Question

Dotsero Technology, Inc., has a job-order costing system. The company uses departmental predetermined overhead rates to...

Dotsero Technology, Inc., has a job-order costing system. The company uses departmental predetermined overhead rates to apply manufacturing overhead cost to individual jobs. The predetermined overhead rate in Department A is based on machine hours, and the rate in Department B is based on direct labour hours. At the beginning of the most recent year (i.e., January 1, 2012), the company's management made the following estimates for the coming year:

Department

A B

Machine hours 80,000 21,000

Direct labour hours 35,000 65,000

Direct materials cost $190,000 $400,000

Direct labour cost $280,000 $530,000

Manufacturing overhead cost $416,000 $720,000

Job 243 entered into production on April 1, 2012, and all 24 units of product in the job were completed on May 1, 2012. The company's cost records show the following information about the job:

Department

A B

Machine hours 350 70

Direct labour hours 80 130

Direct materials cost $940 $1,200

Direct labour cost $710 $980

At the end of the year (December 31, 2012), the records of Dotsero showed the following actual total cost and operating data for all jobs worked on during the year:

Department

A B

Machine hours 73,000 24,000

Direct labour hours 30,000 68,000

Direct materials cost $165,000 $420,000

Direct labour cost $265,000 $510,000

Manufacturing overhead cost $390,000 $740,000

Required:

  1. Compute the predetermined overhead rates for Department A and Department B at the beginning of the year 2012. ( 3 marks)

  1. Compute the total overhead cost applied to Job 243 during the year 2012. ( 2 marks)

  1. What was the total cost of Job 243 once the job was completed? ( 1 mark)

  1. Compute the amount of under-applied or over-applied overhead in each department, and in total, at the end of the current year (December 31, 2012). Based on this analysis, comment on the apparent relative quality of this job costing system for generating useful cost information. Briefly justify your answer. ( 5 marks)

  1. Return to the original data at the beginning of the question. Assume that, instead of two separate departmental overhead rates, the company uses a single plant-wide overhead application rate based on direct materials cost as the allocation base. Compute the single predetermined overhead application rate for Dotsero Company as of the beginning of the year 2012, and the amount of overhead which would be applied to Job 243.  

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Estimated cost as on 01/01/2012
Dept A Dept B
Machine Hours 80000.00 21000.00
Direct Labour Hours 35000.00 65000.00
Direct Material cost $        190,000.00 $        400,000.00
Direct Labour Cost $        280,000.00 $        530,000.00
Manufacturing Overhead Cost $        416,000.00 $        720,000.00
Manufacturing Overhead Cost / machine hour $5.20 $34.29
Job No:243
Dept A Dept B
Machine Hours 350.00 70.00
Direct Labour Hours 80.00 130.00
Direct Material cost $940.00 $1,200.00
Direct Labour Cost $710.00 $980.00
Manufacturing Overhead Cost $1,820.00 $2,400.00
Total Cost $3,470.00 $4,580.00
Applied cost as on 31/12/2012
Dept A Dept B
Machine Hours 73000.00 24000.00
Direct Labour Hours 30000.00 68000.00
Direct Material cost $        165,000.00 $        420,000.00
Direct Labour Cost $        265,000.00 $        510,000.00
Manufacturing Overhead Cost $        390,000.00 $        740,000.00
Total Cost $820,000.00 $1,670,000.00
Manufacturing Overhead Cost / machine hour $5.34 $30.83
Over Applied Overhead Rate 0.14
Under applied Overhead Rate 3.45

Relative quality of this job costing system for generating useful cost information.

1. Costs are determined for Each Job order which may differ from one order to the other based on the specifications in each job. It applies mainly for the Garment & Art Industry

2. The Profit or loss for Each job can be determined against the cost and revenue of the order

3. It Facilitates in producuction planning. Standards are fixed and deviations are corrected.

Add a comment
Know the answer?
Add Answer to:
Dotsero Technology, Inc., has a job-order costing system. The company uses departmental predetermined overhead rates to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • White Company has two departments: cutting and finishing. The company uses a job-order costing system and...

    White Company has two departments: cutting and finishing. The company uses a job-order costing system and computes a predetermined overhead rate in each department. The cutting department bases its rate on machine-hours, and the finishing department bases its rate on direct labour cost. At the beginning of the year, the company made the following estimates: Department Cutting Finishing   Direct labour-hours 6,300 34,300   Machine-hours 48,250 4,300   Manufacturing overhead cost $ 472,850 $ 544,500   Direct labour cost $ 63,000 $ 302,500 Required:...

  • White Company has two departments: cutting and finishing. The company uses a job-order costing system and...

    White Company has two departments: cutting and finishing. The company uses a job-order costing system and computes a predetermined overhead rate in each department. The cutting department bases its rate on machine-hours, and the finishing department bases its rate on direct labour cost. At the beginning of the year, the company made the following estimates: Department Cutting Finishing   Direct labour-hours 6,500 34,500   Machine-hours 48,750 4,500   Manufacturing overhead cost $ 487,500 $ 553,500   Direct labour cost $ 65,000 $ 307,500 Required:...

  • Overhead Applied to Jobs, Departmental Overhead Rates Xania Inc. uses a normal job-order costing system. Currently,...

    Overhead Applied to Jobs, Departmental Overhead Rates Xania Inc. uses a normal job-order costing system. Currently, a plantwide overhead rate based on machine hours is used. Xania’s plant manager has heard that departmental overhead rates can offer significantly better cost assignments than a plantwide rate can offer. Xania has the following data for its two departments for the coming year: Department A Department B Overhead costs (expected) $100,000 $61,000 Normal activity (machine hours) 18,000 14,800 Required: 1. Compute a predetermined...

  • Overhead Applied to Jobs, Departmental Overhead Rates Xania Inc. uses a normal job-order costing system. Currently,...

    Overhead Applied to Jobs, Departmental Overhead Rates Xania Inc. uses a normal job-order costing system. Currently, a plantwide overhead rate based on machine hours is used. Xania’s plant manager has heard that departmental overhead rates can offer significantly better cost assignments than a plantwide rate can offer. Xania has the following data for its two departments for the coming year: Department A Department B Overhead costs (expected) $95,000 $48,000 Normal activity (machine hours) 12,000 3,800 Required: 1. Compute a predetermined...

  • White Company has two departments, Cutting and Finishing. The company uses a job-order costing system and...

    White Company has two departments, Cutting and Finishing. The company uses a job-order costing system and computes a predetermined overhead rate in each department. The Cutting Department bases its rate on machine-hours, and the Finishing Department bases its rate on direct labor-hours. At the beginning of the year, the company made the following estimates: Department Cutting Finishing Direct labor-hours 64,000 Machine-hours 65,000 1,300 Total fixed manufacturing overhead cost $360,000 $488,600 Variable manufacturing overhead per machine-hour 4.00 Variable manufacturing overhead per...

  • White Company has two departments, Cutting and Finishing. The company uses a job-order costing system and...

    White Company has two departments, Cutting and Finishing. The company uses a job-order costing system and computes a predetermined overhead rate in each department. The Cutting Department bases its rate on machine hours, and the Finishing Department bases its rate on direct labor-hours. At the beginning of the year, the company made the following estimates: eBook Direct labor-hours Machine-hours Total fixed namatacturing overhead cost Variable manufacturing overhead per machine-hour Variable manufacturing overhead per direct labor-hour Department Cutting Finishing 6, 700...

  • White Company has two departments, Cutting and Finishing. The company uses a job-order costing system and...

    White Company has two departments, Cutting and Finishing. The company uses a job-order costing system and computes a predetermined overhead rate in each department. The Cutting Department bases its rate on machine-hours, and the Finishing Department bases its rate on direct labor-hours. At the beginning of the year, the company made the following estimates: Direct labor-hours Machine-hours al fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour Variable manufacturing overhead per direct labor-hour Department Cutting Finishing 8,100 67,000 53,500 3,300...

  • White Company has two departments, Cutting and Finishing. The company uses a job-order costing system and...

    White Company has two departments, Cutting and Finishing. The company uses a job-order costing system and compresa predetermined overhead rate in each department. The Cutting Department bases its rate on machine hours, and the Finishing Department bases its rate on direct labor hours. At the beginning of the year, the company made the following estimates: Cutting in 55,800 3. Total Fin est rechead coat Variable tacturing overhead per machine Required: 1. Compute the predetermined overhand rate for each department 2....

  • White Company has two departments, Cutting and Finishing. The company uses a job-order costing system and...

    White Company has two departments, Cutting and Finishing. The company uses a job-order costing system and computes a predetermined overhead rate in each department. The Cutting Department bases its rate on machine-hours, and the Finishing Department bases its rate on direct labor-hours. At the beginning of the year, the company made the following estimates: Department Cutting Finishing Direct labor-hours 9,000 77,000 Machine-hours 56,600 3,600 Total fixed manufacturing overhead cost $ 390,000 $ 527,000 Variable manufacturing overhead per machine-hour $ 4.00...

  • White Company has two departments, Cutting and Finishing. The company uses a job-order costing system and...

    White Company has two departments, Cutting and Finishing. The company uses a job-order costing system and computes a predetermined overhead rate in each department. The Cutting Department bases its rate on machine-hours, and the Finishing Department bases its rate on direct labor-hours. At the beginning of the year, the company made the following estimates: Direct labor-hours Machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour Variable manufacturing overhead per direct labor-hour Department Cutting Finishing 8,500 90,000 60,700 1,100...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT