Question

The following data relate to direct labor costs for the current period: Standard costs Actual costs 36,000 hours at $22.00 35
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Standard Rate Direct labour time variances (Standard hours - Actual hours) x = (36,000 hrs – 35,000 hrs) * $22 = $ 22,000 Fav

Add a comment
Know the answer?
Add Answer to:
The following data relate to direct labor costs for the current period: Standard costs Actual costs...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT