Multiply each cost with the percentages provided in the table.

This can be done by Cost * Percentage

Add the total cost of each activity cost pools of three cost

The resultant will be the cost assigned to each activity cost pools.

Please go through the following attachment for solution.

Cost Working on engagements Business Developments Others Total Wages and Salaries 207000 138000 115000 460000 460000*45% 4600

Add a comment
Know the answer?
Add Answer to:
Figge and Mathews PLC, a consulting firm, uses an activity-based costing in which there are three...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Findt & Thompson PLC, a consulting firm, uses an activity-based costing in which there are three...

    Findt & Thompson PLC, a consulting firm, uses an activity-based costing in which there are three activity cost pools. The company has provided the following data concerning its costs and its activity based costing system: Costs: Wages and salaries.. Travel expenses.. Other expenses $480,000 200,000 160,000 $840,000 Total Distribution of resource consumption: Activity Cost Pools Business Working On Engagements 60% Development 10% Other Total Wages and salaries... Travel expenses.. Other expenses. 30% 100% 55% 35% 10% 100% 20% 40% 40%...

  • Hosley Corporation uses an activity-based costing system with three activity cost pools. The company has provided...

    Hosley Corporation uses an activity-based costing system with three activity cost pools. The company has provided the following data concerning its costs: Costs: $360,000 Wages and salaries Depreciation 100,000 120,000 Осcирancy $580,000 Total The distribution of resource consumption across the three activity cost pools is given below: Activity Cost Pools Fabricating Order Processing Other Total 408 10% 100% 50% Wages and salaries 100 Depreciation 45% 10% 45% 35% 100% Осcирancy 5 % 608 How much cost, in total, would be...

  • A manufacturing company uses an activity-based costing system with three activity cost pools. The company has...

    A manufacturing company uses an activity-based costing system with three activity cost pools. The company has provided the following data concerning its costs: Costs: Wages and salaries Depreciation 5800,000 120,000 Occupancy 300,000 $1,220,000 Total The distribution of resource consumption across the three activity cost pools is given below: Activity Cost Pools Order Fabricating Processing Other Total Wages and salaries 60% 30% 10% 5% Depreciation 75% 20% 100% 100% 100% Occupancy 80% 10% 10% How much cost, in total, would be...

  • Bossie Corporation uses an activity-based costing system with three activity cost pools. The company has provided...

    Bossie Corporation uses an activity-based costing system with three activity cost pools. The company has provided the following data concerning its costs and its activity based costing system: Costs: Wages and salaries $296,000 Depreciation 236,000 Utilities 176,000 Total $708,000 Distribution of resource consumption: Activity Cost Pools Assembly Setting up Other Total Wages and salaries 50% 20% 30% 100% Depreciation 20% 35% 45% 100% Utilities 10% 70% 20% 100% How much cost, in total, would be allocated in the first-stage allocation...

  • 19. Geneva Corporation uses an activity-based costing system with three activity cost pools. The company has...

    19. Geneva Corporation uses an activity-based costing system with three activity cost pools. The company has provided the following data concerning its costs: Costs: Wages and salaries ...... Depreciation Occupancy Total $240,000 160,000 140.000 $540,000 The distribution of resource consumption across the three activity cost pools is given below: Activity Cost Pools Order Processing Fabricating 30% 20% Other 25% Total 100% 45% Wages and salaries...... Depreciation.... Occupancy 35% 100% 65% 30% 100% How much cost, in total, would be allocated...

  • 8. Bossie Corporation uses an activity-based costing system with three activity cost pools. The company has...

    8. Bossie Corporation uses an activity-based costing system with three activity cost pools. The company has provided the following data concerning its costs and its activity based costing system: How much cost, in total, would be allocated in the first-stage allocation to the Assembly activity cost pool? A. $229,600 B. $164,000 C. $215,300 D. $202,633 Costs: Wages and salaries Depreciation Utilities $261,000 252,000 143,000 $656,000 Total Total Distribution of resource consumption: Activity Cost Pools Assembly Setting up Other Wages and...

  • Eccles Corporation uses an activity-based costing system with three activity cost pools. The company has provided...

    Eccles Corporation uses an activity-based costing system with three activity cost pools. The company has provided the following data concerning its costs and its activity based costing system: Costs: Wages and salaries $ 261,000 Depreciation 252,000 Utilities 143,000 Total $ 656,000 Distribution of resource consumption: Activity Cost Pools Assembly Setting Up Other Total Wages and salaries 35% 30% 35% 100% Depreciation 35% 30% 35% 100% Utilities 25% 65% 10% 100% How much cost, in total, would be allocated in the...

  • eccles Corporation uses an activity-based costing system with three activity cost pools. The company has provided...

    eccles Corporation uses an activity-based costing system with three activity cost pools. The company has provided the following data concerning its costs and its activity based costing system: Costs: Wages and salaries $ 318,000 Depreciation 247,000 Utilities 206,000 Total $ 771,000 Distribution of resource consumption: Activity Cost Pools Assembly Setting Up Other Total Wages and salaries 45% 30% 25% 100% Depreciation 30% 10% 60% 100% Utilities 20% 50% 30% 100% How much cost, in total, would be allocated in the...

  • the question was to long for one picture. Duerr Corporation uses an activity-based costing system with three activi...

    the question was to long for one picture. Duerr Corporation uses an activity-based costing system with three activity cost pools: Fabricating. Order Processing, and other. The total costs to be assigned to the three cost pools are presented in Table 1 Table 1: Total costs to be assigned to cost pools Wages and salaries $400,000 Depreciation $180,000 Renton equipment $200,000 Total $780,000 The distribution of resource consumption across the three activity pools is presented in Table 2. Table 2: Distribution...

  • Diehl Company uses an activity-based costing system with three activity cost pools. The company has provided...

    Diehl Company uses an activity-based costing system with three activity cost pools. The company has provided the following data concering is costs and system Costs: Manufacturing overhead Selling and administrative expenses Total $180,000 100.000 $580,000 Distribution of Resource Consumption: Activity Cost Pools Order Size Customer Support 5% 85% Other Total 10% 100% Manufacturing Joverhead 20% 60% 100% 20% Selling and administrative expenses The "Other" activity cost pool consists of the costs of idle capacity and organization-sustaining costs. You have been...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT