Dear student ,
Please check below answer line by line. Any doubt, please drop me message. I will support immediately.
Thank You !!
Three Jobs are running Job 7650 ,7651 and 7652 | |||||||
First we need to claculate Opening in process | |||||||
Balance of 2 Job ( | |||||||
Job Number | Details | Total Cost$ | |||||
7650 | Balance 1/1( Opening ) | 63,000 | |||||
7651 | Balance 1/1( Opening ) | 48,000 | |||||
Total | Opening balance | 1,11,000 | |||||
Derived other cost | |||||||
Direct Material | |||||||
Job Number | Details | Total Cost$ | |||||
7650 | current Year cost | 32,000 | |||||
7651 | current Year cost | 30,000 | |||||
7652 | current Year cost | 45,000 | |||||
Total | Direct material | 1,07,000 | |||||
Direct Labour | |||||||
Job Number | Details | Total Cost$ | |||||
7650 | current Year cost | 36,000 | |||||
7651 | current Year cost | 40,000 | |||||
7652 | current Year cost | 68,000 | |||||
Total | Direct Labour | 1,44,000 | |||||
Manufacturing Overhead | |||||||
Job Number | Details | Total Cost$ | |||||
7650 | current Year cost | 45,000 | |||||
7651 | current Year cost | 50,000 | |||||
7652 | current Year cost | 85,000 | |||||
Total | Manufacturing Overhead | 1,80,000 | |||||
Now derived completed work cost in relates to two Job order | |||||||
as below : | |||||||
Job Number | Amnt($) | ||||||
7650 | Opening balance | 63,000 | |||||
7651 | Opening balance | 48,000 | |||||
7650 | Direct material | 32,000 | |||||
7651 | Direct material | 30,000 | |||||
7650 | Direct Labour | 36,000 | |||||
7651 | Direct Labour | 40,000 | |||||
7650 | Manufacturing Overhead | 45,000 | |||||
7651 | Manufacturing Overhead | 50,000 | |||||
Total | Complete Work cost | 3,44,000 | |||||
T ACCOUNT OF WORK IN PROGRESS | |||||||
Answer a | WORK IN PROGRESS | ||||||
Details | Amnt($) | Details | Amnt($) | ||||
Opening balance | 1,11,000 | Cost of works completed | 3,44,000 | ||||
Direct Material | 1,07,000 | Balance | 1,98,000 | ||||
Direct Labour | 1,44,000 | ||||||
Manufacturing OH | 1,80,000 | ||||||
Total | 5,42,000 | Total | 5,42,000 | ||||
Work in process and unfinished job value $ 198,000 |
Answer b | Amnt($) | Amnt($) | |||
Manufactured Oh ( point 5 in the Question) | 1,35,000 | ||||
Add | |||||
Other manufacturing OH | |||||
Indirect material | 12,000 | ||||
Indirect Labour | 18,000 | ||||
Depreciation on Factory Machine | 19,500 | 49,500 | |||
Total Manufacturing OH - Actual | 1,84,500 | ||||
Total Manufacturing OH - Applied( calculated as above) | 1,80,000 | ||||
Under applied ( a-b) | 4,500 | ||||
Journal Entry | |||||
Details | Debit($) | Credit($) | |||
Cost of goods sold | 4,500 | ||||
Manufacturing OH | 4,500 | ( As above) |
Answer c | |||
Calculate Gross profit | |||
Amnt($) | Amnt($) | ||
Sales | 4,90,000 | ||
Less | |||
Cost of finished goods | |||
Job 7648 | 93000 | ||
Job 7649 | 62000 | 1,55,000 | |
Job 7651 | Open Bal - $48000 | ||
*( completed Job ) | Material + Labour + Manfg OH- $120000 | 1,72,500 | |
Add - Under applied OH -$4500 | |||
Gross Profit | 1,62,500 |
P20-2B For the year ended December 31, 2012, the job cost shects of Guo Company contained...
For the year ended December 31, 2020, the job cost sheets of Cinta Company contained the following data. Job Number 7640 Explanation Balance 1/1 Current year's costs Balance 1/1 Current year's costs Current year's costs Direct Materials $27,500 33,000 12,100 47,300 63,800 Direct Labor $26,400 39,600 19,800 52,800 60,500 Manufacturing Total Overhead Costs $31,680 $85,580 47,520 120,120 23,760 55,660 63,360 163,460 72,600 196,900 7641 7642 Other data: 1. Raw materials inventory totaled $16.500 on January 1. During the year, $154,000...
For the year ended December 31, 2020, the job cost sheets of Onta Company contained the following data Job Number Direct Materials Direct Labor 7640 Explanation Balance 1/1 Current year's costs Balance 1/1 Current year's costs Current year's costs $29,250 35,100 12,870 50,310 67.860 Manufacturing Overhead $33.000 50,544 25.272 67,292 77,220 $28.080 42,120 21,060 56,160 64,350 7641 Total Costs $91,026 127,764 59,202 173,862 209,430 7642 Other data: 1. 2. 3. 4. 5. 6. Raw materials inventory totaled $17,550 on January...
For the year ended December 31, 2020, the job cost sheets of Pharoah Company contained the following data. Job Number Explanation 7640 Direct Materials $26,500 31,800 11,660 45,580 61,480 Balance 1/1 Current year's costs Balance 1/1 Current year's costs Current year's costs Direct Labor $25,440 38,160 19,080 50,880 58,300 Manufacturing Overhead $30,528 45,792 22,896 61,056 69,960 Total Costs $82,468 115,752 53,636 157,516 189,740 7641 7642 Other data: 1. Raw materials inventory totaled $15,900 on January 1. During the year, $148,400...
For the year ended December 31, 2020, the job cost sheets of Cinta Company contained the following data. Job Number Explanation Direct Materials Direct Labor Manufacturing Overhead Total Costs 7640 Balance 1/1 $27,000 $25,920 $31,104 $84,024 Current year’s costs 32,400 38,880 46,656 117,936 7641 Balance 1/1 11,880 19,440 23,328 54,648 Current year’s costs 46,440 51,840 62,208 160,488 7642 Current year’s costs 62,640 59,400 71,280 193,320 Other data: 1. Raw materials inventory totaled $16,200 on January 1. During the year, $151,200...
P2-2A For the year ended December 31, 2017, the job cost sheets of Cinta Company con- tained the following data. Prepare entries i cost system and income stateme Job 7640 Balance 1/1 7641 Balance 1/1 Direct Direct Manufacturing Total (L01,2,3,4, Number Explanation Materials Labor Overhead $ 77,800 109,200 50,600 148,600 179,000 $25,000 $24,000 Current year's costs 30,000 36,000 $24,000280Costs 11,000 18,000 Current year's costs 43,000 48,000 43,200 21,600 57,600 66,000 7642 Current year's costs58,000 55,000 Other data: f raw 1....
Question 4 of 5 < 0.57/4 For the year ended December 31, 2020, the job cost sheets of Cinta Company contained the following data. Job Number 7640 Explanation Balance 1/1 Current year's costs Balance 1/1 Current year's costs Current year's costs Direct Materials $30,000 36,000 13.200 51.600 69,600 Direct Labor $28,800 43,200 21,600 57,600 66.000 Manufacturing Overhead $34.560 51,840 25.920 69,120 79,200 Total Costs $93,360 131,040 60,720 178,320 214,800 7641 7642 Ac Other data: QL ACCE 1. 2. 3 Raw...
SIGNMENT For the year ended December 31, 2017, the job cost sheets of Coronado Company contained the following data Explanation MaterialsLabor Overhead Balance 1/1 Current years costs Balance 1/1 Current year's costs Current year's costs $30,000 $28,800 36,000 43,200 13,200 21,600 51,600 57,600 69,600 66,000 $34,560 $93,360 51,840 131,040 25,920 60,720 69,120 178,320 79,200 214,800 7641 7642 1. Raw materials inventory totaled $18,000 on January 1. During the year, $168,000 of raw materials were purchased on account. Factory labor incurred...
*Problem 20-02A a-c For the year ended December 31, 2020, the job cost sheets of Pharoah Company contained the following data. Job Number 7640 Explanation Direct Materials Direct Labor Manufacturing Overhead Total Costs 7641 Balance 1/1 Current year's costs Balance 1/1 Current year's costs Current year's costs $26,500 31,800 11,660 45,580 61,480 $25,440 38,160 19,080 50,880 58,300 $30,528 45,792 22,896 61,056 69,960 $82,468 115,752 53,636 157,516 189,740 7642 Other data: 1. Raw materials inventory totaled $15,900 on January 1. During...
Question 9 For the year ended December 31, 2020, the job cost sheets of Devoe Company contained the following data: Direct Direct Manufacturing Total Job Number Explanation Materials Labour Overhead Costs 7640 Balance 1/1 $25,700 $24,800 $29,700 $80,200 Current year's costs 30,900 35,600 43,200 109,700 7641 Balance 1/1 11,800 18,200 22,300 52,300 Current year's costs 43,600 48,300 58,000 149,900 7642 Current year's costs 48,500 55,700 66,100 170,300 Other data: 1. Raw materials inventory totalled $15,900 on January 1. During the...
Question 9 For the year ended December 31, 2020, the job cost sheets of DeVoe Company contained the following data: Direct Materials Direct Labour Total Costs Job Number Explanation 7640 Balance 1/1 Current year's costs Balance 1/1 $25,100 30,500 11,800 43,600 48,300 7641 Manufacturing Overhead $28,900 43,900 22,100 57,900 66,800 $24,900 35,400 18,800 48,300 55,000 $78,900 109,800 52,700 149,800 170,100 Current year's costs Current year's costs 7642 Other data: 1. Raw materials inventory totalled $15,100 on January 1. During the...