1 | Production budget | ||||||
July | August | September | October | November | |||
Unit sales | 35,000 | 40,000 | 50,000 | 30,000 | 20,000 | ||
Desired ending inventory | 11,000 | 13,000 | 9,000 | 7,000 | 5,000 | ||
Total needed | 46,000 | 53,000 | 59,000 | 37,000 | 25,000 | ||
Less: Beginning inventory | 10,000 | 11,000 | 13,000 | 9,000 | 7,000 | ||
Units produced | 36,000 | 42,000 | 46,000 | 28,000 | 18,000 | ||
3 | Direct materials purchases budget | ||||||
July | August | September | October | November | |||
Units produced | 36,000 | 42,000 | 46,000 | 28,000 | 18,000 | ||
Direct mat. per unit | 3 | 3 | 3 | 3 | 3 | ||
Production needs | 108,000 | 126,000 | 138,000 | 84,000 | 54,000 | ||
Desired Ending Inventory | 63,000 | 69,000 | 42,000 | 27,000 | |||
Total needed | 171,000 | 195,000 | 180,000 | 111,000 | |||
Less: Beginning Inventory | 54,000 | 63,000 | 69,000 | 42,000 | |||
Direct. mat. to purchase | 117,000 | 132,000 | 111,000 | 69,000 | |||
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following Inventory requirements: a. The finished goods Inventory on hand at the end of...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (CC) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company is now planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company is now planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (CC) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...