Question

A3 was ered by a customer on September 25 Dungeon Steve Coo dan ada 300 de and one of 8300 then balance in te Work Process Co
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Balance in work in process = Direct material+Direct labour+Overhead applied

= 3400+4900+(4900*200%)

= 3400+4900+9800

Balance in work in process = 18100

Add a comment
Know the answer?
Add Answer to:
A3 was ered by a customer on September 25 Dungeon Steve Coo dan ada 300 de...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT