Question

[The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable...

[The following information applies to the questions displayed below.]

Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows:

Direct material: 6 pounds at $8.00 per pound $ 48.00
Direct labor: 4 hours at $17 per hour 68.00
Variable overhead: 4 hours at $4 per hour 16.00
Total standard variable cost per unit $ 132.00

The company also established the following cost formulas for its selling expenses:

Fixed Cost per Month Variable Cost per Unit Sold
Advertising $ 370,000
Sales salaries and commissions $ 440,000 $ 29.00
Shipping expenses $ 20.00

The planning budget for March was based on producing and selling 19,000 units. However, during March the company actually produced and sold 24,000 units and incurred the following costs:

  1. Purchased 160,000 pounds of raw materials at a cost of $7.20 per pound. All of this material was used in production.
  2. Direct-laborers worked 72,000 hours at a rate of $18.00 per hour.

  3. Total variable manufacturing overhead for the month was $336,960.

  4. Total advertising, sales salaries and commissions, and shipping expenses were $374,000, $540,000, and $285,000, respectively.

rev: 11_16_2018_QC_CS-146879

3. What is the materials price variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Input the amount as a positive value.)

4. If Preble had purchased 187,000 pounds of materials at $7.20 per pound and used 160,000 pounds in production, what would be the materials quantity variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Input the amount as a positive value.)

5. If Preble had purchased 187,000 pounds of materials at $7.20 per pound and used 160,000 pounds in production, what would be the materials price variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Input the amount as a positive value.)

7. What is the direct labor efficiency variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Input the amount as a positive value.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

3) Material price variance = (8-7.20)*160000 = 128000 F

4) Material quantity variance = (24000*6-160000)*8 = 128000 U

5) Material price variance = (8-7.20)*187000 = 149600 F

7) Direct labor efficiency variance = (24000*4-72000)*17 = 408000 F

Add a comment
Know the answer?
Add Answer to:
[The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information [The following information applies to the questions displayed below.] Preble Company manufactures one product....

    Required information [The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 5 pounds at $8.00 per pound $ 40.00 Direct labor: 3 hours at $15 per hour 45.00 Variable overhead: 3 hours at $9 per hour 27.00 Total standard variable cost per unit $ 112.00 The company also established the following...

  • [The following information applies to the questions displayed below.] Preble Company manufactures one product. Its varia...

    [The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 6 pounds at $8.00 per pound $ 48.00 Direct labor: 4 hours at $17 per hour 68.00 Variable overhead: 4 hours at $4 per hour 16.00 Total standard variable cost per unit $ 132.00 The company also established the following cost formulas...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct materials: 5 pounds at $8.00 per pound Direct labor: 2 hours at $14 per hour Variable overhead: 2 hours at $5 per hour Total standard cost per unit $ 40.00 28.00 10.00 $78.00 The planning budget for March was based on producing and selling 25,000 units. However, during March the company actually...

  • Preble Company manufactures one product

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows:Direct material: 6 pounds at $8.00 per pound$48.00Direct labor: 3 hours at $14 per hour42.00Variable overhead: 3 hours at $5 per hour15.00Total standard variable cost per unit$105.00The company also established the following cost formulas for its selling expenses:Fixed Cost per MonthVariable Cost per Unit SoldAdvertising$250,000Sales salaries and commissions$200,000$17.00Shipping expenses$8.00The planning budget for March was...

  • The following information applies to the questions displayed below Preble Company manufactures one product. Its variable...

    The following information applies to the questions displayed below Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor hours and its standard cost card per unt is as follows Direct materials 6 pounds at 58 per pound Direct labor: 3 hours at $14 per hour Variable overhend 3 hours at $5 per hour Total standard cost per unit s 48 42 $ 105 The planning budget for March was based on producing...

  • Required information [The following information applies to the questions displayed below) Preble Company manufactures one product....

    Required information [The following information applies to the questions displayed below) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg Direct labour: 3 hours at $14 per hour Variable overhead: 3 hours at $5 per hour Total standard cost per unit $ 48.ee 42.00 15.00 $ 105.00 The company planned to produce and sell 19,000...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct materials: 5 pounds at $8.00 per pound Direct labor: 2 hours at $14 per hour Variable overhead: 2 hours at $5 per hour Total standard cost per unit $ 40.00 28.00 10.00 $78.00 The planning budget for March was based on producing and selling 25,000 units. However, during March the company actually...

  • Required information [The following information applies to the questions displayed below.] Preble Company manufactures one product....

    Required information [The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 5 pounds at $8.00 per pound $ 40.00 Direct labor: 2 hours at $14 per hour 28.00 Variable overhead: 2 hours at $5 per hour 10.00 Total standard variable cost per unit $ 78.00 The company also established the following...

  • Required information [The following information applies to the questions displayed below.] Preble Company manufactures one product....

    Required information [The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 5 pounds at $8.00 per pound $ 40.00 Direct labor: 2 hours at $14 per hour 28.00 Variable overhead: 2 hours at $5 per hour 10.00 Total standard variable cost per unit $ 78.00 The company also established the following...

  • Required information [The following information applies to the questions displayed below.) Preble Company manufactures one product....

    Required information [The following information applies to the questions displayed below.) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labdr-hours and its standard cost card per unit is as follows: Direct materials: 5 pounds at $8.00 per pound Direct labor: 2 hours at $14 per hour Variable overhead: 2 hours at 55 per hour Total standard cost per unit $40.00 28.se 10.90 $78.90 The planning budget for March was based on producing...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT