Question

Exercise 24-09 a-e (Part Level Submission) You have been given the following information about the production of Usher Co., a(a) How many units were produced during the period? (Round answers to 0 decimal places, e.g. 125.) Number of units (b) How ma

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Number of units produced = Total Standard cost/Standard cost per unit Number of units produced = $410,000/$20 Number of units

Standard hours allowed = 20,500*0.80 = 16,400 hours Direct labor efficiency variance = (Actual hours-Standard hours) Standar

Add a comment
Know the answer?
Add Answer to:
Exercise 24-09 a-e (Part Level Submission) You have been given the following information about the production...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You have been given the following information about the production of Usher Co., and are asked...

    You have been given the following information about the production of Usher Co., and are asked to provide the plant manager with information for a meeting with the vice president of operations. Standard Cost Card Direct materials (5 pounds at $4 per pound) $20.00 Direct labor (0.80 hours at $10) 8.00 Variable overhead (0.80 hours at $3 per hour) 2.40 Fixed overhead (0.80 hours at $7 per hour) 5.60 $36.00 The following is a variance report for the most recent...

  • You have been given the following information about the production of Usher Co., and are asked...

    You have been given the following information about the production of Usher Co., and are asked to provide the plant manager with information for a meeting with the vice president of operations. Standard Cost Card Direct materials (8 pounds at $5 per pound) $40.00 Direct labor (0.70 hours at $10) 7.00 Variable overhead (0.70 hours at $3 per hour) 2.10 Fixed overhead (0.70 hours at $7 per hour) 4.90 $54.00 The following is a variance report for the most recent...

  • You have been given the following information about the production of Usher Co., and are asked to provide the plant mana...

    You have been given the following information about the production of Usher Co., and are asked to provide the plant manager with information for a meeting with the vice president of operations. Standard Cost Card Direct materials (6 pounds at $5 per pound) $30.00 Direct labor (0.70 hours at $10) 7.00 Variable overhead (0.70 hours at $4 per hour) 2.80 Fixed overhead (0.70 hours at $9 per hour) 6.30 $46.10 The following is a variance report for the most recent...

  • You have been given the following information about the production of Usher Co., and are asked to provide the plant man...

    You have been given the following information about the production of Usher Co., and are asked to provide the plant manager with information for a meeting with the vice president of operations. Direct materials (8 pounds at $4 per pound) Direct labor (0.70 hours at $10) Variable overhead (0.70 hours at $5 per hour) Fixed overhead (0.70 hours at $7 per hour) Standard Cost Card $32.00 7.00 3.50 4.90 $47.40 The following is a variance report for the most recent...

  • Exercise 24-09

    Exercise 24-09You have been given the following information about the production of Usher Co., and are asked to provide the plant manager with information for a meeting with the vice president of operations.Standard Cost CardDirect materials (7 pounds at $5 per pound) $35.00Direct labor (0.80 hours at $10) 8.00Variable overhead (0.80 hours at $5 per hour) 4.00Fixed overhead (0.80 hours at $7 per hour) 5.60$52.60The following is a variance report for the most recent period of operations.VariancesCostsTotal Standard CostPriceQuantityDirect materials...

  • You have been given the following information about the production of Gamma Co: Problem 12.40A a-h...

    You have been given the following information about the production of Gamma Co: Problem 12.40A a-h You have been given the following information about the production of Gamma Co., and are asked to provide the plant manager with information for a meeting with the vice-president of operations: Direct materials (5.00 kg at $3.00 per kilogram) Direct labour (0.50 hours at $4.00) Variable overhead (0.50 hours at $3.00 per hour) Fixed overhead (0.50 hours at $6 per hour) Standard Cost Card...

  • Vitex, Inc, manufactures a popular consumer product and it has provided the following data excerpts from...

    Vitex, Inc, manufactures a popular consumer product and it has provided the following data excerpts from its standard cost system: Inputs Direct materials Direct labor Variable manufacturing overhead Total standard cost per unit (1) Standard Quantity or Hours 2.30 pounds 1.00 hours 1.00 hours (2) Standard Price or Rate $16.80 per pound $15.00 per hour $ 9.50 per hour Standard Cost (1) x (2) $38.64 $15.80 $ 9.5e $63.94 Direct materials Direct labor Variable manufacturing overhead Total Variances Reported Standard...

  • Vitex, Inc. manufactures a popular consumer product and it has provided the following data excerpts from...

    Vitex, Inc. manufactures a popular consumer product and it has provided the following data excerpts from its standard cost system: Inputs Direct materials Direct labor Variable manufacturing overhead Total standard cost per unit Quantity or Hours 2.20 pounds 1.00 hours 1.00 hours Price Or Rate $16.70 per pound $15.90 per hour $ 9.20 per hour Cost (1) (2) $36.74 $15.90 $ 9.20 $61.84 Direct materials Direct labor Variable manufacturing overhead Total Variances Reported Standard Price Quantity or Cost. Or Rate...

  • Vitex, Inc. manufactures a popular consumer product and it has provided the following data excerpts from...

    Vitex, Inc. manufactures a popular consumer product and it has provided the following data excerpts from its standard cost system: Inputs (1) Standard Quantity or Hours (2) Standard Price or Rate Standard Cost (1) × (2) Direct materials 2.10 pounds $ 16.30 per pound $ 34.23 Direct labor 1.00 hours $ 15.80 per hour $ 15.80 Variable manufacturing overhead 1.00 hours $ 9.30 per hour $ 9.30 Total standard cost per unit $ 59.33 Total Variances Reported Standard Cost* Price...

  • Standard Standard Price (1) Standard Quantity or Hours 2.30 pounds 1.ee hours 1.00 hours or Rate...

    Standard Standard Price (1) Standard Quantity or Hours 2.30 pounds 1.ee hours 1.00 hours or Rate Inputs Direct materials Direct labor Variable manufacturing overhead (1) X (2) $39.10 $17.00 per pound $16.10 per hour $ 9.20 per hour Total standard cost per unit Direct materials Direct labor Variable manufacturing overhead Total Variance Reported Standard Price Quantity or Cost or Rate Efficiency 5782,000 $ 13,920 F $ 34,000 U $322,000 $ 4,200 $ 16,100 U $184,000 $4,700 F S "Applied to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT