Question

A manufactured product has the following information for August. Actual Direct materials Direct labor Overhead Units manufactCompute the total budgeted cost for production in August. Total budgeted costCompute the total cost variance for August. (Indicate the effect of each variance by selecting for favorable, unfavorable, an

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Direct materials (2*2.50) 5
Direct labor (0.5*16) 8
Overhead (12*0.5) 6
Total 19

.

Total budgeted cost = 19*12,000

= 228,000

.

Cost variance = 228,000 - 225,400

= 2600 Favourable

Comment if you face any issues

Add a comment
Know the answer?
Add Answer to:
A manufactured product has the following information for August. Actual Direct materials Direct labor Overhead Units...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A manufactured product has the following information for August. Standard Actual Direct materials 2 lbs. per...

    A manufactured product has the following information for August. Standard Actual Direct materials 2 lbs. per unit @ $4.00 per lb. Direct labor 0.5 hours per unit @ $28 per hour Overhead $30 per direct labor hour Units manufactured 12,600 Total manufacturing costs $ 460,400 (1) Compute the standard cost per unit. (2) Compute the total budgeted cost for production in August. (3) Compute the total cost variance for August. (Indicate the effect of each variance by selecting for favorable,...

  • A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured...

    A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard 6 lbs. @ $8 per lb. 2 hrs. @ $16 per hr. 2 hrs. @ $12 per hr. Actual 48,500 lbs. @ $8.10 per lb. 15,700 hrs. @ $16.50 per hr. $198,000 8,000 (1) Compute the standard cost per unit. (2) Compute the total cost variance for June. Complete this question by entering your answers in the tabs below. Required 1 Required 2...

  • Exercise 21-7 Standard unit cost; cost variances LO P2 A manufactured product has the following information...

    Exercise 21-7 Standard unit cost; cost variances LO P2 A manufactured product has the following information for August. Direct materials Direct labor Overhead Units manufactured Total manufacturing costs Standard 2 lbs. per unit @ $7.50 per lb. 0.5 hours per unit @ $56 per hour $72 per direct labor hour 14.00 $1.184,400 (1) Compute the standard cost per unit. (2) Compute the total budgeted cost for production in August (3) Compute the total cost variance for August. (Indicate the effect...

  • A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured...

    A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. esper lb.) (2 hrs. @ $16 per hr.) (2 hrs. $12 per hr.) Actual 47,200 lbs. @ $7.20 per lb. 15,300 hrs. $16.40 per hr. $ 193,600 7,800 (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute the total cost variance for June. Indicate whether the cost variance is favorable or unfavorable. Total cost varianco.

  • A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured...

    A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard 6 lbs. @ $8 per lb. 2 hrs. @ $16 per hr. 2 hrs. @ $12 per hr. Actual 48,500 lbs. @ $8.10 per lb. 15,700 hrs. @ $16.50 per hr. $198,000 8,000 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of each variance by selecting for favorable, unfavorable, and no variance. Round "Cost per unit"...

  • need help thanks A manufactured product has the following information for August Atual Standard 2 lbs....

    need help thanks A manufactured product has the following information for August Atual Standard 2 lbs. per unit $7.00 per lb. 0.5 hours per unit 552 per hour $66 per direct labor hour Units manufactured Total manufacturing costs $1,005, 400 (1) Compute the standard cost per unit (2) Compute the total budgeted cost for production in August (3) Compute the total cost variance for August. (Indicate the effect of each variance by selecting for favorable, unfavorable, and no variance) Complete...

  • HOW DO I CALCULATE? A manufactured product has the following information for June. Direct materials Direct...

    HOW DO I CALCULATE? A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard 5 lbs. @ $7 per lb. 3 hrs. @ $16 per hr. 3 hrs. @ $12 per hr. Actual 42,500 lbs. @ $7.20 per lb. 24,900 hrs. @ $16.40 per hr. $308,000 8,400 (1) Compute the standard cost per unit. (2) Compute the total cost variance for June. Complete this question by entering your answers in the tabs below....

  • A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured...

    A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. @ $7 per lb.) (2 hrs. $16 per hr.) (2 hrs. $12 per hr.) Actual 47,200 lbs. @ $7.20 per lb. 15,300 hrs. $16.40 per hr. $ 193,600 7,800 Compute the direct labor rate variance and the direct labor efficiency variance. Indicate whether each variance is favorable or unfavorable. AH = Actual Hours SH = Standard Hours AR = Actual Rate...

  • A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured...

    A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (5 lbs. @ $8 per lb.) (2 hrs. @ $17 per hr.) (2 hrs. @ $13 per hr.) Actual 36,500 lbs. @ $8.10 per lb. 14,200 hrs. @ $17.50 per hr. $193,700 7,200 Compute the direct labor rate variance and the direct labor efficiency variance. Indicate whether each variance is favorable or unfavorable. AH - Actual Hours SH - Standard Hours AR -...

  • A manufactured product has the following information for June. Standard Actual Direct materials (6 lbs. @...

    A manufactured product has the following information for June. Standard Actual Direct materials (6 lbs. @ $8 per lb.) 50,400 lbs. @ $8.20 per lb. Direct labor (3 hrs. @ $16 per hr.) 24,700 hrs. @ $16.50 per hr. Overhead (3 hrs. @ $11 per hr.) $ 279,800 Units manufactured 8,300 1) Compute the standard cost per unit and the total cost variance for June. Indicate whether the cost variance is favorable or unfavorable. Direct materials Direct labor Overhead Total...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT