Answer:- 1)- Throughput Time = Process time + Inspection time + Move time + Queue time
=2.5 days+ 0.4 days+ 1.0 days+ 4.5 days
= 8.4 days
2)-Manufacturing cycle efficiency (MCE)= Value added time/ Throughput time
=(2.5 days/8.4 days)*100
= 30%
Where:-
Value added time =Process time
3)- The percentage of throughput time was spent in non-value-added activities= 1- Manufacturing cycle efficiency
= 1.00-0.30
=0.70 or 70%
4)- Delivery cycle time = Wait time + Throughput time
= 15.4 days+ 8.4 days
= 23.8 days
5)- New Manufacturing cycle efficiency (MCE)= 64.1%
Explanation- New Throughput Time = Process Time + Inspection Time + Move Time
= 2.5 days+0.4 days+ 1.0 days
= 3.9 days
New Manufacturing cycle efficiency (MCE)= Value added time/ New Throughput
Time
= (2.5 days/3.9 days)*100
= 64.1%
Chapter 10 Homework 0 Helps Management of Mittel Rhein AG of Köln, Germany, would like to...
Management of Mittel Rhein AG of Köln, Germany, would like to
reduce the amount of time between when a customer places an order
and when the order is shipped. For the first quarter of operations
during the current year the following data were reported:
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.3 days 16.7 days 3.0 days 1.1 days 4.3 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.7 days Wait time (from order to start of production) 16.5 days Process time 3.1 days Move time 1.1 days Queue time 3.7 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.6 days 16.5 days 2.7 days 1.3 days 4.1 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.5 days 16.4 days 3.0 days 0.7 days 3.7 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) 0.4 days 16.0 days 2.9 days 0.6 days 3.6 days Process time Move time Queue time Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection t ime Wait time (from order to start of production) Process time 0.6 days 16.9 days 3.2 days 0.7 days 4.4 days Move time Queue time Required: 1. Compute the throughput time. (Round your answer...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order tostart of production) Process time Move time 0.2 day 17.0 days 3.2 days 0.5 day 3.7 days Queue time Required: 1.Compute the throughput time. (Round your answer to 1 decimal...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.3 days 15.4 days 3.4 days 1.4 days 4.2 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.7 days Wait time (from order to start of production) 16.6 days Process time 2.9 days Move time 0.8 days Queue time 4.3 days Required: 1. Compute the throughput time. (Round your answer to...