a2) Your answer is...
Owen Company manufactures bicycles and tricycles. For both products, materials are added at the beginning of the production process, and conversion costs are incurred uniformly. Owen Company uses the FIFO method to compute equivalent units. Production and cost data for the month of March are as follows. Production Data—Bicycles Units Percentage Complete Work in process units, March 1 200 80 % Units started into production 1,440 Work in process units, March 31 300 40 % Cost Data—Bicycles Work in process...
Owen Company manufactures bicycles and tricycles. For both products, materials are added at the beginning of the production process, and conversion costs are incurred uniformly. Owen Company uses the FIFO method to compute equivalent units. Production and cost data for the month of March are as follows. Units 210 Percentage Complete 80 % Production Data-Bicycles Work in process units, March 1 Units started into production Work in process units, March 31 1.270 300 40 % Cost Data-Bicycles Work in process...
Swifty Company manufactures basketball Materials are deathe production process and conversion costs incurred ory Production and cost data for the northet 2020 Production Data Basketballs Work in process units, July 1 Units stated into production Work in process units, fly 31 CostDataBasketball 560 Work in process, July 1 Materials Conversion costs Direct materials Direct labor Marutacturing overhead We were unable to transcribe this imagePrepare a production cost report for the month of July for the basketballs. (Round unit costs to...