Question

Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month Machine Hours Electricity Costs January 2,500 $ 19,200 February 2,900 $ 22,600 March 1,900 $ 14,300 April 3,100 $ 24,600 May 3,800 $ 29,050 June 3,300 $ 23,600 July 4,100 $ 25,550 August 3,500 $ 23,550 September 2,000 $ 17,100 October 3,700 $ 27,600 November 4,700 $ 32,600 December 4,200 $ 28,550 Summary Output Regression Statistics Multiple R .956 R Square .914 Adjusted R2 .905 Standard Error 1,615.39 Observations 12.00 Coefficients Standard Error t Stat P-value Lower 95% Upper 95% Intercept 4,974.43 1,907.43 2.61 0.03 724.41 9,224.45 Machine Hours 5.76 0.56 10.30 0.00 4.51 7.00

If the controller uses the high-low method to estimate costs, the fixed cost portion of the cost equation for electricity cost is: (Round intermediate calculations to 2 decimal places.) $1,615.39. $1,862.00. $4,974.43. $24,138.00.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Machine hours Electricity Costs
High-level 4700 32600
Low-level 1900 14300
Difference 2800 18300
Unit variable cost = 18300/2800 = $6.54
Fixed cost portion = 32600-(4700*6.54)= $1862.00
Option 2 $1,862.00 is correct
Add a comment
Know the answer?
Add Answer to:
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,500 2,900 1,900 3,100 3,800 3,300 4,100 3,500 2,000 3,700 4,700 4,200 Electricity Costs $19, 200 $22,600 $14,300 $24,600 $29,050 $23,600 $25,550 $23,550 $17, 100 $27,600 $32,600 $28,550 Summary Output Regression Statistics...

  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,500 2,900 1,900 3,100 3,800 3,300 4,100 3,500 2,000 3,700 4,700 4,200 Electricity Costs $19, 200 $22,600 $14,300 $24,600 $29,050 $23,600 $25,550 $23,550 $17,100 $27,600 $32,600 $28,550 Summary Output Regression Statistics Multiple...

  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow:    Month Machine Hours Electricity Costs January 3,100 $ 18,700 February 3,500 $ 21,600 March 2,500 $ 13,800 April 3,700 $ 23,600 May 4,400 $ 28,550 June 3,900 $ 22,600 July 4,700 $ 25,050 August 4,100 $ 23,050 September 2,600 $ 16,100 October 4,300 $ 26,600 November...

  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow:    Month Machine Hours Electricity Costs January 2,600 $ 19,250 February 3,000 $ 22,700 March 2,000 $ 14,350 April 3,200 $ 24,700 May 3,900 $ 29,100 June 3,400 $ 23,700 July 4,200 $ 25,600 August 3,600 $ 23,600 September 2,100 $ 17,200 October 3,800 $ 27,700 November...

  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,600 3,000 2,000 3,200 3,900 3,400 4,200 3,600 2,100 3,800 4,800 4,300 Electricity Costs $19, 250 $22,700 $14,350 $24,700 $29,100 $23,700 $25,600 $23,600 $17,200 $27,700 $32,700 $28,600 Summary Output Regression Statistics Multiple...

  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow:      Month Machine Hours Electricity Costs January 2,600 $ 19,250 February 3,000 $ 22,700 March 2,000 $ 14,350 April 3,200 $ 24,700 May 3,900 $ 29,100 June 3,400 $ 23,700 July 4,200 $ 25,600 August 3,600 $ 23,600 September 2,100 $ 17,200 October 3,800 $ 27,700 November...

  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,500 2,900 1,900 3,100 3,800 3,300 4,100 3,500 2,000 3,700 4,700 4,200 Electricity Costs $ 18,400 $ 21,000 $ 13,500 $ 23,000 $ 28,250 $ 22,000 $ 24,750 $ 22,750 $ 15,500...

  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,500 2,900 1,900 3,100 3,800 3,300 4,100 3,500 2,000 3,700 4,700 4,200 Electricity Costs $ 18,400 $ 21,000 $ 13,500 $ 23,000 $ 28,250 $ 22,000 $ 24,750 $ 22,750 $ 15,500...

  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Electricity Hours Costs 2,500 $18,400 2,900 21,000 1,900 13,500 3,100 23,000 3,800 28, 250 3,300 22,000 4,100 24,750 3,500 22,750 2,000 15,500 3,700 26,000 4,700 31,000 4,200 27,750 Summary Output Regression Statistics Multiple...

  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow:      Month Machine Hours Electricity Costs January 2,100 $ 19,000 February 2,500 $ 22,200 March 1,500 $ 14,100 April 2,700 $ 24,200 May 3,400 $ 28,850 June 2,900 $ 23,200 July 3,700 $ 25,350 August 3,100 $ 23,350 September 1,600 $ 16,700 October 3,300 $ 27,200 November...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT