Whispering Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period.
2020 |
2021 |
2022 |
||||
Costs to date | $257,570 | $413,310 | $609,000 | |||
Estimated costs to complete | 341,430 | 185,690 | –0– | |||
Progress billings to date | 270,000 | 551,000 | 905,000 | |||
Cash collected to date | 240,000 | 501,000 | 905,000 |
(a) Using the percentage-of-completion method,
compute the estimated gross profit that would be recognized during
each year of the construction period. (If answer is 0,
please enter 0. Do not leave any fields blank.)
Gross profit recognized in 2020 | $ | |
Gross profit recognized in 2021 | $ | |
Gross profit recognized in 2022 | $ |
(b) Using the completed-contract method, compute
the estimated gross profit that would be recognized during each
year of the construction period. (If answer is 0,
please enter 0. Do not leave any fields blank.)
Gross profit recognized in 2020 | $ | |
Gross profit recognized in 2021 | $ | |
Gross profit recognized in 2022 | $ |
Click if you would like to Show Work for this question: |
Modify Show Work |
Solution a:
Computation of % of completion, revenue recognition and Gross Profit - Whispering Construction Company | ||||||||
Year | Actual cost incurred (A) | Total cost incurred till date (B) | Total estimated Cost ( C ) | % of completion (D) (B/C) |
Contract Price (E) |
Total Revenue to be recoganized (F) (E * D) | Revenue for current period (G) | Gross Profit (H) (G - A) |
2020 | $257,570 | $257,570 | $599,000 | 43.00% | $905,000 | $389,150 | $389,150 | $131,580 |
2021 | $155,740 | $413,310 | $599,000 | 69.00% | $905,000 | $624,450 | $235,300 | $79,560 |
2022 | $195,690 | $609,000 | $609,000 | 100.00% | $905,000 | $905,000 | $280,550 | $84,860 |
Solution b:
Computation of Gross Profit - Revenue on completion - Whispering Construction Company | |||||
Year | Actual cost incurred (A) | Total cost incurred till date (B) | Total estimated Cost ( C ) |
Contract Price (D) |
Gross Profit |
2020 | $257,570 | $257,570 | $599,000 | $905,000 | $0 |
2021 | $155,740 | $413,310 | $599,000 | $905,000 | $0 |
2022 | $195,690 | $609,000 | $609,000 | $905,000 | $296,000 |
Whispering Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period 2020 2021 2022 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...
Bramble Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $272,700 $466,620 $618,000 Estimated costs to complete 333,300 139,380 –0– Progress billings to date 273,000 546,000 902,000 Cash collected to date...
Pronghorn Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $894,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $274,160 $417,200 $607,000 Estimated costs to complete 321,840 178,800 –0– Progress billings to date 272,000 550,000 894,000 Cash collected to date...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $598,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $897,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $275,080 $412,620 $607,000 Estimated costs to complete 322,920 185,380 –0– Progress billings to date 272,000 545,000 897,000 Cash collected to date...
Grouper Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2020 2021 Costs to date Estimated costs to complete Progress billings to date Cash collected to date $266,640 339,360 270,000 240,000 $412,080 193,920 545,000 495,000 2022 $617,000...
Pearl Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2020 2021 2022 $272,700 $466,620 $618,000 333,300 139,380 -0- 273,000 546,000 902,000...
Bonita Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2020 $256,280 339,720 270,000 240,000 2021 $429,120 166,880 555,000 505,000 2022 $606,000...
Problem 18-09 Shamrock Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $601,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $903,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $270,450 $492,820 $613,000 Estimated costs to complete 330,550 108,180 –0– Progress billings to date 273,000 550,000 903,000 Cash collected...
Problem 18-09 Sweet Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $605,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $909,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2020 $254,100 350,900 272,000 242,000 2021 $496,100 108,900 550,000 500,000...
Sandhill Construction Company has entered into a non-cancellable contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $650,000 and will take three years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2022 $660,000 Costs to date Estimated costs to complete Progress billings to date (non-refundable) Cash collected to date 2020 $292,500 357,500 292,500 262,500 2021 $487,500 162,500...