(NPV, PI, and IRR calculations) You are considering two independent projects, project A and project B. The initial cash outlay associated with project A is $50,000 and the initial cash outlay associated with project B is $70,000. The required rate of return on both projects is 11 percent. The expected annual free cash inflows from each project are on the table below. Calculate the NPV, PI, and IRR for each project and indicate if the project should be accepted.
Project A | Project B | |
Initial Outlay | -$50,000 | -$70,000 |
Inflow year 1 | 17,000 | 18,000 |
Inflow year 2 | 17,000 | 18,000 |
Inflow year 3 | 17,000 | 18,000 |
Inflow year 4 | 17,000 | 18,000 |
inflow year 5 | 17,000 | 18,000 |
inflow year 6 | 17,000 | 18,000 |
Calculate the NPV, PI, and IRR for each project and indicate if the project should be accepted.
Since, Project A has better NPV of 21,918.50 $, PI = 1.4384 and IRR of 25.20% (Assuming it as a short term investment period) compared to Project B's NPV of 6,149$, PI = 1.0878 and IRR of 14.04%. Hence, Project A should be preferred over Project B.
(NPV, PI, and IRR calculations) You are considering two independent projects, project A and project B....
(NPV, PI, and IRR calculations) You are considering two independent projects, project A and project B. The initial cash outlay associated with project A is $50,000 and the initial cash outlay associated with project B is $70,000. The required rate of return on both projects is 11 percent. The expected annual free cash inflows from each project are on the table below. Calculate the NPV, PI, and IRR for each project and indicate if the project should be accepted. Project...
(NPV, PI, and IRR calculations) You are considering two independent projects, project A and project B. The initial cash outlay associated with project A is $55,000, and the initial cash outlay associated with project B is $75,000. The required rate of return on both projects is 10 percent. The expected annual free cash inflows from each project are in the popup window: PROJECT A PROJECT B Initial Outlay -55,000 -75,000 Inflow year 1 16,000 17,000 Inflow year 2 16,000 ...
(NPV, PV, and IRR calculations) You are considering two independent projects, project A and project B. The initial cash outlay associated with project Als $55,000 and the initial cash outlay associated with project is $75,000. The required role of return on both projects is 12 percent. The expected arvual free cash inflows from each project are in the popup window. Calculate the NPV, Pt, and IRR for each project and indicate if the project should be accepted. a. What is...
(NPV, PI, and IRR calculations) Fijisawa Inc. is considering a major expansion of its product line and has estimated the following cash flows associated with such an expansion. The initial outlay would be $1,850,000 , and the project would generate incremental free cash flows of $550,000 per year for 6 years. The appropriate required rate of return is 9% a. Calculate the NPV. b. Calculate the PI. c. Calculate the IRR. d. Should this project be accepted?
(NPV,PI, and IRR calculations) Fijisawa Inc. is considering a major expansion of its product line and has estimated the following cash flows associated with such an expansion. The initial outlay would be $1,850,000, and the project would generate incremental free cash flows of $700,000 per year for 7 years. The appropriate required rate of return is 8 percent. a. Calculate the NPV. b. Calculate the PI. c. Calculate the IRR. d. Should this project be accepted? a.What is the project's...
(NPV, PI, and IRR calculations) Fijisawa Inc. is considering a major expansion of its product line and has estimated the following cash flows associated with such an expansion. The initial outlay would be $1,850,000, and the project would generate incremental free cash flows of $500,000 per year for 55 years. The appropriate required rate of return is 77 percent. a. Calculate the NPV. b. Calculate the PI. c. Calculate the IRR. d. Should this project be accepted? a.What is the...
(Payback period, NPV, PI, and IRR calculations) You are considering a project with an initial cash outlay of $85.000 and expected free cash flows of $20,000 at the end of each year for 7 years. The required rate of return for this project is 6 percent. a. What is the project's payback period? b. What is the project's NPV? c. What is the project's PI? d. What is the project's IRR?
(Payback period, NPV, PI, and IRR calculations )You are considering a project with an initial cash outlay of 90,000 and expected free cash flows of 30,000 at the end of each year for 6 years. The required rate of return for this project is 8 percent. a. What is the project's payback period? b. What is the project's NPV ? c. What is the project's PI ? d. What is the project's IRR ?
(Payback period, NPV, PI, and IRR calculations) You are considering a project with an initial cash outlay of $85 comma 000 and expected free cash flows of $30 comma 000 at the end of each year for 6 years. The required rate of return for this project is 6 percent. a. What is the project's payback period? b. What is the project's NPV? c. What is the project's PI? d. What is the project's IRR?
(NPV, PI, and IRR calculations) Fijisawa Inc. is considering a major expansion of its product line and has estimated the following free cash flows associated with such an expansion. The initial outlay would be $1,800,000, and the project would generate incremental free cash flows of $600,000 per year for 5 years. The appropriate required rate of return is 8 percent. a. Calculate the NPV. b. Calculate the Pl. c. Calculate the IRR. d. Should this project be accepted? a. What...