Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3,LO2-4]
Solution 1a to 1d:
Computation of Plantwide predetermined Overhead Rate | ||
Fixed Manufacturing Overhead costs | $9,10,000 | |
Variable
Manufacturing Overhead cost [(20000*$3) + (30000*$1)] |
$90,000 | |
Total Estimated Overhead costs (a) | $10,00,000 | |
/Total Estimated Machine Hours (b) | 50000 | |
Plantwide Overhead Rate (a/b) | $20.00 | |
Computation of Total Manufacturing Costs | ||
Job D-70 | Job C-200 | |
Direct Material Costs | $7,00,000 | $5,50,000 |
Direct Labor Costs | $3,60,000 | $4,00,000 |
Manufacturing Overhead costs (Total Machine Hours*$20) |
$4,00,000 | $6,00,000 |
Total Manufacturing Costs | $14,60,000 | $15,50,000 |
Computation of Bid Prices | ||
Job D-70 | Job C-200 | |
Total Manufacturing Costs | $14,60,000 | $15,50,000 |
Bid price (Total Manufacturing Costs*150%) | $21,90,000 | $23,25,000 |
Computation of Delph's Cost of Goods sold | ||
Total Manufacturing Costs of Job D-70 | $14,60,000 | |
Total Manufacturing Costs of Job C-200 | $15,50,000 | |
Total Cost of Goods sold | $30,10,000 |
Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3,LO2-4] Part 1 of...
Required information Exercise 2-15 (Algo) Plantwide and Departmental Predetermined Overhead Rates; Job Costs (LO2-1, LO2-2, LO2-3, LO2-4) [The following information applies to the questions displayed below.) Delph Company uses a job-order costing system and has two manufacturing departments-Molding and Fabrication The company provided the following estimates at the beginning of the year Molding Fabrication 24, eee 33,eee $740, eee $ 220, eee $ 4.00 $ 1.ee Total 57, eee $960, eee Machine-hours Fixed manufacturing overhead cost Variable manufacturing overhead cost...
Exercise 2-15 (Static) Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4) [The following information applies to the questions displayed below) Delph Company uses a job-order costing system and has two manufacturing departments-Molding and Fabrication. The company provided the following estimates at the beginning of the year. Machine-hours Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour Molding 20,800 $ 700,000 $ 3.00 Fabrication 30,000 $ 210,000 $ 1.00 Total 50,000 $ 918,800 During the year,...
Exercise 2-15 (Algo) Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4] (The following information applies to the questions displayed below.] Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company provided the following estimates at the beginning of the year: Molding Fabrication Machine-hours 22,000 33,000 55,000 Fixed manufacturing overhead cost $ 740,000 $ 240,000 $980,000 Variable manufacturing overhead cost per machine-hour $ 5.00 $ Total 2.00 During the year, the...
Required information Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2- 1, LO2-2, LO2-3, LO2-4) The following information applies to the questions displayed below.) Delph Company uses a job-order costing system and has two manufacturing departments-Molding and Fabrication. The company provided the following estimates at the beginning of the year: Machine-hours Fixed manufacturing overhead costs Variable manufacturing overhead cost per machine-hour Molding Fabrication 21,000 31,000 $ 730,000 $ 300,000 $ 5.20 $ 5.20 Total 52,000 $1,030,000 During the...
Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4] [The following information applies to the questions displayed below.] Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company provided the following estimates at the beginning of the year: Molding Fabrication Total Machine-hours 33,000 43,000 76,000 Fixed manufacturing overhead costs $ 800,000 $ 200,000 $ 1,000,000 Variable manufacturing overhead cost per machine-hour $ 5.70 $ 5.70 During the...
Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4] [The following information applies to the questions displayed below.] Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company provided the following estimates at the beginning of the year: Molding Fabrication Total Machine-hours 30,000 40,000 70,000 Fixed manufacturing overhead costs $ 760,000 $ 210,000 $ 970,000 Variable manufacturing overhead cost per machine-hour $ 5.30 $ 5.30 During the...
Exercise 2-15 (Algo) Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4] [The following information applies to the questions displayed below.] Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company provided the following estimates at the beginning of the year: Molding Fabrication Total Machine-hours 24,000 32,000 56,000 Fixed manufacturing overhead cost $ 740,000 $ 200,000 $ 940,000 Variable manufacturing overhead cost per machine-hour $ 3.00 $ 1.50 During...
Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3,LO2-4] Required Information Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3,LO2-4] [The following information applies to the questions displayed below.) Delph Company uses a job-order costing system and has two manufacturing departments-Molding and Fabrication. The company provided the following estimates at the beginning of the year: Machine-hours Fixed manufacturing overhead costs Variable manufacturing overhead cost per machine-hour Molding 20,000 $ 700,000 $ 3.00...
Required information Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4) (The following information applies to the questions displayed below.) Delph Company uses a job-order costing system and has two manufacturing departments-Molding and Fabrication The company provided the following estimates at the beginning of the year: Machine-hours Fixed manufacturing overhead costs Variable manufacturing overhead cost per machine-hour Molding Fabrication 21,000 31,000 $ 730,000 $300,000 $ 5.20 $ 5.20 Total 52,000 $1,030,000 During the year, the...
this is all one problem Required information Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3,LO2-4) (The following information applies to the questions displayed below.) Delph Company uses a job-order costing system and has two manufacturing departments-Molding and Fabrication. The company provided the following estimates at the beginning of the year: Machine-hours Fixed manufacturing overhead costs Variable manufacturing overhead cost per machine-hour Molding Fabrication 20,000 30,000 $ 700,000 $ 210,000 $ 3.00 $ 1.00 Total 50,000...