In order to calculate the IRR of a project, one shall use excel
to get an accurate and correct figure:
Year | Cash flow |
0 | $ (55,939.28) |
1 | $ 13,000.00 |
2 | $ 13,000.00 |
3 | $ 13,000.00 |
4 | $ 13,000.00 |
5 | $ 13,000.00 |
6 | $ 13,000.00 |
7 | $ 13,000.00 |
8 | $ 13,000.00 |
9 | $ 13,000.00 |
IRR | 18.00% |
This project shall have a single IRR because there is only one negative cash flow at the beginning.
Check My Work 11-3: Internal Rate of Return (IRR) IRR Project K costs $55,939.28, its expected...
Click here to read the eBook: Internal Rate of Return (IRR) IRR Project L costs $39,183.66, its expected cash inflows are $9,000 per year for 9 years, and its WACC is 11%. What is the project's IRR? Round your answer to two decimal places.
Project K costs $65,000, its expected cash inflows are $13,000 per year for 11 years, and its WACC is 12%. What is the project's NPV? Round your answer to the nearest cent. Project K costs $48,457.36, its expected cash inflows are $10,000 per year for 11 years, and its WACC is 12%. What is the project's IRR? Round your answer to two decimal places.
11-6: Modified Internal Rate of Return (MIRR) MIRR Project K costs $55,000, its expected cash inflows are $9,000 per year for 8 years, and its WACC is 12%. What is the project's MIRR? Round your answer to two decimal places. 6.41 % Hide Feedback Incorrect
Project K costs $66,022.66, its expected cash inflows are $13,000 per year for 11 years, and its WACC is 12%. What is the project's IRR? Round your answer to two decimal places.
IRR Project L costs $73,123.92, its expected cash inflows are $14,000 per year for 11 years, and its WACC is 9%. What is the project's IRR? Round your answer to two decimal places.
Project K costs $45,000, its expected cash inflows are $15,000 per year for 8 years, and its WACC is 11%. What is the project's MIRR? Round your answer to two decimal places. Project K costs $55,000, its expected cash inflows are $13,000 per year for 8 years, and its WACC is 7%. What is the project's discounted payback? Round your answer to two decimal places.
Project K costs $48,457.36, its expected cash inflows are $10,000 per year for 11 years, and its WACC is 12%. What is the project's IRR? Round your answer to two decimal places.
1.Project L costs $35,000, its expected cash inflows are $13,000 per year for 9 years, and its WACC is 9%. What is the project's NPV? Do not round intermediate calculations. Round your answer to the nearest cent. 2.Project L costs $50,011.04, its expected cash inflows are $12,000 per year for 8 years, and its WACC is 11%. What is the project's IRR? Round your answer to two decimal places 3.Project L costs $60,000, its expected cash inflows are $15,000 per...
IRR Project L costs $56,400.61, its expected cash inflows are $12,000 per year for 11 years, and its WACC is 10%. What is the project's IRR? Round your answer to two decimal places.
Check My Work (3 remaining) eBook Problem Walk-Through Project L requires an initial outlay at t 0 of $77,184, its expected cash inflows are $13,000 per year for 10 years, and its WACC is 10 %. What is the project's IRR? Round your answer to two decimal places. % Check My Work (3 remaining) MacBook Air