ANSWER:
Throughput time = Process time + Inspection time + Move time + Queue time = 0.9 hours + 0.4 hours + 2.3 hours + 4.5 hours = 8.1 hours
Delivery cycle time = Wait time + Throughput time = 10.7 hours + 8.1 hours = 18.8 hours
Manufacturing cycle efficiency = [Value-added time (Process time) ÷ Throughput time] = 0.9 hours / 8.1 hours = 0.1111 or 11.11%
2. Durkee Corporation keeps careful track of the time required to fill orders. The times required...
Vandenheuvel Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below: Hours Move time 2.3 Wait time 19.3 Queue time 11.4 Process time 1.3 Inspection time 0.9 The manufacturing cycle efficiency (MCE) was closest to: (Round your intermediate calculations to 1 decimal place.) Multiple Choice 0.16 0.02 0.08 0.34
Vandenheuvel Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below: Hours Move time 3.3 Wait time 19.7 Queue time 9.9 Process time 1.7 Inspection time 0.9 The manufacturing cycle efficiency (MCE) was closest to: 0.11 0.31 0.19 0.05
to fill orders. Data concerning 5) Santoyo Corporation keeps careful track of the time required to a particular order appear below: Hours 28.0 1.0 Inspection time 0.4 Move time 3.2 Queue time Wait time Process time 5.1 The delivery cycle time was: A) 8.3 hours B) 3.2 hours C) 37.7 hours D) 36.3 hours 35) Simkin Corporation keeps careful track of the time required to fill orders. Data concem a particular order appear below: Hours 20.6 1.9 0.1 Wait time...
Schapp Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below Hours 2.8 10.6 Move time Wait time Queue time Process time Inspection time The throughput time was:
Simkin Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below. Hours 21.9 5.8 Wait time Process time Inspection time Move time Queue time 4.0 The manufacturing cycle efficiency (MCE) was closest to:
Santoyo Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below. Wait time Process time Inspection time Move time Queue time Hours 12.9 2.0 0.4 4.6 6.3 The delivery cycle time was: Multiple Choice 0 10.9 hours O 23 8 hours Schapp Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below. Move time Wait time Queue time Process time Inspection time...
Schapp Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below: Hours 4.6 12.4 Move time Wait time Queue time Process time Inspection time 8.8 3.5 2.4 The throughput time was: Multiple Choice 19.3 hours 31.7 hours 0 212 hours 10.5 hours
Santoyo Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Hours Wait time 13.7 Process time 2.8 Inspection time 0.4 Move time 3.4 Queue time 7.1 The delivery cycle time was: Multiple Choice 10.5 hours 3.4 hours 27.4 hours 24.2 hours
Tanouye Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Hours Wait time 28.4 Process time 3.6 Inspection time 0.6 Move time 4.2 Queue time 9.7 The throughput time was:
Rotan Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below: Hours Move time Wait time Queue time Process time Inspection time 12.6 6.8 2.9 1.9 The throughput time was: Multiple Choice O 97 hours 16 Shares The throughput time was: Multiple Choice o 9.7 hours o 16.5 hours o o 19.4 hours