NPV = PV of cash Inflows - PV of Cash outflows
Project A:
Year | CF | PVF @12% | Disc CF |
0 | $ -55,000.00 | 1.0000 | $ -55,000.00 |
1 | $ 16,000.00 | 0.8929 | $ 14,285.71 |
2 | $ 16,000.00 | 0.7972 | $ 12,755.10 |
3 | $ 16,000.00 | 0.7118 | $ 11,388.48 |
4 | $ 16,000.00 | 0.6355 | $ 10,168.29 |
5 | $ 16,000.00 | 0.5674 | $ 9,078.83 |
6 | $ 16,000.00 | 0.5066 | $ 8,106.10 |
NPV | $ 10,782.52 |
Project B:
Year | CF | PVF @12% | Disc CF |
0 | $ -75,000.00 | 1.0000 | $ -75,000.00 |
1 | $ 17,000.00 | 0.8929 | $ 15,178.57 |
2 | $ 17,000.00 | 0.7972 | $ 13,552.30 |
3 | $ 17,000.00 | 0.7118 | $ 12,100.26 |
4 | $ 17,000.00 | 0.6355 | $ 10,803.81 |
5 | $ 17,000.00 | 0.5674 | $ 9,646.26 |
6 | $ 17,000.00 | 0.5066 | $ 8,612.73 |
NPV | $ -5,106.08 |
PI = PV of Cash Inflows / PV of Cash Outflows
Project A:
Year | CF | PVF @12% | Disc CF |
1 | $ 16,000.00 | 0.8929 | $ 14,285.71 |
2 | $ 16,000.00 | 0.7972 | $ 12,755.10 |
3 | $ 16,000.00 | 0.7118 | $ 11,388.48 |
4 | $ 16,000.00 | 0.6355 | $ 10,168.29 |
5 | $ 16,000.00 | 0.5674 | $ 9,078.83 |
6 | $ 16,000.00 | 0.5066 | $ 8,106.10 |
PV of Cash Inflows | $ 65,782.52 | ||
PV of Cash Outflows | $ 55,000.00 | ||
PI | 1.20 |
Project B:
Year | CF | PVF @12% | Disc CF |
1 | $ 17,000.00 | 0.8929 | $ 15,178.57 |
2 | $ 17,000.00 | 0.7972 | $ 13,552.30 |
3 | $ 17,000.00 | 0.7118 | $ 12,100.26 |
4 | $ 17,000.00 | 0.6355 | $ 10,803.81 |
5 | $ 17,000.00 | 0.5674 | $ 9,646.26 |
6 | $ 17,000.00 | 0.5066 | $ 8,612.73 |
PV of Cash Inflows | $ 69,893.92 | ||
PV of Cash Outflows | $ 75,000.00 | ||
PI | 0.93 |
IRR is the rate at which PV of cash inflows are equal to PV of Cash Outflows.
Project A:
Year | CF | PVF @18% | Disc CF | PVF @19% | Disc CF |
0 | $ -55,000.00 | 1.0000 | $ -55,000.00 | 1.0000 | $ -55,000.00 |
1 | $ 16,000.00 | 0.8475 | $ 13,559.32 | 0.8403 | $ 13,445.38 |
2 | $ 16,000.00 | 0.7182 | $ 11,490.95 | 0.7062 | $ 11,298.64 |
3 | $ 16,000.00 | 0.6086 | $ 9,738.09 | 0.5934 | $ 9,494.65 |
4 | $ 16,000.00 | 0.5158 | $ 8,252.62 | 0.4987 | $ 7,978.70 |
5 | $ 16,000.00 | 0.4371 | $ 6,993.75 | 0.4190 | $ 6,704.79 |
6 | $ 16,000.00 | 0.3704 | $ 5,926.90 | 0.3521 | $ 5,634.28 |
NPV | $ 961.64 | $ -443.56 |
IRR = Rate at which least +ve NPV + [ NPV at that rate / CHange in NPV due to 1% inc in DIsc rate ] * 1%
= 19% + [ 961.64 / 1405.21 ] *1%
= 19% + 0.68%
= 19.68%
Project B:
Year | CF | PVF @9% | Disc CF | PVF @10% | Disc CF |
0 | $ -75,000.00 | 1.0000 | $ -75,000.00 | 1.0000 | $ -75,000.00 |
1 | $ 17,000.00 | 0.9174 | $ 15,596.33 | 0.9091 | $ 15,454.55 |
2 | $ 17,000.00 | 0.8417 | $ 14,308.56 | 0.8264 | $ 14,049.59 |
3 | $ 17,000.00 | 0.7722 | $ 13,127.12 | 0.7513 | $ 12,772.35 |
4 | $ 17,000.00 | 0.7084 | $ 12,043.23 | 0.6830 | $ 11,611.23 |
5 | $ 17,000.00 | 0.6499 | $ 11,048.83 | 0.6209 | $ 10,555.66 |
6 | $ 17,000.00 | 0.5963 | $ 10,136.54 | 0.5645 | $ 9,596.06 |
NPV | $ 1,260.62 | $ -960.57 |
IRR = Rate at which least +ve NPV + [ NPV at that rate / CHange in NPV due to 1% inc in DIsc rate ] * 1%
= 9% + [ 1260.62 / 2221.18 ] *1%
= 9% + 0.57%
= 9.57%
Project A is selected as it has higher NPV, PI & IRR.
(NPV, PV, and IRR calculations) You are considering two independent projects, project A and project B....
(NPV, PI, and IRR calculations) You are considering two independent projects, project A and project B. The initial cash outlay associated with project A is $55,000, and the initial cash outlay associated with project B is $75,000. The required rate of return on both projects is 10 percent. The expected annual free cash inflows from each project are in the popup window: PROJECT A PROJECT B Initial Outlay -55,000 -75,000 Inflow year 1 16,000 17,000 Inflow year 2 16,000 ...
(NPV, PI, and IRR calculations) You are considering two independent projects, project A and project B. The initial cash outlay associated with project A is $50,000 and the initial cash outlay associated with project B is $70,000. The required rate of return on both projects is 11 percent. The expected annual free cash inflows from each project are on the table below. Calculate the NPV, PI, and IRR for each project and indicate if the project should be accepted. Project...
(NPV, PI, and IRR calculations) You are considering two independent projects, project A and project B. The initial cash outlay associated with project A is $50,000 and the initial cash outlay associated with project B is $70,000. The required rate of return on both projects is 11 percent. The expected annual free cash inflows from each project are on the table below. Calculate the NPV, PI, and IRR for each project and indicate if the project should be accepted. Project...
(Payback period, NPV, PI, and IRR calculations) You are considering a project with an initial cash outlay of $85 comma 000 and expected free cash flows of $30 comma 000 at the end of each year for 6 years. The required rate of return for this project is 6 percent. a. What is the project's payback period? b. What is the project's NPV? c. What is the project's PI? d. What is the project's IRR?
Payback period calculations) You are considering the independent projects project A project before an investment can be accepted, which project(s) would be nccepted? and project. Given the cash flow information in the popup Window, calculate the payback period for each. If you require a year payback i Data Table D $105 Initial Outlay Inflow year 1 Inflow year 2 Inflow year 3 Inflow year 4 Inflow year 5 PROJECT A - $1,000 700 200 300 200 500 PROJECT B -$10,500...
(Payback period, NPV, PI, and IRR calculations) You are considering a project with an initial cash outlay of $85.000 and expected free cash flows of $20,000 at the end of each year for 7 years. The required rate of return for this project is 6 percent. a. What is the project's payback period? b. What is the project's NPV? c. What is the project's PI? d. What is the project's IRR?
(Payback period, NPV, PI, and IRR calculations )You are considering a project with an initial cash outlay of 90,000 and expected free cash flows of 30,000 at the end of each year for 6 years. The required rate of return for this project is 8 percent. a. What is the project's payback period? b. What is the project's NPV ? c. What is the project's PI ? d. What is the project's IRR ?
( Payback period Calculations) You are considering three independent projects, project A, project B, and project C. Given the following cash flow information, calculate the payback period for each. if you require a 3-year payback before an investment can be accepted, which project(s) would be accepted? Project A Project B Project C Initial Outlay -$1,100 -$9,000 -$6,000 Inflow year 1 600 4,000 2,000 inflow year 2 300 3,000 2,000 inflow year 3 200 3,000 3,000 inflow year 4 100 3,000...
NPV and IRR analysis of projects Thomas Company is considering two mutually exclusive projects. The firm, which has a cost of capital of 14%, has estimated its cash flows as shown in the following table: a. Calculate the NPV of each project, and assess its acceptability. b. Calculate the IRR for each project, and assess its acceptability. a. The NPV of project A is $ (Round to the nearest cent.) Х i Data Table (Click on the icon located on...
All techniques with NPV profile - Mutually exclusive projects Projects A and B, of equal risk, are alternatives for expanding Rosa Company's capacity. The firm's cost of capital is 16%. The cash flows for each project are shown in the following table: PF a. Calculate each project's payback period. b. Calculate the net present value (NPV) for each project. c. Calculate the internal rate of return (IRR) for each project. d. Indicate which project you would recommend. a. The payback...