Question

We are establishing a quality control program for a process and need to establish the mean and standard deviation for the process. The first 10 batches had samples of size 5 taken, and the following data were recorded. 负43.3 2.53 45.7 1.85 42.8 1.96 4 46.2 2.70 43.5 3.11 6 42.6 2.59 44.6 1.95 47.02.36 46.6 1.90 43.3 2.94 Based on this information, where should the center line for the x chart be? 44.56 0 44.3

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The center line for the ar x chart is arar x

The formula to find arar x is

arar x = Sum of all ar x / Total number of batches

445,6 = 44,56 Sum of all r z= tTotal number of batches 10

Therefore, based on the information the center line for the ar x should be 44.56

Add a comment
Know the answer?
Add Answer to:
We are establishing a quality control program for a process and need to establish the mean...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT