Question

Exercise 07-4 Manufacturing: Direct materials budget LO P1 Zira Co. reports the following production budget for the next four

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Material Budget = Material needed for Production + Ending inventory - Beginning inventory

Zira co

Direct Material Budget

Particulars April May June July
Budgeted production 574 615 607 587
Material per unit 5 5 5 5
Material needed for production 2870 3075 3035 2935
Budgeted ending inventory (40% of next Month's production needs) 1230 1214 1174
Total material requirements 4100 4289 4209
Beginning inventory 1148 1230 1214
Materials to be purchased 2952 3059 2995
Cost per lb 4 4 4
Total budgeted direct Material cost 10368 12236 11980
Add a comment
Know the answer?
Add Answer to:
Exercise 07-4 Manufacturing: Direct materials budget LO P1 Zira Co. reports the following production budget for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 07-4 Manufacturing: Direct materials budget LO P1 Zira Co. reports the following production budget for...

    Exercise 07-4 Manufacturing: Direct materials budget LO P1 Zira Co. reports the following production budget for the next four months April 536 Production (units) May 590 June 568 July 548 Each finished unit requires six pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month's production needs. Beginning raw materials inventory for April was 965 pounds. Assume direct materials cost $4 per pound Prepare a direct materials budget...

  • Please work the problem attached. Exercise 07-4 Manufacturing: Direct materials budget LO P1 Zira Co. reports th...

    Please work the problem attached. Exercise 07-4 Manufacturing: Direct materials budget LO P1 Zira Co. reports the following production budget for the next four months. April May 670 June July Production (units) 642 676 656 Each finished unit requires four pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month's production needs. Beginning raw materials inventory for April was 770 pounds. Assume direct materials cost $5 per pound....

  • Exercise 20-4 Manufacturing: Direct materials budget LO P1 Zira Co. reports the following production budget for...

    Exercise 20-4 Manufacturing: Direct materials budget LO P1 Zira Co. reports the following production budget for the next four months. April May June July Production (units) 624 665 657 637 Each finished unit requires five pounds of raw materials and the company wants to end each month with raw materials inventory equal to 20% of next month’s production needs. Beginning raw materials inventory for April was 624 pounds. Assume direct materials cost $6 per pound. Prepare a direct materials budget...

  • Zira Co. reports the following production budget for the next four months. April 676 May 730 July 688 June Product...

    Zira Co. reports the following production budget for the next four months. April 676 May 730 July 688 June Production (units) 708 Each finished unit requires six pounds of raw materials and the company wants to end each month with raw materials inventory equal to 40% of next month's production needs. Beginning raw materials inventory for April was 1,622 pounds. Assume direct materials cost $4 per pound. Prepare a direct materials budget for April, May, and June. (Round your intermediate...

  • Zira Co. reports the following production budget for the next four months. Production (units) April 455...

    Zira Co. reports the following production budget for the next four months. Production (units) April 455 May 570 June 560 July 540 Each finished unit requires five pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month's production needs. Beginning raw materials inventory for April was 663 pounds. Assume direct materials cost $4 per pound. Prepare a direct materials budget for April, May, and June. ZIRA CO. Direct...

  • Zira Co. reports the following production budget for the next four months. Production (units) April 632...

    Zira Co. reports the following production budget for the next four months. Production (units) April 632 May 662 June 666 July 646 Each finished unit requires four pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month's production needs. Beginning raw materials inventory for April was 758 pounds. Assume direct materials cost $4 per pound Prepare a direct materials budget for April, May, and June (Round your intermediate...

  • Zira Co. reports the following production budget for the next four months. Production (units) April 584...

    Zira Co. reports the following production budget for the next four months. Production (units) April 584 May 625 June 617 July 597 Each finished unit requires five pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month's production needs. Beginning raw materials inventory for April was 876 pounds. Assume direct materials cost $5 per pound Prepare a direct materials budget for April, May, and June. (Round your intermediate...

  • 4 0 Zira Co. reports the following production budget for the next four months. April 692...

    4 0 Zira Co. reports the following production budget for the next four months. April 692 June May 720 July 706 Production (units) 726 Each finished unit requires six pounds of raw materials and the company wants to end each month with raw materials inventory equal to 20% of next month's production needs. Beginning raw materials inventory for April was 830 pounds. Assume direct materials cost $3 per pound Assignments ct materials budget for April, May, and June. (Round your...

  • Zira Co. reports the following production budget for the next four months. Production (units) April 624...

    Zira Co. reports the following production budget for the next four months. Production (units) April 624 May 665 June 657 July 637 Each finished unit requires four pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month's production needs. Beginning raw materials inventory for April was 749 pounds. Assume direct materials cost $3 per pound. Prepare a direct materials budget for April, May, and June. (Round your intermediate...

  • 1 Zira Co. reports the following production budget for the next four months. April July May...

    1 Zira Co. reports the following production budget for the next four months. April July May June Production (units) 572 600 606 586 10 polnts Each finished unit requires five pounds of raw materials and the company wants to end each month with raw materials inventory equal to 20% of next month's production needs. Beginning raw materials inventory for April was 572 pounds. Assume direct materials cost $6 per pound. Prepare a direct materials budget for April, May, and June....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT