Question

The following data relate to direct labor costs for February: Actual costs 7,700 hours at $14...

The following data relate to direct labor costs for February:

Actual costs 7,700 hours at $14
Standard costs 7,000 hours at $15


What is the direct labor rate variance?

Group of answer choices

$7,700 favorable

$7,000 favorable

$7,700 unfavorable

$7,000 unfavorable

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer : $ $7,700 Favorable

Direct Labor Rate Variance = ( Standard Rate - Actual Rate) * Actual Hours

Direct Labor Rate Variance = (15-14)*7700 = $7,700 Favorable (Answer)

Add a comment
Know the answer?
Add Answer to:
The following data relate to direct labor costs for February: Actual costs 7,700 hours at $14...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT